The Department of the Interior and Local Government (DILG), given its
mandate as overseer, is tasked to implement mechanisms that foster
continuous growth in transparency and accountability at all local government
levels. Henceforth, the Department adopts a multi-faceted approach to the
monitoring and evaluation of programs and projects under the "Assistance to
Local Government Units - Local Government Support Fund" (ALGU-LGSF).
More specifically, risk-based progress monitoring shall be its overarching
frame, which considers timeliness, quality and the dimensions of transparency
and accountability. The methodology is based on participatory governance
practices involving multiple stakeholders from the Local Government Units
(LGUs), the DILG, and non-government organizations/civil society
organizations (NGOs/CSOs) while using digital platforms (e.g. SubayBayan
and RSSA).
The Management Action is also embedded into the Monitoring and Evaluation
(M&E) process as presented in the latter part of the issuance. Moreover, a
guiding framework and a brief discussion pertaining thereto is provided in
Annex A which details the rationale, approach, and methodology used in these
guidelines.
2.0 Purpose
4.0 Scope/Coverage
4.2 All DILG Field Offices (DILG-FO) primarily involved in the monitoring
and evaluation of LGSF projects;
4.4 Projects under the LGSF for FY 2021 and thereafter, including, but
not limited to:
4.4.1 Assistance to Cities (AC)
4.4.2 Conditional Matching Grant to Provinces (CMGP)
4.4.3 Disaster Rehabilitation and Reconstruction Assistance
Program (DRRAP)
4.4.4 Financial Assistance to Local Government Units (FALGU)
4.4.5 Growth Equity Fund (GEF)
4.4.6 Support to the Barangay Development Program (SBDP)
Page 2 of 18
5.1.3 To ensure transparency of the projects to be implemented, the
implementing LGU shall develop or maintain its
functional/operational website. In addition to the website, the
LGUs may also maintain and use their official social media
pages (Facebook, Twitter, etc.) to disclose reports and
showcase progress pertaining to project implementation.
Page 3 of 18
share of LGUs or supported by funds
released directly to the
province/city/municipality; and
For InfrastructureProjects
Page 4 of 18
Memorandum Circular No. 2020-151, to include
the following:
i. Project Profile;
ii. Project Milestones;
iii. Physical Status including its proof
document, such as but not limited to
Statement of Work Accomplished (SWA) -
Annex F, Certificate of Completion (COC)-
Annex G for infrastructure projects; and
iv. Financial Status including its proof
documents such as but not limited to Report
of Disbursement I Liquidations - Annex H,
Report on Fund Utilization and Status of
Program I Project Implementation - Annex
I.
For Non-InfrastructureProjects
Page 5 of 18
mentioned in item C shall be done by the DILG.
The DILG shall then issue an Aide Memoire
containing the observations, findings and
recommendations;
i. Project Profile;
ii. Project Milestones;
iii. Physical Status physical status including its
proof document, Monitoring Templates
using Appendix 1 - 19, whichever is
applicable, for non-infrastructure projects;
and
iv. Financial Status including its proof
documents such as but not limited to Report
of Disbursement I Liquidations - Annex H,
Report on Fund Utilization and Status of
Program I Project Implementation - Annex
I;
Page 6 of 18
tools mentioned in Item c, Section 5.2.1.2 and/or
Item C. Section 5.2.1.3 of these guidelines;
Infrastructure Projects:
Quality Assurance Assessment Report
(QAAR) Tool -Annex D;
Page 7 of 18
Aide Memoire (template already
incorporated in the QAAR Tool)
InfrastructureProjects:
Mentioned in Section 5.2.1.2 of these
guidelines in relation to infrastructure projects
Procurement Schedule;
Detailed Engineering Design
Implementation Schedule;
Final Inspection Report;
Certificate of Completion and Acceptance;
Statement of Work Accomplished;
Report of Disbursement;
Report on Fund Utilization
Non-infrastructureProjects:
Page 8 of 18
Project Profile;
Inventory of Motor Vehicles;
Report of Disbursement;
Report on Fund Utilization
InfrastructureProjects:
Quality Assurance Assessment Report
(QAAR) Tool -Annex D;
Aide Memoire (template already
incorporated in the QAAR Tool)
Page 9 of 18
*Ensure that the LGU will confirm the
observations, findings and recommendations
through an issuance of reply letter and they have
issued a Notice of Defects I Deficiencies - Annex
£. to the contractor for infrastructure projects.
Page 10 of 18
iii. Conduct periodic assessment of programs
based on targets;
i. Shall ensure:
1. Proper implementation of all projects under
the SBDP;
Page 11 of 18
4. All policy issuances and implementing
guidelines are cascaded to all LGUs thru the
DILG Field Offices;
Page 12 of 18
Aside from the regular monitoring of the projects done by the
field officers, they shall also be able to prioritize those that
show possible risks that may develop into issues that may
impede the project implementation.
Page 13 of 18
NOTIFICATION SYSTEM
MONITORING AND
Figure 1: DILG Management Action Process Flow
l YES
All identified triggersshall
Issue a LETTERTO LCEregarding the be subjected to the
findings and recommendation warning scheme
based on the M&F
RESULT
Page 14 of 18
Being able to identify which level shall take actions on various
concerns on the field, this process flow establishes the steps
that the monitors are to undertake for concerns and issues of
non-compliance with the Local Government Units. This is
closely incorporated in the regular conduct of the monitoring
and evaluation.
Note:
* If no LGU was issued with the Notice, the DILG RO
shall submit a report stating that there is none in the
area of jurisdiction.
Page 15 of 18
5.3.4.5 All offices concerned may refer to the links below in
aide of monitoring and reporting:
a. https://tinyurl.com/OmnibusMatrix
1. Matrix of Risk Triggers
2. Matrix of Notification Scheme (Roles and
Responsibility per level)
b. https://tinyurl.com/Casesandlnterventions
1. Matrix of Cases and Possible Interventions
Page 16 of 18
7.0 Annexes/Downloadable forms
8.0 Effectivity
All previous policies, issuances, or part thereof that are inconsistent with the
provisions of these guidelines are hereby repealed.