Professional Documents
Culture Documents
The Effect of Procurement Management Practice On The Project Performance The Case of CBE
The Effect of Procurement Management Practice On The Project Performance The Case of CBE
MARY’S UNIVERSITY
SCHOOL OF GRADUATE STUDIES
ADDIS ABABA
BY
FREWEYNI BELAY
JULY, 2019
ADDIS ABABA, ETHIOPIA
ST. MARY’S UNIVERSITY
SCHOOL OF GRADUATE STUDIES
JULY, 2019
ADDIS ABABA, ETHIOPIA
ST. MARY’S UNIVERSITY
SCHOOL OF GRADUATE STUDIES
I declare that this thesis entitled “The Effect of Procurement Management Practice on the
Project Performance: The Case of Commercial Bank of Ethiopia Addis Ababa” is my
original work. This thesis has not been presented for any other university and is not concurrently
submitted in candidature of any other degree, and that all sources of material used for the thesis
have been duly acknowledged.
Candidate:
This thesis has been submitted to St. Mary’s University, School of Graduate studies for
examination with my approval as a university advisor.
___________________ ____________
Advisor Signature
Table of Contents
Acknowledgments............................................................................................................................................ I
Abstract ........................................................................................................................................................... V
INTRODUCTION .......................................................................................................................................... 1
2 .1 Introduction .............................................................................................................................................. 6
CHAPTER FOUR......................................................................................................................................... 22
Above all and for most, I would like to thank the Almighty God for helping me accomplish this
study. Next, I am deeply indebted to the professional staff of procurement of Commercial Bank of
Ethiopia who helped me so much that none of this would have been possible if it were not for
their intellectual and emotional support.
I would especially like to acknowledge, my advisor Dr. Temesgen Belayneh (PhD) for his
continuous assistance. An acknowledgement of this kind would not be complete without an
expression of profound gratitude towards my work colleagues, friends and my whole family for
every kind of support they provide me with.
I
LIST OF ACRONYM
II
List of Tables
Table 3.1: Measurement of the dependent and independent variables………………………19
Table 3.2: Reliability Test……………………………………………………………………20
Table 4.1: Characteristics of the Respondents …………………………………………………21
Table 4.2: The extent to which Need Assessment Practices Affect Project Performance…23
Table 4.3: The Effect of Supplier Sourcing Practices on Project Performance…………….24
Table 4.4: The Effect of Contract Management Practices on Project Performance………..25
III
List of Figures
IV
Abstract
This project studies the effect of procurement management practice on the project performance
the case of commercial bank of Ethiopia where the concept of procurement management comes a
long way in the practice of project undertaking. Thus, the researcher came up with a major
research gap which the effectiveness of procurement practice on the project’s performance. In
addition, the researcher has further assessed the effectiveness of procurement practice in terms of
Inventory Management practice, Need Assessment, Supplier sourcing and Contract Management.
The methodology was designed as quantitative approach since the data which was gathered
through questionnaire is quantitative (numerical). Moreover, this study adopts explanatory
research design. In this research design, empirical data are collected for testing the hypotheses.
The researcher employs the test-retest reliability test, where the consistency of the questionnaire
is evaluated over time by Cronbach’s alpha (Using SPSS version 22) and the researcher used
Regression Analysis to analyze data presentations. Its general objective included to find out the
effect of need assessment, supplier sourcing processes, contract management and inventory
management on project performance of CBE. Procurement functions such as need assessment,
supplier sourcing, contract management and inventory management play a very important role in
the execution of projects. The study recommends that CBE should include the four procurement
functions i.e. need assessment, supplier sourcing, contract management and inventory
management in their implementation of projects.
Key words, procurement management, CBE, project performance, need assessment, contract
management.
V
CHAPTER ONE
INTRODUCTION
3|Page
1.6 Research Hypotheses
The following are the research hypotheses:
H01: Need Assessment does not have a significant effect on Project Performance of CBE.
H02: Supplier Management does not have a significant effect on Project Performance of CBE.
H03: Contract management level involvement does not have a significant effect on Project
Performance of CBE.
H04: Inventory management does not have a significant effect on Project Performance of CBE
4|Page
1.9 Organization of the Study
This study consists of five distinct chapters. Chapter one deals with the back ground, statement
of the problem, research objective, significance of the study and scope of the research. Chapter
two focuses on relevant literature review with the topic, differences and similarities as well as
arguments of different writers regarding procurement management would be dealt under this
chapter. Third chapter presents methodologies used in conducting the study and description of
the study area, research design, data sources, target populations, data collection instruments,
data collection procedures, methods of data analysis and validity & reliability of the instrument.
Chapter four includes the result and discussion & the study of data collected and analyzed using
the data analysis tools. Finally, the last chapter shows the summary, conclusion and
recommendation.
5|Page
CHAPTER TWO
2 .1 Introduction
The chapter provides information from publications on topics related the study. It examines
what various scholars and authors have said about the concept of procurement functions. In this
chapter, the concept of procurement functions including need assessment, supplier sourcing
process, contract management and inventory management on project performance are covered.
Theoretical review on procurement functions in organizations and the effects on project are also
emphasized.
6|Page
expensive to verify whether agents have appropriately performed the delegated work, or rather
moral hazard. The ethical and moral issues that arise from the manner donor underline the
manner in which a project should be implemented. This problem also arises when it becomes
difficult or expensive to verify that agents have the expertise to perform the delegated work (i.e.
adverse selection) that they claim to have. A risk-sharing problem arises when principals and
agents have different attitudes towards risk that cause disagreements about actions to be taken
(Xingxing 2012).
According to the theory, party (the principle) contracts another (the agent) to perform some
services on their behalf. The principle passes on decision making authority to the agent. The
difference between buyers and suppliers will result in the two parties concerning themselves
only with their self-interests (Xingxing 2012).
Agency theory determines how procurement managers execute procurement practices on behalf
of donor funding agencies. Existence of poor principle agent relationship leads to low level of
top management commitment and this also affects the relationship between institutions and the
suppliers. Existence of conflict of interest amongst the agents leads to execution of procurement
practices against the standard policies which leads to waste of time in tendering and cancelling
of tender advertised and loss of procurement funds.
The public procurement Act requires all stakeholders to assess the processes involved in the
Procurement and to know the efficiency and reliability in the procurement processes.
Importantly is to recognize the flaws and challenges inherent in the system of procurement in
order to correct them. These can be achieved through a formal procurement audit, among
others. The agency theory model anchored on the fact that information asymmetries and
pursuant of self-interests, principles lack basis to trust their appointed agents and will seek to
mitigate these concerns by putting in place mechanisms to align interests of agents with
principle and to reduce the scope for information asymmetries and opportunistic tendencies
(Keng’ara, 2013). The study, thus Used this model to determine the effect of procurement
management on effective project performance in CBE.
7|Page
the objectives of the principals. It implies that managers have an intrinsic satisfaction when firm
performance improves and organization success is attained. The implication of the theory is that
Managers are also motivated by non-financial factors like challenging work, the opportunity to
Exercise responsibility and authority as well as gaining recognition from peers and their
managers.
It is critical for the organization to build a structure which allows for symphony between
principles agents. Turning to the firm’s leadership, the structure which allows for symphony
between principles is where there is CEO duality. In such a scenario, the powers of the
chairman of the board (responsible for board processes) and CEO (responsible for operational
issues of the organization) are vested in one office. Donaldson and Davis indicated that such a
structure allows an ambiguity in the CEO role as power and authority over lower ranking
managers and other board members is then vested in one office.
The process of amalgamating the role of CEO and the board chairman drives down the cost of
agency while enhancing performance (Abdula and Valentine ,2009).Apart from supporting
CEO duality, proponents of stakeholders theory favors majority of insiders’ directors and argue
that they have superior knowledge of procurement functions in an organization thus take a
shorter time to make decisions; they are more effective at evaluating the performance of top
managers and utilize their expertise to ensure high quality procurement performance at all
levels. According to Letting et al. (2012), the inclusion of more executive directors in the
boards of companies would lead to more effective and efficient decision which include supplier
sourcing. Procurement functions can enjoy the consistency in leadership style, unity of direction
as well as Command.
8|Page
their raw materials. In dependency theory, the degree of dependency increases as time goes on
wealthy countries are able to use their wealth to further influence developing nations into
adopting in describing poverty. Alkire and Santos (2013) indicated that the level of poverty in
Sub-Sahara is an evidence of the developing needs.
The evidence provided by Chen and Ravalli (2010) in describing poverty puts the global
number people living with below poverty line of $ per day in Sub-Sahara Africa at 298 million
up from 168 million policies that increase the wealth of the wealthy nations, even at their own
expense. Similarly, they are able to protect themselves from being turned on by the developing
nations, making their system more secure as time goes on.
9|Page
coined the term ‘democracy’ to describe the use of teams in organizations. The team, as the
building block of the networked enterprise, displaces the traditional bureaucratic hierarchy of
successive levels of pyramided authority. In a democracy, teams’ formation leads to the lattice
network of cross-functional/cross-organizational projects that integrate the activities of the
work groups and reflect their empowerment, dedication, trust, loyalty and commitment.
10 | P a g e
might change and steps to be taken to respond to the changes. Purchasing budgeting procedures
involves various steps before the final budget is arrived at. The process usually starts at various
departments depending on the department needs for the coming financial year. The budgeting
process is then developed to a mister’s budget that is developed by the management. This
process must be followed to make the employees own the purchasing budget allocation (CIPS,
2012).
Adell, Esquerra and Estevan (2009) indicated that needs assessment encourages innovation
through procurement. They further found that need assessment provides transparency and
clarity during procurement process and guarantee the product quality by the third party
certification. They further pointed out in their report that most countries which included Spain,
UK, Denmark, Portugal and Sweden that participated in procurement assessment have a Green/
Sustainable Public Procurement (GPP/SPP) strategy or action plan. A Green/ Sustainable Public
Procurement (GPP/SPP) strategy or action plan minimizes the Environmental impacts.
However, the level of commitment varies from one organization to another. Customer request,
legal requirement, market demand, and business needs are the fundamental approaches of
setting project performance process. A well-defined project can reduce the risk of changes and
delay during project scope definition. A scope definition can be arrived at with effective needs
identification which can alleviate the risk of inadequate design that can lead to expensive
changes or even project failure (Fageha and Aibinu, 2014).
12 | P a g e
team members’ enthusiasm; unanticipated issues discovered mid-project and redefinition or
clarification of customer needs. Murphy’s Law; espouses the principle that anything that can go
wrong may
Go wrong. Pareto’s law; postulates that 80% of project’s problems and delays are caused by
20% of project activities. An effective project monitoring system should focus on activities that
carry the highest risks for delay, cost over-runs, or performance challenges; and lastly,
Escalation of Commitment principle which states that human beings tend to continue pursuing
failing courses of action, even when all signals point to the fallacy of the strategy. Thus, a
procurement project contract monitoring system can have a significant influence on people’s
decisions to escalate or de-escalate commitment. Most donors require that funding recipients
evaluate contractor performance and document, as appropriate, whether contractors have met
the terms, conditions and specifications of the contract.
Selecting a proficient and dependable contractor is one of the greatest problems consumers who
wish to achieve project success face (Kumaraswamy and Anvuur, 2008). Bid assessments can
encompass many diverse factors, for example, cost, technical capability, management aptitude,
previous experience, the object of reference, environmental and quality management systems,
financial solidity and concerted skills (Lam et al., 2001, Eriksson and Laan, 2007; Malmberg,
2007).
13 | P a g e
inventory. Thus, inventory management research is critical in procurement. Inventory programs
can make inventory commitment more efficient and improve customer service. In a recent
examination of the future of the discipline of logistics and logistics research, Davis –Sramek
and Fugate (2007) uncovered that leading discipline visionaries feel that one area in which
logistics researchers must focus on is coordination and collaboration, and subsequently, the
inventory management literature published in logistics journals has evolved in recent years in
that direction. Inventory management according to Heizer and Render (2016) indicated that
businesses hold these stocks for various reasons, including protection against general shortages
or potential problems with suppliers, or, because unit price rises may be imminent.
Nevertheless, the literature focuses upon stock replenishment policies.
Typically, the resultant inventories enable firms to perform a service economically, without the
beneficiaries suffering any untoward delays. Thus inventory planning and control bears Great
significant. The order placing discipline minimizes the cost of transferring goods, besides
shortening the associated lead times and that there are sufficient incentives for the parties to
cooperate because the recipient pays for the upstream storage and freight in one way or another.
Effective inventory management depends on understanding all the details of what is inventory
management. By applying lean practices to all aspects of the inventory management cycle,
businesses can reduce investment in standing inventory, plant rental, shipping costs, reverse
logistics while maintaining or improving customer service levels and in-stock metrics on
critical inventory (Confessore, Rismondo and Stecca, 2014).
The other sensitive area of inventory is the movement of materials as they go through the
various stages of operations which is referred to as goods or work in progress inventory which
involves tracking of materials as they are used to create finished goods that helps to identify the
need to adjust ordering amounts before the raw materials inventory can get dangerously low or
are inflated to unfavorable level (Murphy, 2007).
15 | P a g e
Independent Variable
Dependent Variables
Inventory Management
practice
Project Performance
Contract Management
Practice
16 | P a g e
CHAPTER THREE
3.1 Introduction
This chapter presents the research methodology that is followed in this study. Research
methodology includes the steps that are assumed by a researcher in studying the research
problem as informed by logic (Garg and Kothari, 2014). The research presents the methodology
that is used to carry out the survey, what informs the selection of the research design, the target
population, sampling method to be used, and data collection instrument and how data is
analyzed, interpreted and presented.
3.3Target Population
Target population is the collection of elements that possess the information sought by a
researcher (Solverman, 2016). According to Taylor, Bogdan and DeVault, (2015) a population
refers to the entire group of persons or elements that have at least one thing in common. Target
population is defined as all members of a real or hypothetical set of people, events or objects to
which a study wishes to generalize the results of a study. (Bryman and Bell, 2007). According
to Amin (2005:235), a target population is the population to which the researcher ultimately
wants to generalize the results. The target population for this study would be one hundred
(80/100) respondents. The target population of this study includes procuremnt employees of
CBE.
17 | P a g e
and lacks subjectivity selection which makes it reasonable to make a true generalization.
(Mugenda and Mugenda, 2008). The perfect sample is directly related to the type of research
one is conducting. This study used a random sampling technique formula to estimate sampling
size, was employed in this study. Based Yamane (1967:886) formula, a sample of 80 participants
is used to which a questionnaire is distributed.
n=100/1.25
n=80 (respondents).
19 | P a g e
3.6 Reliability Test Results
In order to test for reliability of the research instrument, the study used Cronbach’s reliability
Test. This determined that indeed the questionnaire was reliable enough to collect information
that could be used to make valid inferences. According to Bonnet and Wright, (2015) an alpha
level of 0.6 and above is considered acceptable.
0.921 33
20 | P a g e
3.8 Ethical Considerations
It is important to note that the code of ethics is approached via three main themes namely
ethical treatment of research participants, competence and honesty. These themes form the basis
upon which the researcher conducts the research. This includes respect for persons as well as
their beneficence, i.e. the process of ensuring that the well–being of participants and justice
which is equity ensured by a professional researcher.
21 | P a g e
CHAPTER FOUR
22 | P a g e
From table 4.1 above, it can be seen that most of the respondents were between the ages of 26
And 30 years. This was represented by 50%. 31.25% of them were between 20 and 25 years
while the remaining 18.75% were between 31and 35 years. Therefore, the respondents’ age was
between 20 and 35, implying that the respondents sought after were not minors and therefore
were at the right age to participate in the study and give answers to the questionnaire.
Finally, on the level of education, it was revealed that 41(51.25%) of the respondents had
attained Under-graduate level while 39 (48.75%) had attained post-graduate level of education.
This signifies that the respondents included in the study were knowledgeable enough to
understand the questions being posed to them in the questionnaire. This also means that the
researcher included the right people to partake in the study.
Results on the working experience of the respondents indicate that most of the respondents
had worked in procurement department for less than 3 years as represented by 46(57.5%).
Next were those who had worked between 3 and 6 years at 2 0 ( 25%) and finally those
who had worked between 7 and 10 years at 14 (17.5%).
This further indicates that the respondents chosen had experience regarding the topic of study
and are therefore in the best position to answer the questions. This is summarized in
figure4.3 Descriptive Statistics Results
The study’s main objectives were investigated and results are presented in this section. The
objectives were to investigate the effect of need assessment, supplier sourcing process, contract
management and inventory management on project performance CBE.
Average 4.01
f % f % f % f % f %
The implementation of the 0 0% 0% 0 7 10.0% 25 35.7% 38 54.3% 4.44
purchasing manual is complete
The workers of CBE 0 0% 0 0% 13 18.6% 30 42.9% 27 38.6% 4.20
serve suppliers objectively
CBE management has fully 0 0% 0 0% 18 25.7% 27 38.6% 25 35.7% 4.10
implemented procurement policy
CBE has procurement functions are in 0 0% 0 0% 19 27.1% 29 41.4% 22 31.4% 4.04
line with PPDA (2018)
The process involved in 0 0% 0 0% 24 34.3% 27 38.6% 19 27.1% 3.93
project implementation are efficient
Proposals are made and 0 0% 0 0% 29 41.4% 26 37.1% 15 21.4% 3.90
submitted to all potential suppliers
25 | P a g e
Table 4.4: Contract Management Practices and Project Performance
Questions Very Low Low Moderate High Very High Mea
n
f % f % f % f % f %
Procurement department 0 0% 0 0% 12 17.1% 31 44.3% 27 38.6% 4.21
go through process
needs of organization
Most projects completed 0 0% 1 1.4% 13 18.6% 31 44.3% 25 35.7% 4.14
in timeline
Suppliers honor their 0 0% 2 2.9% 20 28.6% 30 42.9% 18 25.7% 3.91
Obligation.
Contracts of the 0 0% 0 0% 25 35.7% 27 38.6% 18 25.7% 3.90
organization
managed fairly and
justlyorganization
The 0 0% 7 10.0% 17 24.3% 26 37.1% 20 28.6% 3.84
appraises the
suppliers you use in a
year
Delivered goods rejected 0 0% 6 8.6% 34 48.6% 27 38.6% 3 4.3% 3.39
due to non-conformity
to specification
Average 3.89
On average, most respondents believed that contract management affects project performance
to a large extent as indicated by a mean score of 3.89. Specifically, they believed that the
following are affected to a large extent; Procurement department go through process needs of
organization (mean= 4.21), Most projects completed in time (mean= 4.14), Suppliers honour
their obligation (mean= 3.91), Contracts of the organization managed fairly and justly
(mean= 3.90), the organization appraises the suppliers they use in a year (mean= 3.84) and
finally that delivered goods are rejected due to non-conformity to specification (mean= 3.39).
Finally, the study sought to find out the effect of Inventory Management on Project
26 | P a g e
performance. Table 4.5 presents the results below.
f % f % f % f % f %
Procuring of goods and 0 0% 0 0% 0 0% 36 51.4% 34 48.6% 4.49
services add to cost
reduction to the organization
Able to deliver quality 0 0% 1 1.4% 3 4.3% 50 71.4% 16 22.9% 4.16
service to end users of
the project
An average score of 4.14 also implies that respondents believe the effect of inventory
management on project performance is to a large extent. They agreed that procuring of goods
and services add to cost reduction to the organization (mean= 4.49), NGO’s are able to
deliver quality service to end users of the project (mean= 4.16), organization level of
reduction in inventory costs (mean= 4.04), organization level of stores management practice
(mean= 4.03) and that inventory purchases often meet the demand and supply principle
(mean= 3.97).
27 | P a g e
4.4 Regression Analysis Results
Regression analysis results were discussed under this section.
Model Summary
The model summary Table 4.8 indicates an R-Square of 0.395. This implies that 39.5% of the
independent variable, which were inventory management, supplier sourcing process, need
assessment, contract management explained project performance. R-Square indicates the
percentage of the independent variables that explains the dependent variable as illustrated.
Regression Coefficients
28 | P a g e
X2 = Supplier Sourcing Practices
X3 = Contract Management Practices
X4 = Inventory Management Practices
The coefficients were interpreted as follows;
β1 - 0.057 implies that holding Supplier Sourcing , Contract Management and Inventory
Management constant, a unit increase in Need Assessment will increase Project performance
by 5.7%.
β2 - 0.023 implies that holding Need Assessment, Contract Management and Inventory
Management constant, a unit increase in Supplier Sourcing will decrease Project performance
by 2.3%.
β3 - 0.032 implies that holding Need Assessment, Supplier Sourcing and Inventory
Management constant, a unit increase in Contract Management will increase Project
performance by 3.2%.
β4 - 0.029 implies that holding Need Assessment, Supplier Sourcing and Contract
Management constant, a unit increase in Inventory Management will increase Project
performance by 2.9%.
Diagnostic Test Results
The study employed ANOVA test to test the significance of the regression line and whether
any variables were omitted.
29 | P a g e
This test indicates a statistically significant F calculated value of 4.303 which is greater than
the critical F value 2.51304 (obtained from statistical tables), implying that the regression
equation generated by the study predicts the dependent variable significantly well.
Alternatively, this can be indicated by a p value of p = 0.004 <0.05. This further implies that
the regression equation adopted by the study was a line of good fit, thus can be used to
effectively predict project performance based on the functions of supply chain performance
indicated by the study.
Heteroscedasticity Test Results
The Breusch-Pagan Test for heteroscedasticity was also used to check that there is a constant
variance in the fitted variables. Table 4.9 indicates the result below.
Step 3: Rejection criteria: Reject the null hypothesis if significant value less than
0.05. Fail to reject (accept) the null hypothesis if the significant value is greater than
0.05. Conclusion: Significant value (P value) found= 0.939. This significant value is
greater than 0.05. Hence fail to reject null hypothesis. This implies that
heteroscedasticity is not present.
Variance Inflation Factor Results
VIF tests revealed that the variance inflation factor of Need Assessment was 2.890, Supplier
Sourcing 3.061, Contract Management 2.092 and Inventory Management had 3.703. From
these findings, the study concluded that there were low levels of multi collinearity since
all the values were less than 5 (Cohen, Cohen, West and Aiken, 2013).
30 | P a g e
Table 4.10: VIF test results
Variable VIF
Need Assessment 2.890
Supplier Sourcing 3.061
Contract Management 2.092
Inventory Management 3.703
The second hypothesis was that Supplier Management does not have a significant effect on
Project Performance of CBE. Similarly, the alpha value used was 0.05. Calculated t value
obtained from table 8 was 2.300. Comparing it to critical t value obtained from statistical
tables (t 69, 0.05) = 1.66724, the study rejected the null hypothesis since calculated t value was
greater than critical t value. This implied that Supplier Management has a significant effect
on Project Performance of CBE.
Contract management level involvement does not have a significant effect on
Project Performance of CBE
The third hypothesis was that Contract management level involvement does not have a
significant effect on Project Performance of CBE. The study tested this at 0.05 level of
significance and revealed a calculated t value of 2.909 (See Table 8). This was compared to a
critical value of (t 69, 0.05) 1.66724. It was concluded that the null hypothesis was to be
31 | P a g e
rejected because the calculated value of t was greater than the critical value of t.
This implies that Contract management level involvement has a significant effect on Project
Performance of CBE.
The study conducted a test to investigate the claim that Inventory management does Not
have a significant effect on Project Performance of CBE. Similarly, an alpha level of 0.05
was used. From table 8, a critical t value of 2.231 was reported, which was compared to a
critical t value obtained from statistical tables (t 69, 0.05) = 1.66724, the study rejected the null
hypothesis because calculated value of t was greater than the critical value of t. This implied
that Inventory management has a significant effect on Project Performance of CBE.
Finally, it is very important at the very outset of the project to carefully consider all factors
when selecting the most appropriate procurement approach for a construction project. This is
because each system has its own feature and peculiarity that will have effect on the cost, time
and quality of the project i.e. the project performance. In summary all the four independent
variables of procurement procedures in the conceptual framework had a positive effect on the
performance of projects.
32 | P a g e
CHAPTER FIVE
5.1 Conclusion
This study was set out to investigate the effect of procurement functions on project
performance in CBE. Its general objective included to find out the effect of need assessment,
supplier sourcing processes, contract management and inventory management on project
performance of CBE. The study employed explanatory research design and used
questionnaires as its main data collection tool. A total of 80 employees were sampled
using simple random sampling from a total of 100. Of these, 80 questionnaires were
submitted back for analysis, representing a response rate of 87.5%.
Respondents indicated that need assessment affects Project Performance to a large extent as
indicated by a mean of 4.01. The majority of them indicated that processes such as having
their annual procurement report (mean= 4.36), having a procurement database (mean= 4.19),
international competitive bidding (mean= 4.16), procurement review committee (mean=
3.90), advertising (mean= 3.89), having procurement plans (mean=3.89), having a scorecard
for procurement evaluation (mean=3.87) and finally having need functions, planning and
assessing the risk (mean= 3.83) affect procurement performance to a large extent Through
regression analysis, the study found a coefficient for Need Assessment to be 0.057, which
implied that holding Supplier Sourcing, Contract Management and Inventory Management
constant, a unit increase in Need Assessment will increase Project performance by 5.7%.
Moreover, hypothesis tests also revealed that employee Commitment to Need Assessment
has a Significant Effect on Project Performance of CBE.
Regarding the effect of supplier management on project performance, the study found an
average mean score of 4.03, which implied that the respondents indicated that supplier
sourcing process affects project performance to a large extent. The majority of the respondents
indicated that the implementation of the purchasing manual is complete (mean= 4.44), the
workers of CBE serve suppliers objectively (mean= 4.20), CBE management has fully
implemented procurement policy (mean= 4.10), CBE has procurement functions in line with
PPDA (2015) (mean= 4.04), that the process involved in project implementation are efficient
(mean= 3.93), that CBE is linked up to its suppliers and end users (mean= 3.90), that CBE
33 | P a g e
employees have fully adopted acceptable tendering regulation (mean= 3.84) and finally that
proposals are made and submitted to all potential suppliers (mean= 3.80).
Regression analysis also revealed a coefficient for Supplier Sourcing as 0.023, implying that
holding need assessment, contract management and inventory management constant, a unit
increase in supplier sourcing will decrease Project performance by 2.3%.
Finally, hypothesis tests confirm that this effect is significant by concluding that Supplier
Management has a significant effect on Project Performance of CBE. It is important to note
that Vaart and Donk (2008) also found that supplier management is a key procurement
function in as far as ensuring project success is concerned. They asserted that it is important
to involve suppliers in decision making, encouraging information, sharing and looking for new
ways to integrate upstream activities.
The study also investigated how contract management as a procurement function affects
project management. On average, most respondents believed that contract management
affects project performance to a large extent as indicated by a mean score of 3.89.
Specifically, they believed that the following are affected to a large extent; Procurement
department go through process needs of organization (mean= 4.21), Most projects completed
in time (mean= 4.14), Suppliers honor their obligation (mean= 3.91), Contracts of the
organization managed fairly and justly (mean= 3.90), the organization appraises the suppliers
you use in a year (mean= 3.84) and finally that delivered goods are rejected due to non-
conformity to specification (mean= 3.39).
A coefficient for Contract Management of 0.032 implied that holding need assessment,
supplier s o u r c i n g a n d inventory m a n a g e m e n t constant; a u n i t increase i n
Contract Management will increase project performance by 3.2%. Hypothesis tests confirmed
that Contract management level involvement has a significant effect on Project Performance of
CBE. These results are comparable to Brown and Hyer (2010) who anchored their
argument for monitoring and control on the fact that there are several phenomena which
influence project execution and cause actual performance to depart from planned
performance.
35 | P a g e
5.2 Recommendations
Based on the conclusions therefore, the study recommends that CBE should include the
four procurement functions i.e. need assessment, supplier sourcing, contract management
and inventory management in their implementation of projects. Through need assessment
processes such as need functions, planning, risk assessment, advertising, competitive
international biding, having a procurement review committee, creating a Scorecard for
Procurement Evaluation, having a procurement database and generating Annual
Procurement Reports, CBE will go a long way in ensuring that project performance
improves.
Supplier sourcing is also another critical function that helps to improve project
performance. It is important for CBE to have procurement functions ain line with PPDA
(2015), have employees that are fully adopted acceptable tendering regulation, implement
procurement policies, complete the implementation of purchasing manuals, serve suppliers
effectively, submit proposals to potential suppliers and finally ensure that the organization is
linked up to its suppliers and end users.
Contract management , on the other hand ,will improve project performance if CBE
ensures that delivered are goods which were not rejected due to non-conformity to
specification, the organization appraises the suppliers yearly, suppliers honor their
obligation, the procurement department goes through process needs of organization,
contracts of the organization managed fairly and justly and that most projects completed in
timeline.
Through inventory management, CBE can improve project performance if they ensure that
inventory purchases never fail to meet the demand and supply principle, if store
management is practiced, inventory costs are reduced, quality services are delivered to end
users and that procuring of goods and services reduces cost to the organization.
Lastly, Further research work on more delay and related cases are suggested and arranging
forums of discussion among parties in procurement management departement is crucially
important to save extra money and upgrade professional commitments of those involved in
the project.
36 | P a g e
REFERENCES
Abuzeid, F. (2009). Foreign Aid and the "Big Push" Theory: Lessons from Sub-Saharan Africa.
Stanford Journal of International Relations. Vol. XI | No. 1
Akech, M. (2014). Evaluating the Impact of Corruption Indicators on Governance Discourses.
Alkire, S., & Santos, M. E. (2014). Measuring acute poverty in the developing world: Robustness and
Scope of the multidimensional poverty index. World Development, 59, 251-274.
Alzahrani, J. I., & Emsley, M. W. (2013). The impact of contractors’ attributes on construction
Project success: A post construction evaluation. International Journal of Project
Management, 31(2), 313-322.
Arow S. (2008) an overview of EC policy on public procurement: European journal of
Operation research Vol 202, No 1 pp 16 -24
Asfaw Gezahegn (2009).The relationship between organizations’ performance. Jimma:Jimma
University.
Boström, M., Jönsson, A. M., Lockie, S., Mol, A. P., & Oosterveer, P. (2015). Sustainable
And responsible supply chain governance: challenges and opportunities. Journal of
Cleaner Production, 107, 1-7.
Burger, R., & Owens, T. (2011). Foreign funding critical for NGO survival. October 18,
2011. Global Policy Forum.
Cohen, J., Cohen, P., West, S. G., & Aiken, L. S. (2013). Applied multiple regression/correlation
Analysis for the behavioral sciences. Routledge.
Collier.P. (2007). The Bottom Billion: Why the Poor Countries Are Failling and What Can
Be Done About It Oxford univ. Press, Oxford
Dasgupta (2014) In Annual World Bank Conference on Development Economics World
Poverty: Causes and Consequences.
Dunn S.C. (2011) Motivation by Project and Functional Managers in Matrix Organization
Engineering Management Journal 13(2) 3-10
Fengler, W., & Kharas, H. (eds. 2011).Delivering Aid Differently —Lessons from the
Field.Washington, DC: Brookings Institution. President Housing Project Competes
Funds. April 6, 2011.
Galeitse, T. (2011). Policy Forum.
Garg, G., & Kothari, C. R. (2014). Research Methodology. Methods and Techniques. New
Age International Publishers. New Delhi- 110002.
Grepin, K., & Jack, W. (2008). Too Much of a Good Thing? -Potential Economic Consequences
Of Donor-financed HIV/AIDS Spending.UN AIDS/World Bank Economics Reference
Group Meeting. 28/29 April, 2008
Grimm, J. H., Hofstetter, J. S., & Sarkis, J. (2016). Exploring sub-suppliers' compliance with
37 | P a g e
Corporate sustainability standards.
Lentz, E. C., Passarelli, S., & Barrett, C. B. (2013). The timeliness and cost-effectiveness of
The local and regional procurement of food aid. World Development, 49, 9-18.
Lysons, K. and Farrington, B. (2016).Purchasing and Supply Chain Management, 7th Ed.
London: Prentice Hall.
Mugenda &Mugenda (2008), Research Methodology 2nd Ed). Research Methods; Qualitative
Approaches, Nairobi Acts Press.
Murphy, C (2007). Imagining what’s possible, Information. Journal of procurement
Management.Vol.32, No.12.pp .132-138
Odieki.M, K, Moindi M, (May 2013).Interdisciplinary Journal of Contemporary Research
Business. Vol. 5, No 1
OECD (2012), Public procurement practices in developing Countries; Journal of supply
Supply chain management.VOL.31, NO, 11. Pp.136-144.
Panda, P., & Sahu, G. P. (2012). E-Procurement implementation: critical analysis of success
Factors' impact on project outcome.
Pooe, D. R., Mafini, C., & Makhubele, D. T. (2015). Investigating Municipal Procurement Challenges
in South Africa: A Qualitative Study. The International Business Economics
Research Journal (Online), 14(1), 67.
Robert. Kates, (2007).Africa Poverty: A grand Challenge for Sustainability Science.
Said, J. Alam, M. M., & Aziz, M. A. (2015). Public accountability system: Empirical assessment
Of public sector of Malaysia. Asian Journal of Scientific Research, 8(2), 225-236.
Silverman, D. (Ed.). (2016). Qualitative research. Sage.
Taylor, S. J., Bogdan, R., & DeVault, M. (2015). Introduction to qualitative research methods:
A guidebook and resource. John Wiley & Sons.
Tenhiälä, A., Rungtusanatham, M. J., & Miller, J. W. (2017). ERP System versus Stand‐
Alone Enterprise Applications in the Mitigation of Operational Glitches. Decision
Sciences.
Zhang F. Wei, L., Yang, J., & Zhu, L. (2017). Roles of Relationships between Large
Shareholders and Managers in Radical Innovation: A Stewardship Theory
Perspective. Journal of Product Innovation Management.
38 | P a g e
APPENDIX
QUESTIONNAIRE
Introduction
Dear respondent, this questionnaire has been designed for the purpose of collecting data on
the effect of procurement management on project performance in CBE. The items in the
questionnaire are intended to assess the constraints to need assessment process, to evaluate
suppliers’ contract administration and to investigate inventory management functions that
enable accountability, fairness, timeliness, quality and acceptability in project performance of
CBE.
Your responses will be kept confidential. Please respond to the questions honestly by ticking
the most appropriate response.
SECTION A:
GENERAL QUESTIONS
Please tick appropriately in the boxes using a tick (√) or cross mark (x).
1. Gender: Male [ ]
Female [ ]
2. Age Bracket in years: 20-25[ ]
26-30[ ]
31-35[ ]
36-40 [ ]
41 -50 [ ]
51 and Above [ ]
3. Highest level of education
a) Undergraduate Level [ ]
b) Post-Graduate Level [ ]
d) Any other (Specify).........
4. How long have you worked for the organization?
a) Less than 3 years
b) 3 –6 years
c) 7–10 years
d) More than 10 years
39 | P a g e
5. How many employees are employed by your organization?
a) Less than 50 [ ]
b) 50 -100 [ ]
c) 100 –200[ ]
d) More than 200[ ]
SECTION B: PROCUREMENT FUNCTIONS
a. Need Assessment Questions
Among the Need Assessment procurement practices listed below, which ones have been
adopted by your organization? Indicate based on the scale below;
1-Very Low Extent,
2-low extent
3-moderate extent
4-great extent,
5-very great extent
Questions 1 2 3 4 5
40 | P a g e
Questions 1 2 3 4 5
c) Contract Management
Indicate based on the scale below;
1-Very Low Extent,
2-low extent,
3-moderate extent,
4-great extent,
5-very great extent
Questions 1 2 3 4 5
22 Delivered goods are rejected due to non
conformity to specification
23 The organization appraises the
suppliers you use in a year
24 Suppliers fail to honor their obligation.
41 | P a g e
d) Inventory Management
Answer the following questions by choosing the suitable rating scale from the ratings
provided.
1-Very Low Extent,
2-low extent,
3-moderate extent,
4-large extent,
5-very great extent
Questions 1 2 3 4 5
42 | P a g e
Questions 1 2 3 4 5
43 | P a g e