Professional Documents
Culture Documents
Basic Operation Concept For Turbine and Auxiliary Plant
Basic Operation Concept For Turbine and Auxiliary Plant
PROJECT :
OWNER’S ENGINEER :
CONTRACTOR :
SUBCONTRACTOR :
M. Kajiwara 25-01-2017 Basic Operation Concept for Turbine and Auxiliary Plant
CHECKED BY DATE OWNER’S DOCUMENT NUMBER REV.
8 Dec. 01, 2020 Revised as per design progress H. Tao H. Tao M. Kajiwara
7 Oct. 20, 2020 Revised as per design progress H. Tao H. Tao M. Kajiwara
6 Apr. 03, 2020 Revised as per design progress H. Tao H. Tao M. Kajiwara
5 Oct. 09, 2019 Revised as per owner comment and design progress H. Tao H. Tao M. Kajiwara
4 Aug. 30, 2019 Revised as per design progress H. Tao H. Tao M. Kajiwara
3 Mar. 12, 2019 Revised as per design progress H. Tao M. Kajiwara K. Tanaka
2 Jul. 03, 2018 Revised as per Owner comments. Y.Sugimori K.Tanaka M.Kajiwara
Y.Sugimori
1 May.17, 2018 Revised as per Owner comments. K.Tanaka M.Kajiwara
H.Tao
回 数 日 付 記 事 承 認 調 査 担 当
REV.NO. DATE CONTENTS APPROVED BY CHECKED BY REVISED BY
配 布 先
(PJM) 1 (Tasetsu-1) 1
DISTRIBUTION 発 行 課 Utility Plant Engineering Group
ISSUED BY Plant Engineering Dept.
Customer 1 (Ka-EX) 1 (Seigyo) 1
承 認
HEC 1 (Ka-IX) 1 (Netsusetsu) 1 H. Tao
APPROVED BY
調 査
HDEC 1 (Ka-IC) 1 (P-setsu) 1 T. Miyazaki
CHECKED BY
担 当
MHPS 1 (Ka-FP) 1 (Ka-PU) 1 M. Kajiwara
PREPARED BY
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
CONTENT
Page
Clause No. Description
No.
1 Introduction 3
1.1 Turbine Island Balance of Plant (BOP) 4
1.2 Control Configuration 4
2 Operating Condition 5
2.1 Steam Turbine Operation 6
2.2 Plant Operation 7
2.3 Turbine Bypass System 13
2.4 Steam Turbine Trip Condition 14
3 Main System and Main Equipment 15
3.1 Make Up System 15
3.2 Condensate System 15
3.3 Feedwater System 17
3.4 Extraction Steam and Heater Drain System 22
3.5 Clean up System 27
3.6 Main Cooling Water System 30
3.7 Auxiliary Cooling Water System 31
3.8 Closed Cycle Cooling Water System 33
4 Local Control System 35
5 Special Operation 36
5.1 Condenser Half Tube Bundle Operation 36
5.2 Boiler Feedwater Pump Parallel Operation 36
5.3 Load Runback 36
5.4 HP and LP Heaters Bypass Operation 37
6 Reference documentation 38
Annexure-I Typical BFP Turbine Start-up Curve & Shut-down Curve 38
Annexure-II Typical Sequence of Manual Turbine Start-up Time Chart 40
Annexure-III Mismatch Chart 41
Annexure-IV Typical Sequence of Turbine Shutdown Time Chart 42
2 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
1. INTRODUCTION:
The Plant consists of one 1000 MW Capacity Coal fired Thermal Power plant. Coal is used
as a primary fuel for normal operation and Light fuel oil is used during startup, low load
operation and shutdown condition.
Specification of Generator:
Type = Water cooling for stator, H2 cooling for rotor
Capacity = 1210 MVA
Power Factor = 0.85 lagging
Frequency = 50 HZ
3 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
A Systems
1 HP steam system
2 Reheat steam system
3 Gland steam system
4 Turbine generator lube oil system
5 Control oil system
6 Condenser air extraction system
7 Condensate water system
8 Condensate polishing plant
9 Boiler feedwater pump turbine system
10 Boiler feedwater pump turbine lube oil system
11 Feed water system
12 Closed cycle cooling water system
13 Main cooling water system (Toshiba will supply piping and equipment within
condenser pit)
14 Makeup water system
15 N2 sealing system(Turbine area)
16 CO2 gas control system
16 H2 gas control system
17 Generator seal oil system
B Equipments
1 Steam Turbine Components
2 Steam Turbine Valves
3 Condenser Vacuum Pumps
4 Condenser
5 Condensate Pumps
6 Condensate Polisher
7 LP Heaters
8 Deaerator
9 Turbine Driven Boiler Feedwater Pumps
10 Motor Driven Boiler Feedwater Pumps
11 HP Heaters
12 Closed Cycle Cooling Water Pumps
13 Closed Cycle Cooling Water Heat Exchanger
14 Auxiliary Cooling Water Pumps
15 Generator and Auxiliaries
16 LP Heater Drain Pump
17 Sump Pumps for Turbine House
18 Hoists and Monorails
19 Piping, Valves and accessory
Turbine startup and shutdown automatic operation will be controlled by Plant automation
system (PAS). Turbine and its auxiliaries are controlled by DCS system. Some BOPs, for
example Condensate polishing plant, shall have their own dedicated control system and
interfaced with DCS system for overall monitoring.
4 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
2. OPERATING CONDITION:
The Turbine and Auxiliary Plant can be operated up to the Maximum load (BMCR) or can be
operated at any intermediate Load Set point between minimum and the maximum load as
desired by the operator when plant parameters do not exceed alarm point. For low load
operation, terminal point parameters such as main / hot reheat steam temperature / pressure
etc. shall be agreed with boiler supplier to maintain monitoring parameters not exceeding
alarm point and to avoid plant lifetime shortening.
The minimum continuous operating load is 30% of TMCR.
Temperature rise of Main Cooling Water between Condenser inlet and outlet is 8.3 deg.C at
TMCR condition.
5 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
The Steam Turbine operation concept includes Basic operation, Special operation, main
equipment operation, Failure action and runback operation. Boiler and Turbine unit startup
and shutdown automatic operation will be controlled by Plant automation system (PAS).
The Steam Turbine consists of several stages with each stage consisting of the High
Pressure (HP), Intermediate Pressure (IP) and Low Pressure (LP) stages. The Boiler and
Turbine Generator units are operated with sliding pressure mode. While MSV is fully opened
in any load operation, opening of CVs are depending on the required load. Steam Turbine is
controlled by Digital Electro-Hydraulic-Control (D-EHC) system. The Main Functions of
D-EHC are to control Turbine speed, load, load limit, line speed matching, CV Chest warming,
Automatic Turbine startup, Thermal stress calculation, Turbine trip, Turbine valve test,
Turbine over speed trip test and backup over speed governor test.
Four (4) CVs control main steam pressure. For load requirement above 97% Flow, main
steam pressure will be kept 258.02 bar(a). For load requirement between 97% Flow and
30%TMCR, the plant will be operated by sliding pressure operation. Four (4) CVs are
opening simultaneously during all operating range. (Ref. Fig-1)
(Fig-1) Sliding Pressure Pattern and CV control pattern for static condition
6 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
2.2.1 Start up
Start up of Turbine and its auxiliaries systems will be performed always to ensure operational
reliability and economy. 1000MW Boiler-Turbine set has an automatic startup and shutdown
sequence logic, which may be used in the normal start–stop operation of the unit. This
sequence logic includes the equipment and control variable sequencing steps necessary to
take the Boiler -Turbine unit from Ready-to-Start condition to the desired load level and back
to shutdown condition. To establish Ready-to-Start conditions, certain operations are to be
done by manual or sequenced actions initiated by the operator for some cases from the DCS
and in other cases from the respective local equipment.
The period of startup after shutdown is indicated in Table-1 & 2. To maintain operational
safety, reliability, and economy, certain test (Turbine protection/valve test) shall be performed
during all phases of Turbine operation.
A) The following list describes pre-start conditions which are to be established to bring the
Turbine to Ready-to-Start conditions. (For reference)
6) Make Up Water System for condensate and closed cycle cooling water are in
service
7 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
20) HP Turbine Bypass Control Valve Oil Supply Unit in service and auto.
31) DC power for Emergency Oil Pumps and Emergency Seal Oil Pump is
available
32) Auxiliary Steam System in service and Auxiliary Steam Header pressure
normal
35) Filling valves and Vent valves opened/closed during filling operation (such as
Boiler, Feed water heater, HP, LP Heater, condenser hotwell and CCCW
system)
Note 2) Checking and establishing systems mentioned above include manual selection
and changeover of line for duty and stand-by equipment.
After the confirmation of pre-start conditions, Turbine becomes ready to the condition.
8 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
B) Automatic operations
4) HP Turbine Warming
5) 1st BFP Start and Stop, 2nd BFP Start and Stop
6) Extraction Steam System and Heater Drain System Start and Stop
9 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
time, and those are to be established as for pre-checking, confirmation, breaking point check and/or
preparation before initiating unit startup activities.
The time wasted caused by the factor which is not related to the main boiler and steam turbine
generator.
The time for condenser vacuum up. It shall be completed in advance before the boiler firing by the
auxiliary steam from auxiliary boiler.
The time for HP/IP steam turbine warming.
The time for CV warming
The time for abnormal rub check during steam turbine run up
The time for the switchover of boiler feedwater pump(BFP) from Motor driven boiler feedwater
pump(MBFP) to Turbine driven boiler feedwater pump(TBFP) at the partial load at the intermediate
process of unit startup
The time for the switchover of the boiler fuel from light fuel oil to coal at the partial load at the
intermediate process of unit startup.
The time during clean-up operation period until the water quality reaches a prescribed value.
The time until the steam purity and feedwater/condensate water quality are established for the
substantial operation in the process of startup.
The time for the break point operation of Boiler/Turbie startup sequence, and the waiting time
caused by the operating delay of EP and FGD etc.
Note 3: The operator is requested immediately to take corrective actions with the following manner to decrease
HP exhaust temperature.
a) When the unit is at no load operation, the unit should be synchronized immediately under all conditions
at the ready for synchronization.
b) When the steam temperature is higher than normal condition at no load or low load operation, the boiler
operation should be adjusted in order to decrease steam temperature.
Note 4: Those above definitions are fundamental conditions to determine a represented startup schedule to
know the typical startup mode and expected time based on shut down duration. Meanwhile actual start
up schedule and mode of steam turbine is selected/optimized by the mismatch of HP turbine metal and
steam temperature mainly as per pre-set condition called “Mismatch chart”. Important note is hereby
given that actual unit startup condition is always different from the represented condition by surrounding
situation, and optimized startup schedule and mode selection as per mismatch chart have more detail
several variation depend on various parameters, which may be different from the expected typical
condition shown in Table-1.
Note 5: Further detail is referred to boiler/steam turbine startup curves
2.2.2 Total Number of Start up per unit During life time of 40 years are indicated in Table-2
Plant Startup Criteria consists of the following Conditions & type of start and Turbine startup
criteria consists of 1st stage metal temperature.
Feedwater will be supplied by MBFP during normal unit start-up. At appropriate load
(around.15% Load), it will be switched over to TBFPs automatically. Plant startup by TBFP
without MBFP is not considered.
Boiler and Turbine unit startup automatic operation will be controlled by Plant Automation
System (PAS) based on the Boiler and Turbine conditions such as shut down duration,
10 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
mismatch temperature between boiler steam and metals, and so on. In case of the start-up
after condenser vacuum break, condenser vacuum up shall be done as the first step for the
steam turbine start preparation.
NOTE)
Attachments of “Annexure-II: Sequence of Manual Turbine Startup Time Chart” and
“Annexure-III: Mismatch Chart” are TYPICAL one, and similar one for this project will be
provided and finalized later.
Turning operation before rolling prevents temporary rotor bows due to thermal distortion. It is
desirable to have continuous operation maintained since the previous shutdown. Following
long periods off turning, a 4-hour minimum operation period is essential to get smooth
trouble-free starting. Generally, an 8-hour period is preferable. However, the unit on which
rotor eccentricity detectors are installed can be started following 1-hour minimum operation
period after the eccentricity has reached 10 percent of the normal value specified. In any
event, following a shutdown period, the rotor should be turned on gear 10 minutes for each
minute it was shut down, until it has turned for 8 hours.
In case of Initial Cold Start up, when the 1st stage metal temperature of the HP Turbine is
less than 150 deg.C, pre-warming of the HP Turbine must be conducted by supplying the
auxiliary steam from HP Turbine Exhaust End. Similarly, when the reheat bowl temperature
of the IP Turbine is less than 150 deg.C, pre-warming of the IP Turbine must be conducted
by supplying auxiliary steam from the steam seal header.
1) ST roll-off
* Confirm that MS pipe warming, MSV/CV warming and ST Pre-warming are completed.
* Upon checking that the MS and HRH steam conditions are ready, admit the main steam to
the ST and take the following steps;
Rub-check
* After ST speed reaches Rub-check speed of 400 rpm, stop the ST speed increase and
confirm that there is no rubbing at field.
* After confirming that there is no abnormal sound, increase the ST speed in accordance
with ST Start up chart, which is pre-installed in D-EHC.
11 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
3) Load up
* After ST load reaches the Initial load or completion of Initial load holding, ST load increases
with Loading up rate by the operator or Plant DCDAS with Loading up rate in accordance
with ST Start up Curves.
* ST side drain valves are closed when the ST load reaches a predetermined load.
Shut down time indicated in the shutdown (Annexure-IV) curve is typical. The shut down time
will vary depends on operator intervention during normal or load through off or emergency
Turbine trip or emergency Boiler trip.
12 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Boiler and Turbine shutdown automatic operation will be controlled by Plant Automation
System (PAS) based on the Boiler and Turbine conditions.
Ramp rate during normal operation is indicated in Table-3, and ramp rate for startup and
shutdown conditions is indicated in Table-4.
30 to 100% 1%/min
High pressure (HP) bypass system is provided so as to reduce the unit startup time during
Hot/Warm/Cold startup mode. During turbine bypass operation, steam from main steam line is
damped into condenser. The design inlet capacity is indicated in Table-5
13 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
14 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
3.2.1 Condensate system is equipped with three (3) x 50 % Condensate Pump (CP), Condensate
Polishing Plant (CPP), Gland Steam Condenser (GSC), LP Heater 1,2,3 & 4 and Deaerator. CP
take suction from Condenser hotwell and deliver to Deaerator through CPP, GSC, seal water for
Condenser Vacuum Pump and Valves sealing systems, LP Heaters, HP Turbine Bypass Spray,
Condenser Water Curtain spray, and LP Turbine Casing Spray. Chemical Dosing System shall
be provided at Condensate Pump discharge to maintain condensate water quality such as
dissolved Oxygen and pH. One (1) x 100% LP Heater Drain Pump (HDP) is provided to pump
the drain of both LP Heater 4 and LP Heater 3 from LP Heater Drain Tank to condensate
system.
15 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Permanent suction strainer will be applied at CP suction to remove foreign particles during
commissioning as well as normal operation.
16 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
3.3.1 Feedwater system consists of two (2) x 50% duty Turbine Driven Boiler Feedwater Pumps
(TBFP), one (1) x 25% duty Motor Driven Boiler Feedwater Pump (MBFP) and HP Heater
6A/B,7A/B, 8A/B and Desuperheater. The feedwater system is provided to supply feedwater
from Deaerator to Boiler via High Pressure Heaters. The Reheater spray water will be supplied
from intermediate stage extraction of Boiler feedwater pumps.
17 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
To BOILER
MHPS
From LP HTR 4
TSB
DEAERATOR
DSH A DSH B
HP HTR 8A HP HTR 8B
HP HTR 7A HP HTR 7B
HP HTR 6A HP HTR 6B
BP BP
Turbine Driven Boiler Feedwater Pump (2 x 50%)
BP
18 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
a) Unit start up
MBFP shall be always used at unit startup and keep in service up to 25 % load.
TBFP shall be started less than 25% load and switched over from MBFP to TBFP before
reaching 25% load.
In service: In service:
Before HP Clean up 25% load or Before TBFP to MBFP
Stop: Changed over
After MBFP to TBFP changed Stop :
over After All Boiler
Equipment stopped (manual)
Note:
Above operation should be done under Note:
PAS (Plant Automation System) as Above operation should be done under PAS
MBFP regular operation routine. (Plant Automation System) as regular
operation routine.
In service:
After runback operation due to
one TBFP trip is completed.
Note:
Start of MBFP after completion of the
plant runback should be done by
operator using DLC (Drive level control
function.
BFP Turbine shall be driven by the following source of steam and Exhaust is connected to
the condenser.
Note) In case required steam for BFP Turbine cannot be obtained by extraction steam
during plant startup, auxiliary steam is used as supplemental steam source.
BFP Turbine is controlled by BFPT D-EHC, conditions generated by BFPT D-EHC and other
controllers are monitored by HMI. The main function of D-EHC are acceleration control,
speed holding, Deceleration control, over speed trip test, speed control and CV position
control.
19 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
e) TBFP/MBFP Operation
MBFP shall be always used for unit start up and Flow Control Valve will be used for feed
water control. MBFP Pump speed will be controlled by Boiler controller according to feed
water demand.
During plant startup, MBFP will be taken into service and loaded around 15% load or
maximum as up to 25% load. First TBFP will be taken into service when the load exceeds
more than 15%, and MBFP will be unloaded simultaneously. Before 50%, second TBFP will
be taken into service. Finally both the TBFPs will be loaded together up to total 100 % load.
In case of tripping of any one of the TBFPs during normal operation, unit load should be
reduced to target load at once, and MBFP will be started. And, the capability of pumps
recovering the load to 75% Rated load in T-MBFP parallel operation should be considered.
Temporary suction strainer with 60 mesh will be applied during the first half of commissioning
stage so that any foreign particles from various systems connected to the Deaerator to be
removed, and permanent suction strainer with 20 mesh will be applied after temporary mesh
removal.
Parallel operation by using one (1) TBFP and one (1) MBFP is possible within the extent of
allowable load range is possible, however this shall not be the regular routine operation and
shall be the case only when it is required by the reason of one BFPT or one TBFP is in
trouble conditions.
20 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
21 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
3.4.1 Steam is extracted from different stages from HP Turbine, IP Turbine and LP Turbine and
supply for feed water heating. The Extraction lines from the Turbines are listed in Table-12.
No.5 Extraction from IP Turbine Deaerator pegging steam and Turbine driven Boiler
feed pump
No.6 Extraction from IP Turbine Desuperheater and HP HTR 6 feed water heating
3.4.2 Cascades drains are provided from a higher pressures heater to a lower pressure heater.
Each feed water heater, including Deaerator is provided with venting system, thus allowing of
non-condensable gas from each heater shells. Gases from the HP heaters normally flow to
the Deaerator. Gases from the Deaerator vent to atmosphere. Gases from the LP heaters
flow through condenser. Heater Drain system details are listed in Table-13.
(Table-13) Heater Drain System Details
Normal Before During Before shut During shut
Emergency
Equipment Discharge Startup startup down down
Discharge To
To Discharge to Discharge to Discharge to Discharge to
22 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
During Startup, when the Main Turbine load reaches to greater than 10% Turbine load, the
extraction steam isolation valves are opened one by one in the order from lower pressure
extraction steam line to higher pressure extraction steam line.
During Shutdown, when the main Turbine load comes down less than 15% Turbine load, the
extraction steam isolation valves are closed from High pressure extraction steam line to low
pressure extraction steam line.
The basic concept for the water induction protection are as follows:
1) Alarm :
Each Feedwater heater provided with High water level alarm (HWL) and High-High water
level alarm (HHWL)
2) Protection action:
a) Automatic drain system from the feedwater heater (Deaerator) shell to condenser
b) Automatic shutoff in extraction line to feedwater heater (Deaerator).
c) Automatic shutoff in all sources of water entering the feedwater heater (Deaerator) shell
and tubes.
3) Heater drain:
All Feed water heater emergency drain lines are directly connected to the Condenser.
23 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
These emergency drain valves will open at HWL by automatically split controls with the
normal drain controls.
4) In case of water induction detected, the following action should be taken. (Ref: Table-15)
b) LP HTR 3 and 4
HWL Alarm Alarm
8 High Opening of emergency drain valve.
HHWL Alarm • Closure of motorized isolation valve in extraction
High- High line. NRV is also forced closed using same signal.
c) LP HTR 2
HWL Alarm Alarm
8 High Opening of emergency drain valve.
HHWL Alarm • Opening of motorized common bypass valve for
High- High LP HTR 1&2 and closure of motorized inlet / outlet
isolation valves of series LP HTR 1&2.
d) LP HTR 1
HWL Alarm Alarm
8 (HTR Drain Tank) High Opening of emergency drain valve.
HHWL Alarm • Opening of motorized common bypass valve for
(LP HTR-1) High- High LP HTR 1&2 and closure of motorized inlet / outlet
isolation valves of series LP HTR 1&2.
e) Deaerator
HWL Alarm Alarm
High
HHWL Alarm • Closure of motorized isolation valve in extraction
High- High line
• Opening of motorized valve in LP clean up line.
8
24 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
To ATM
DSH A DSH B
To ATM
To ATM
Vent line
To PIT
HP HTR 8A HP HTR 8B
HP HTR 7A HP HTR 7B
To Condenser To PIT
To PIT
To Condenser
HP HTR 6A HP HTR 6B
To PIT
To Condenser
To PIT To PIT
Drain line To Condenser
25 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
To ATM
Vent line
LP HTR 4 To Condenser
To Condenser
To PIT
LP HTR
Drain Tank
LP HTR 3 To Condenser
Drain line
To PIT
To Condenser
Vent
line LP HTR 1
LP HTR 2
Condenser
Drain line
26 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Pre-boiler cleanup system is provided for condensate system and feedwater system in
Turbine portion to ensure the water quality will meet the requirements before supplying
feedwater to boiler for unit startup and operation.
Pre-boiler cleanup system is categorized as three processes which are Condensate Cleanup,
LP Cleanup and HP Cleanup, and these processes are sequentially carried out by checking
the water quality at each process. Also, the water is drained out and collected to wastewater
system through boiler blowdown tank located at Boiler area first, and subsequently the water
is re-circulated through condenser at each process until getting acceptable water quality.
(Ref: Table-16)
Pre-boiler cleanup is generally required for Cold startup mode and/or condenser vacuum
break condition, and the excepted cleanup requirement at respective startup mode are
summarized in Table-17A.
Related equipment during cleanup operation at each cleanup process are shown in
Table-17B.
27 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Condensate
Condensate Blow
Cleanup Condensate Condensate
Cond.
re-circulating
Cleanup Recirculation FCV
Recirculation
28 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
29 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Main cooling water (MCW) are supplied from four (4) x Main Cooling Water Pumps (supplied
by HEC/HDEC). The cooling water is pumped up by Main Cooling Water Pumps (MCWPs),
and supplied to Condenser through MCW supply piping. After undergoing heat exchange in
Condenser, the heated cooling water is sent to cooling tower (supplied by HEC/HDEC)
through MCW return piping.
Condenser has two (2) cooling water inlet & outlet lines to continue the steam turbine
operation even if one (1) cooling water line is isolated. Each line has motorized isolation
valves at the inlet and outlet to isolate the associated water box from main cooling water
system.
2 x 50% Condenser Tube Ball Cleaning System for steam turbine unit is provided for on-line
cleaning of Condenser tubes by passage of slightly oversized sponge ball (larger than
condenser tube diameter), through Condenser tubes.
3.6.1 Equipment
(Table-18) Equipment of MCW System
Sponge ball on-load cleaning system is used in order to keep clean internal surface of
condenser tube. The cleaning system mainly consists of ball strainer, ball strainer pump, ball
collector and ball injection nozzle.
30 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Auxiliary cooling water system consists of two (2) x 100% Auxiliary Cooling Water Pumps
(ACWP) and two (2) x 100% CCCW Heat Exchangers. Auxiliary Cooling Water Pump takes
suction from main cooling water line (upstream of condenser) and pumped up to CCCW Heat
Exchangers and Condenser Vacuum Pump Seal Water Coolers. Return hot water from the
CCCW Heat Exchangers and Condenser Vacuum Pump Seal Water Coolers are connected
to the main cooling water line (downstream of condenser)
3.7.1 Equipment
If running ACWP trips, the stand by pump will start automatically. Adequate drain and vents
are provided for start-up and maintenance. ACWPs are controlled by DCS.
31 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
32 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Closed cycle cooling water (CCCW) system consists of 3 x 50% Closed Cycle Cooling Water
Pumps (CCCWP) and 2 x 100% CCCW Heat Exchangers and CCCW Chemical dosing
system. Demineralized water in CCCW system is pumped by CCCWPs up to Boiler auxiliary,
Turbine and BOP auxiliary cooling system through CCCW Heat Exchangers and return hot
water from each cooler shall be discharged to the suction of the CCCWPs to be cooled again
in CCCW Heat Exchangers. CCCWPs are provided with suction side temporary strainer. A
head tank is provided at the suction of the CCCWPs for buffer and to keep the pump suction
head. The make up water is provided from header of Make Up Water Pump discharge. The
chemical dosing line is connected to CCCW Pump suction for corrosion inhibition.
3.8.1 Equipment
(Table-21) Equipment of CCCW System
33 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
34 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Failure
System Valve Service Control Type
Action
LP Turbine Casing Spray Valve On-Off Close
Condensate Water Curtain Spray
On-Off Open
Condensate Valve
System Deaerator Level Control Valve Modulating Lock (O)
Condensate Water Recirculating
Modulating Open
Control Valve
TBFP Minimum Flow Control Valve Modulating Open
Feed water
MBFP Minimum Flow Control Valve Modulating Open
System
MBFP Outlet Flow Control Valve Modulating Lock (C)
HP Heater Level Control Valves Modulating Open
HP Heater Emergency Level Control
Modulating Open
Valves
LP Heater Level Control Valves Modulating Open
Heater Drain and LP Heater Emergency Level Control
Modulating Open
Vent System Valves
Heater Drain Tank Level Control
Modulating Lock (O)
Valve
Heater Drain Tank Emergency Level
Modulating Open
Control Valve
Auxiliary Steam
Deaerator Pressure Control Valve Modulating Close
System
Closed Cooling Water Head Tank
On-Off Open
Level Control Valve
Closed Cycle
Main Oil Temperature Control Valve Modulating Lock (O)
Cooling Water
BFPT Oil Temperature Control
System Modulating Lock (O)
Valve
EHC Oil Temperature Control Valve Modulating Lock (O)
Gland Steam Seal Feed Control
Modulating Lock (O)
Gland Steam Seal Valve
and Drain System Gland Steam Packing Unloading
Modulating Close
Control Valve
Stator Cooling Water Pressure
Generator Stator Modulating Open
Control Valve
Cooling Water
Stator Cooling Water Temperature
System Modulating Open
Control Valve
35 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
5. Special Operation
In case condenser tube leakage occurred, the associated tube bundle is isolated from the main
cooling water system by fully closing condenser water box inlet and outlet isolation valves. The
water box vent and drain valves are opened for the inspection and maintenance of the leaked
tube. The leaked tube is plugged for further operation. Under half tube bundle operation, two
CWPs may be stopped where the Turbine continues to operate at the load up to 50% Turbine
load.
Two TBFPs will be in service during normal operation. In case any one TBFP tripped, MBFP
may be operated manually so that 75% load operation can be achieved by parallel operation of
a TBFP and MBFP.
Runback functions are provided, in case of Quick load reduction and complex of operation is
needed when the accident or protection occurs. It is difficult to predict accident or protection,
except Turbine trip. Other than Turbine tripping operator can reduce the load due to any
accident or protection occurs. The items of run back and load change rates is indicated in Table
-23.
(Table-23) The item of runback
a) BFP Trip
In case of one of the running TBFP trips, the STG load will be reduced to target load at
once. Stand by MBFP will start on manual with minimum flow operation and discharge
valve open. The remaining Feedwater flow is controlled automatically to keep the required
Feedwater flow which is equal to the target load until stable operation after BFP runback.
The load can be recovered to 75% load after feed water flow from two BFPs are balanced
out and stand by BFP in Auto mode.
36 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
a) The maximum plant load limit at heater bypass operation is indicated in Table-24 respectively.
37 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
38 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
39 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
40 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
Annexure-III
Mismatch Chart
41 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved
DSC-GMH-XICR1-0017 Rev.8
42 / 42
TOSHIBA CORPORATION
Proprietary Information
© Toshiba Corporation 2017, All Rights Reserved