SCHEDULE ERECTION GIRDER CISUMDAWU

November Desember
Area Durasi Start Finish Girder
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A Mobilisasi
1 Mobilisasi Crane 4 Unit dan Multi exle 2 Unit 7 01/11/2022 07/11/2022 Mobilisasi
2 Assambly Crane 4 05/11/2022 08/11/2022 Assambly
B Inspeksi Crane
1 PJK3 dan Loadtest 1 08/11/2022 08/11/2022 PJK3
C Erection
1 Span A2-P17
Erection + moving 2 09/11/2022 10/11/2022 12 A2-P17
2 Span P16-P17
Erection + moving 2 11/11/2022 12/11/2022 12 P16-P17
3 Span P15-P16
Erection + moving 2 13/11/2022 14/11/2022 12 P15-P16
4 Span P14-P15
Erection + moving 2 15/11/2022 16/11/2022 12 P14-P15
5 Span P13-P14
Erection + moving 2 17/10/2022 18/10/2022 12 P13-P14
D Demobilisasi
1 Dismatle Cane 4 19/11/2022 22/11/2022 Dismantle
2 Demobilisasi Crane 4 Unit dan Multi exle 2 Unit 7 20/11/2022 26/11/2022 Demobilisasi
E Mobilisasi
1 Mobilisasi LG 10 01/11/2022 10/11/2022 Mobilisasi
2 Setting LG 14 02/11/2022 15/11/2022 Assambly
F Inspeksi LG
1 PJK3 dan Loadtest 1 16/11/2022 16/11/2022 PJK3
G Erection
1 Span A1-P1 14
Erection + Lounching 2 17/11/2022 18/11/2022 A1-P1
Span P1-P2
Erection + Lounching 2 19/11/2022 20/11/2022 14 P1-P2
Span P2-P3
Erection + Lounching 2 21/11/2022 22/11/2022 14 P2-P3
Span P3-P4
Erection + Lounching 2 23/11/2022 24/11/2022 14 P3-P4
Span P4-P5
Erection + Lounching 2 25/11/2022 26/11/2022 14 P4-P5
Span P5-P6
Erection + Lounching 2 27/11/2022 28/11/2022 12 P5-P6
Span P6-P7
Erection + Lounching 2 29/11/2022 30/11/2022 12 P6-P7
Span P7-P8
Erection + Lounching 2 01/11/2022 02/11/2022 12 P7-P8
Span P8-P9
Erection + Lounching 2 03/12/2022 04/12/2022 12 P8-P9
Span P9-P10
Erection + Lounching 2 05/12/2022 06/12/2022 12 P9-P10
Span P10-P11
Erection + Lounching 2 07/12/2022 08/12/2022 12 P10-P11
Span P11-P12
Erection + Lounching 2 09/12/2022 10/12/2022 12 P11--P12
Span P12-P13
Erection + Lounching 2 11/12/2022 12/12/2022 12 P11--P12
H Demobilisasi
Dismantle LG 14 13/12/2022 26/12/2022 Dismantle
Mobilisasi LG to Pool 10 21/12/2022 30/12/2022 Demobilisasi

Jumlah 108 226


Note:
1. Semua Pear head Sudah sipa di erection Equipment:
2. Ada crane servis Untuuk Setting LG Crane 180T 2 unit
Crane 120T 2 unit
Multi Exle 2 Unit
Launcher Gantry 1 Unit
Mobilisasi
Demobilisasi
Assambly
Dismantle
PJK3
Erection

You might also like