Title Method Statement – Anti Climb Fence Installation ZONE X SDN BHD
Doc. No Revise No Date
PRE INSTALLATION
Site Preparation
INSTALLATION
1. 300mm x 300mm x 4500mm hole will be dig. The distance between pole is
around 2400mm center to center.
3. Pole will be put inside the hole & level accordingly. Concrete will be poured to
ground level. No beam required
3. After 15-20 fence installed to pole, fence will be level to get straight level on top.
This will be finish level.
POST INSTALLATION
Housekeeping
1. All dirt from dig activity will be remove or flatten around the area.