Professional Documents
Culture Documents
Avinashkumar V. Karre
Author All books published by WILEY-VCH are carefully
produced. Nevertheless, authors, editors, and
Avinashkumar V. Karre publisher do not warrant the information
Worley Group Inc. contained in these books, including this book,
4949 Esssen Lane to be free of errors. Readers are advised to keep
70809 Baton Rouge LA in mind that statements, data, illustrations,
United States procedural details or other items may
inadvertently be inaccurate.
Cover Image: © nostal6ie/Shutterstock
Contents in this book are solely based on Library of Congress Card No.: applied for
the author’s extensive work experience
and knowledge. If part of the book or British Library Cataloguing-in-Publication Data
some contents match with the external A catalogue record for this book is available
source, it would be considered merely a from the British Library.
coincidence.
Bibliographic information published by
the Deutsche Nationalbibliothek
The Deutsche Nationalbibliothek lists
this publication in the Deutsche
Nationalbibliografie; detailed bibliographic
data are available on the Internet at
<http://dnb.d-nb.de>.
Contents
Preface xi
1 Introduction 3
1.1 What Is EPCC Industry 3
1.2 Types of Projects 4
1.2.1 Cost of a Project 5
1.2.2 Purpose of a Project 7
1.2.3 Engineering Needs 8
1.2.4 Licensors Need 8
1.2.5 Profit Based 8
1.2.6 Schedule Based 9
1.3 Function of Different Disciplines 9
1.4 Different Phases of the Project 11
1.5 Importance of Chemical Process Engineers 14
1.6 Interaction with Operating Industry or Customers 15
1.7 Interaction with Vendors 15
1.8 Workshare with Multiple Offices 17
1.8.1 Importance of Workshare 17
1.8.1.1 Low-Cost Services 17
1.8.1.2 Labor Shortages 18
1.8.1.3 Level the Workload 18
1.8.1.4 Time Differences in Countries 18
1.8.2 Types of Workshares 19
1.8.2.1 Workshare with an Individual 19
1.8.2.2 Workshare a Piece of a Project 19
1.8.2.3 Workshare Part of the Engineering Team 19
vi Contents
Questions 147
Answers 149
Acronyms 153
Appendix 155
References 175
Index 177
xi
Preface
Part I
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
3
Introduction
is received by the EPCC, the project is classified into several categories as mentioned
below, and further planning and manpower loading is estimated by the EPCC. Multi-
ple EPCC companies could be required for grassroot projects where the capabilities
and size of a single EPCC may not be sufficient. This is done to meet the desired
project timeline within the planned budget. The type of project is determined by
following categories:
1. Cost of a project
2. Purpose of a project
3. Engineering needs
4. Licensor’s involvement
5. Profit based
6. Schedule based
Engineering No. of
Example of a team size process
Project types Cost involved project (No. of engineers) engineers
some of the utilities are cooling water and instrument air. The tank farm area lead
process engineer is required to communicate with the main process area team where
the raw material and products are designed.
Grassroot projects are larger in size and might not be handled by the customers
or a single EPCC. Multiple EPCC companies are involved, and the project is
strategically divided into sections. For example, a large tank farm area is handled
by an independent EPCC who has expertise in the tank design, the 2nd EPCC is
handling the main reaction, purification, and separation of the processing plant, and
the 3rd EPCC industry could be handling design of utility services (utilities such
as cooling towers and boilers). A unit lead process engineer supervises all the
engineering activities for a unit and there are multiple unit lead process engineers.
Each unit lead process engineer is required to communicate with all the disciplines,
customers, all the EPCCs involved, and interconnecting areas to make sure smooth
transfer of engineering information.
Megaprojects are much larger in size compared to grassroot projects. They are
often rare and involve installation of a brand new plant, e.g. a refinery complex. Mul-
tiple EPCC companies are involved, similar to grassroot projects, the megaprojects
are also divided strategically into sections. Preplanning, communication, coordina-
tion, and consistency among all the EPCCs are key parameters for the successful
completion of megaprojects.
1.2 Types of Projects 7
Some of the projects are driven primarily by emission standards and regulated by
government agencies. To meet the highest or new emission standards, the processing
plant may have to adapt to a new process or a new catalyst. Some of the customers
or operating companies go one step further and desire projects that take care of such
emission standards for next 20–30 years, as long as there is an economic sense. Such
visionary thinking also avoids any future changes to the processing plant, saving
millions for the customers.
make sure that the old existing distillation columns are in usable condition and
minimal civil structural modifications are needed for the columns to keep the
project cost as low as possible.
In other scenarios, the customer could be doing some laboratory experiments, and
figures that by installation of a simple purification process to the already-existing
unit could double their profits in two years.
Profits based on small-cap projects are very attractive to the customers as they
provide high profits with smaller possible capital investment. Another good example
would be replacing existing low-efficiency natural gas burners for a fired heater with
an ultralow NOx burner (ULN). The replacement of burners ensures high efficiency
is achieved in the burners, saving on operating cost of fuel gas with minor capital
investment.
7. Project manager
8. Procurement manager
9. Project controls
10. Project administrations
11. Document control
12. Estimating
Process Engineer:
Primary responsibility of a process engineer is to design equipment, develop equip-
ment specification sheets, catalyst design and selection, develop piping and instru-
mentation diagrams (P&IDs), develop heat and material-balance tables, perform
hydraulic studies, catalyst research, catalyst inventory calculations, participate in
Hazard and Operability Analysis (HAZOPs), participate in 3D model reviews, flare
and relief system design, provide process input for the instrument and line list data,
input to the material selection and plot plan arrangement diagrams, and coordinate
with other disciplines and customers.
Mechanical engineer:
Primary responsibility of a mechanical engineer is to provide mechanical equipment
details to the process specification sheets, prepare bid tabs or compare different ven-
dor quotes, coordinate with other disciplines and vendors, participate in 3D model
reviews, provide mechanical input to the P&IDs, prepare procurement packages for
equipment, and facilitate meetings with vendors as needed.
Piping engineer:
Primary responsibility of a piping engineer is to provide engineering details (such as
insulation and thickness) to the piping line list, develop specialty piping items (such
as steam trap), develop piping specification documents, and coordinate with other
disciplines and customers.
Piping designer:
Piping designers develop 3D models, prepare squad-check packages for piping
isometric drawings, develop isometric drawings, provide piping input to the P&IDs,
prepare piping tie-in packages, and coordinate with other disciplines and customers.
Control-system engineer:
Control-system engineers develop instrumentation specifications, perform instru-
ment sizing calculations, provide input to the P&IDs, prepare instrumentation
installation details, prepare panel layout drawings, prepare procurement packages
for instruments, participate in 3D models reviews, and coordinate with other
disciplines and customers.
Electrical engineer:
Electrical engineers perform electrical load calculations, determine substation/
generator size needed, finalize electrical lighting needed for the process areas,
prepare wiring loop diagrams, provide input to the P&IDs, participate in 3D models
reviews, prepare procurement packages for electrical equipment, and coordinate
with other disciplines and customers.
1.4 Different Phases of the Project 11
Project manager:
Project managers coordinate with other disciplines and customers, supervise cost
and schedule of a project, facilitate meetings for the project as required, solve pro-
ject engineering problems, maintain decision/risk/action, register, control change
orders, and participate in 3D models reviews.
Procurement:
They work closely with other disciplines and ensure that all the items are procured
according to the schedule.
Project control:
They prepare schedules based on input from other disciplines, monitor manhours on
the project, monitor and adjust schedule with changes on the project, track change
orders, and prepare progress reports on a weekly basis.
Project administration:
They provide onboarding guidelines to the new members coming to the team,
arrange meetings, track safety training for individuals, track and maintain project
meeting calendars, and coordinate with several disciplines and customers.
Document control:
They issue all the documents provided to them by different disciplines, track all
vendor documents and their progress, and coordinate with several disciplines and
customers.
Estimating:
They perform cost evaluation of the project in every phase of the project and provide
feedback to other disciplines and customers. They are important disciplines as the
cost results determine the fate of the project.
Each project is sectioned into several phases to ensure that the money spent on
engineering and toward the final installation of the project makes economic sense.
Each phase of the project undergoes a rigorous cost estimate. If the estimated cost
comes out higher than the target price the project is canceled, or further options are
explored to optimize or reduce cost. A brief description of each phase is given below:
Phase 1 – Scope feasibility:
The customer of the project typically has an idea in their mind from very beginning.
Once the contract is given to the EPCC company, the customer and EPCC company
together make progress with the scope planning. Process engineers from the EPCC
company may be tasked to perform several feasibility studies and explore options.
At this stage, there is a high-level technical interaction/meeting with the process
engineer from the EPCC and customer. Process engineer prepares preliminary scope
reports and presents them to the customers in several meetings. Sometimes there
are different technologies available, and the customer and EPCC must choose one
12 1 Introduction
technology that makes economic sense. At this stage of the project, mainly the pro-
cess engineer from the EPCC company is actively involved in the early design and
communicates directly with the customer. The project manager from EPCC has few
responsibilities to document the decisions and track the progress of the phase. Esti-
mating team is involved toward the end of the phase. No drawings or P&IDs are
developed at this feasibility stage.
Phase 2 – Scope definition:
Once the scope of the project is planned, selected, and feasibility is checked, further
definition is done in this phase. Development of a process or a block-flow diagram,
identification of major pieces of equipment, preliminary sizing of major equipment,
and preparing estimated quality P&IDs (sometimes optional) are done in this
phase, and cost of the project is estimated. A project is dead in this phase if the
cost estimates are higher than the target values. The financial risk of canceling
the project at this stage is very low. If the cost estimates are higher, in such cases,
the customer may decide to cancel the project or explore an option to cut a part
of the processing scheme and start in the middle of the process, which may make
the project viable. For example, if the cost estimate for producing product C from
raw material A is very high, the customer may choose to start from raw material B
to get to C. This should work, provided there is an adequate supply and economics
to start with a raw material B. Following two equations show that avoiding a raw
material A in the modified option saves project cost.
phase 4 until all the items reach the project plant site. All the drawings, including
P&IDs, are issued for construction, piping design issues out isometric drawings to
the pipe fabricators, and electrical and control diagrams are issued to vendor for
construction. Frequent meetings related to design changes on various engineering
drawings are held and are approved through management of change (MOC) pro-
cess. Many plant operation people are involved at this stage actively to review the
3D model and provide recommendations as needed. Initially, 60% accurate model
review meeting is held, and based on the comments from various disciplines and
operations, the 2nd 90% accurate model review meeting is held. In this phase, there
are very few unknowns, less than 2%, toward the end of the project, and financial risk
at this stage is eliminated completely, and the customer and the EPCC company are
confident about the returns on their investment and their hard work. It is possible,
but very rare, that the customers may decide to cancel the project at this stage due to
some reasons, e.g. sudden increase in raw material cost at this stage. Ultimately the
customers should decide if the project is making economic sense on a broader scale
based on the cost estimate completed by the EPCC industry.
Phase 5 – Construction and support:
In this phase, all the equipment, piping, control-system items, electrical items, and
civil items are delivered to the plant site. Construction team is involved heavily in
planning and installation of all the pieces of the project. Engineering team from the
EPCC industry provides support to the construction team and answers any questions
they may have. There is no going back on project in this phase as the materials and
pieces needed for the project are at the site. But sometimes due to sudden changes in
global economics and supply/demand logistics, the project may not be feasible at this
stage. Also, if the government agency denies permission to manufacture a product
at this stage, the customers have no choice but to stop the construction process. The
customers may choose to work on recommendations, which costs them some money,
from the government agency to continue with the construction, and make a product
and project feasible.
Phase 6 – Commissioning and start-up:
Before the plant is introduced with a fresh feed, all the necessary plant operators
are trained for operations and safety. These are the personnel who will be maintain-
ing the routine operations of the processing plant. Standard operating procedures,
training materials, start-up and shutdown manuals, equipment manuals, and sev-
eral operation manuals are helpful to these personnel in maintaining the health of
the plant. The process engineers from the EPCC industry develop all these manuals
with support of plant operations and input from the vendors.
In this phase, all the installed equipment, piping, control-system items, and
electrical items are prepared to take a fresh raw material into the process. A team
of operations and engineers go through several preprepared procedures, and
several activities are carried out. All the equipment are hydrotested, all pipe flanges
are checked for leaks, all instruments are checked for their functioning, and all
electrical equipment are tested with standards. If the team finds an engineering
problem, e.g. a leak in major equipment, the problem is solved before they proceed
14 1 Introduction
to the routine activities of the commissioning. Once all is ok, water or cold feed
is circulated through the entire processing plant. Sometimes circulating water
through a system, e.g. reactor filled with a catalyst, is not permissible. Sometimes
the system cannot work on a cold feed, in that case, heating the processing system
or heating the cold feed is necessary. In such cases, the heating system is made
ready first before starting the main process area.
Electrical area
classification to Equipment datasheets to
electrical engineering mechanical engineers
Licensor
Review of engineering Project progress to
documents from project manager and
everyone project controls
Input to cost estimate
Custom
Figure 1.1 A diagram showing interaction of process engineers with other disciplines.
1.7 Interaction with Vendors 15
Table 1.2 Primary responsibilities of a process engineer in all phases of the project.
Process engineering support is required through all phases of the project, and the
information provided by process engineer affects engineering deliverables of other
disciplines. Table 1.2 shows the primary responsibilities of process engineer in all
phases of the project. It is important to note that process engineers are required and
essential in all the phases. It may not be true with other disciplines, for example,
mechanical engineers are only involved from Phase 3 and onward.
The customers and the operating industry have a general idea of outlook of the final
product, and they support the EPCC industry and make decisions. There could be
more than one person from the customer side who would be making decisions. Most
of the decisions are based on solutions and options provided by the process engi-
neers from the EPCC industry. The EPCC company has no clear idea on important
pieces without consulting the customers. Oftentimes, the customers may ask EPCC
engineers to perform studies and present options before making decisions.
The customer has a key role in the project as they supply information on design
guidelines, information on feed and product compositions, and item specifications
as needed. Sometimes the specifications and guidelines desired by the customers
are not suitable, and the EPCC process engineers should communicate the need
or deviation with the customer. Several addendums and revisions to customer
specifications may be required specific to the project. It is important to have the
latest customer design guidelines practiced by all the EPCC engineers involved in
the project. If a certain guideline is not available, the customer may ask the EPCC
process engineer to prepare one with their support.
Interaction with vendors is very important in any project. There could be more than
one vendor involved in a project. On a larger project, several vendors are involved in
16 1 Introduction
providing several designs and support. Vendors are typically involved in the project
toward the beginning of Phase 4 or detailed design. Several meetings may be required
with vendors to come to agreements and terms. At the end of selection of a vendor,
a delivery schedule and delivery plan are discussed. A delivery timeline for the item
associated with that vendor is then tied to the overall project schedule. Delivery plans
Process engineer
answers questions from Purchase an order
a vendor and tracking
of the goods supplied by the vendor are discussed with the construction team and
special shipping arrangements are then planned, if needed. For example, delivery
of a 600 Klb/h steam boiler from Dubai needs a large barge. Figure 1.2 shows an
interaction of a piping vendor with the EPCC team. Table 1.3 shows classification of
vendors based on their function.
Sometimes the home office where the project is being executed may not have all
the engineering labor support to meet the schedule requirement, and sometimes
the home office is looking for expertise in certain areas of the project within the
company. All such scenarios result in needing workshare with other offices. The
workshare office must provide high-quality results within the schedule requirement
specified.
Table 1.4 Comparison of cost of living in India vs. United States [1].
% of higher cost
in USA compared
Parameter Country: India Country: USA with India
varies anywhere from US$ 200 to US$ 300 per month as compared to US$ 4000–US$
5000 in western countries. When the salaries are compared, it’s very attractive for
an EPCC industry based in a western country to do business with the low-labor-cost
countries.
Project#1 Project#2
Home
Project#3 Project#4 International
Office
pool of talent
Figure 1.3 Importance of workshare, manpower loading, labor shortage, and low cost.
1.8 Workshare with Multiple Offices 19
send the instructions to the workshare office and by the time the home office wakes
up, the workshare office may have completed the work within 11–15 hours. The
home office engineer can present these results, produced by the workshare office,
straight to the customer, saving time on the project. The EPPC industry can work
round the clock with the help of workshare office, which is the biggest benefit.
Home office
(Process
• Line list to piping design and
• Line list engineering)
piping engineering
• P and IDs • P and IDs to project teams
• Equipment design • Filled out line list • Equipment design to
• Relief valves • Marked P and IDs mechanical engineering
• Instrument data • Completed equipment • Relief valve and Instrument
and relief valve design data to control system
• Completed Instrument engineering
Workshare office
datasheets Home office
(Process
engineering) (Project
engineering)
Figure 1.4 Flowchart of process engineering activities between home and workshare
offices.
21
Part II
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
23
of a complex study is the study of arrangement of several heat exchangers in the pre-
heat train of the crude and vacuum distillation units. There could be more than 30 to
40 heat exchangers interlinked with each other in the preheat train. To determine
the optimal arrangement of complex network system, the chemical engineer uses
software called pinch-point analysis. The engineer produces a report based on the
software work. Not only the chemical engineer has to first figure out how to arrange
these exchangers but also the engineer has to make sure the arrangement is optimal
and works with different simulations and heat and material balances. There could
be more than five or six simulation cases depending on the start of run, end of run,
the type of crude, the type of product to be made, and different operating philoso-
phies. So, depending on different modes of operations, the chemical engineer must
complete these studies, simulations, and eventually develop the heat and material
balance tables.
Another example of a complex study is checking the adequacy of the existing
equipment, instruments, and piping for the new anticipated flow rates and com-
position. In this study, the engineer should perform or develop several simulations
and heat and material balances. The engineer may also have to rate or check if some
of the critical equipment is reusable, for example, a study involves checking to see if
a compressor can be reused for the new anticipated rates or composition.
Process
For a e
engineer Information
No
completes provided to a
study process engineer
Study
Revise report to
customer Note action
No Study report for review items if any
acceptable?
Input to
Action item
review
Yes register
Study duration
e
and number of Customer and Project
studies process documentation
engineer
discussions
Figure 2.1 Flowchart for the process engineering studies in the scope planning phase.
of the study, the action plan; and the information required is noted in the product
register. Appropriate action items are assigned to either a chemical engineer or to
the customer, and the information required is provided by the customer. About one
to two weeks are assigned to finish up or resolve those action items, and once those
action items are resolved, the process engineer completes the analysis and calcu-
lations and comes up with the recommendation within two to three weeks. Once
the studies are complete, the process engineer provides the recommendations and
preliminary report to the customer. About two weeks are given to the customer to
review and provide comments. After two weeks, the comments provided by the cus-
tomers are received by the chemical engineer. A second meeting is arranged to go
through the recommendations as well as the comments provided by the customer on
the study reports. If the comments on the reports are extensive, the chemical engi-
neer is asked to revise the report, redo the study, and resubmit, and the previous cycle
begins again. If both the parties agree with the resolutions and the comments, then
the process engineer finalizes the report of the study in one to two weeks. The final
report with the previous customer comments and the revision history is submitted
through the document control to all the parties involved in the project. A complete
flowchart for the process engineering studies is shown in Figure 2.1.
Similarly, the design basis for other equipment, such as pumps and heat exchang-
ers, should be explained in an adequate depth by the process engineer so that all the
parties involved understand the basis.
2.3.2.4.2 Wet Signatures of the Parties and Issuing Through Document Control When
the study is complete, it is required to have approval from the customer, primarily to
document, that the conclusion from the study has been accepted or agreed upon. It
is common practice to get a wet signature from the different parties involved. Those
different parties are the engineer who completed the study, the checker who checked
the study for correctness, customer who approved the study, and the project man-
ager who agreed with the overall outcome of the study in relation to the project.
Table 2.1 shows different signatures required for the approval of process engineering
study reports.
Table 2.1 Signatures required for the process engineering study report.
Action item
assigned to
Action customer or Expected Current Previous
Study Study item EPCC process completion study status week status Study %
No. description description engineer date notes notes complete
In addition to the contract given to the technology companies, the process engineer
also provides ongoing support to ensure that the technology selection is made in the
time frame discussed earlier with the customer. Sometimes, the process engineer
from the EPCC needs to get additional information from the customer.
Continue Technology
with the option action Meeting with
No
project items EPCC and
customer
e No
EPCC process
engineer EPCC process
reviews all engineer narrow
technical down to 2–3
Yes EPCC process
reports technology options?
engineer
provides help
Meeting Yes
Yes
between EPCC Reports
process acceptable?
engineer and
Initiate
the customer Information contract
Technology or help with the
companies needed to technology
complete work No technology companies
and provide companies?
Additional reports
meeting No
needed with Revise
technology Yes meeting
companies? needed with
Any pending
technology e
items?
companies
No
Technology
selection is Yes
made No
3.1.4 Examples
BFD does not show any flow rates, pressure, or temperatures. It is a connection of
several square blocks through a connecting line. Figures 3.1 and 3.2 show examples
of a BFD and a UBFD.
Nitrogen
Boilers n
Power Instrument air
supply
and UBFDs are also needed to get the funding for the next phases of the project.
Also, these block diagrams represent high-level information about the process and
are helpful to explain to newly joined engineers in the team.
Ultrasmall 1–2
Small cap 3–5
Midsized 7–20
Large 21–40
Grassroot 41–60
Mega 61–100
H-100 D-100
Fired heater Distillation
tower
D-100
H-100
equipment. Also, note that rotary equipment, such as pump, is located at the bottom
of the PFD, and static equipment is located in the main area of the PFD.
P-101
TK-103
TK-104 TK-105
Tank P-101
car Transfer pump
3.2.4 Example
Figure 3.4 shows an example of a PFD.
P-101
Tank P-101
car Transfer pump
is sufficient for Phase 2. Very minimum details to the instruments are added. The
line number, instrument number, equipment number, and any electrical loop num-
ber are not added at this stage. Equipment sizes are not shown on the P&IDs, as they
are already shown in the equipment list. There are several hold notes added to the
P&IDs, and the details of the hold note information are needed for further follow-up
in the next phase. Relief valves are not evaluated in phase 2, and the engineer may
choose to show a placeholder just to give something for the estimating. Flare design
is typically studied as a part of feasibility studies, and if the determination is made
to add a new flare, few details of the flare could be added in this phase. The details
of utilities are not shown in Phase 2, as these details will be further developed in
the next phases. The pump seal plans and a plant compressor seal plan details are
also undeveloped at this stage because the seal selection is not done in phase 2. An
example of a P&ID is shown in Figure 3.7.
E-01
V-01
T-01
P-01
(a)
Pump P-01
MF-1-5
B.L.
FT
01
Instrument Instrument
air air
UF-1-1 UF-1-2
From To tower
compressor T-02
C-01
Filter V-01
Reactor R-01 MF-1-6
MF-1-1
Tower T-01
(b) MF-1-3
space planning purposes. This is because according to the National Fire Protection
Association (NFPA) codes, fired heaters need to have a 40-ft clearance around them,
meaning no other equipment is allowed within 40 ft of radius.
Also, if the plot space is tight, the process engineer needs to mention which level
each equipment can be accommodated, and there are some special free training
requirements that should be clearly indicated on the P&IDs so that the piping design
team can locate the equipment accordingly. In such cases, the equipment must be
located at top level of the structure so that it free drains to the downstream equip-
ment. All the rotary equipment, such as pumps and compressors, are located at a
grade level. All the exchangers on the project, to minimize this pipe run, are located
in a common structure. Bigger equipment, such as distillation columns, needs to
have some access for the operators to climb and do maintenance. There may be
some underground equipment, such as vertical underground fire water pump, in
such cases, the civil engineer should make sure the soil conditions are suitable for
the installation of the underground equipment. Some special equipment that is very
tall in the structure, such as a column as high as 220 ft in the air, needs to be evalu-
ated for the wind loads. Hence, identification of the major piece of equipment is very
important in the determination of plot space in early phases. As the current phase
goes to the next phase, the scope develops, and more information on the equipment
is available, and the plot space gets rectified.
The process engineer should make sure to show enough details on the P&IDs so
that the preliminary plot space can be developed.
Civil engineers may not get all the information from the P&IDs or equipment.
In the early phases, if the civil engineers are involved to help estimate, civil engi-
neer would ask for the rough order of magnitude of the equipment sizes so that the
number of piling and the concrete requirement for that piece of equipment can be
estimated. It is too early for civil engineers to be involved in this phase. A common
practice is estimating the cost of the project based on the database that the cost esti-
mating has in the software. The estimating software can come up with rough order
of magnitude of the concrete and the piling.
of an exchanger as 42-in. ID (inside diameter) and 20-ft length AEU type exchanger.
The mechanical engineer may provide additional information required for the cost
estimation based on previous experience on other projects. Another example would
be the process engineer providing basic performance data for a pump, such as
100 gallons per minute at 230 TDH (total developed head) and density of a liquid.
This may not necessarily provide the size of a pump itself, so mechanical engineers
may use this preliminary information to provide a size and a model of the pump
for the cost estimating. Mechanical engineers would look at catalogs and previous
vendor or project information. Similar basis is true for controls and electrical
engineering as well.
Pumping Estimated
Pump Quantity Flow TDH 𝚫P Specific temperature motor
tag no. of pumps (gpm) (ft) (psi) gravity (∘ F) size (hp)
P-XXXX
3.5 Estimate Preliminary Sizing of Major Equipment and Instruments 41
low NOx burner should be mentioned. Other design parameters, such as the oxygen
percentage in the stack, the flame temperature, the fuel gas pressure, temperature,
and the pressure drop across the heater, should be clearly mentioned. The process
engineers may not size the actual heater, but the performance data provided by them
are used by the vendor or the cost estimate to come up with the sizing and costs.
Vessels are very easy piece of the project. The process engineer should consider
the streams involved, holdup time, and separation efficiency as required.
T-01
Table 3.3 Equipment list given to the project and mechanical engineering.
Design
Motor estimated
Insulation (Y/N)
Temperature, ∘ F
Equipment type
New Equip. No.
Pressure (psig)
Capacity/Duty
HP/Voltage
or Diff. Head
Construction
Dimensions
Material of
Scope (New
Description
Modified)
Quantity
power source required for the project. Note that in this phase, as very little informa-Type
tion is known, process engineer assumes efficiencies of the motors and the rotating
equipment to get an approximate power estimate. It is always important for the elec-
trical team to add some additional design margin to account for the approximate
estimation. If the electrical team is not involved earlier in the phases, then the cost
estimate can use the data to come up with the sizes of electrical stations using the
software and the database available. Table 3.3 shows an equipment list produced by
a process engineer in Phase 2.
carbons attack carbon steel. This is mitigated with chrome alloy 5 Chrome/9
Chrome/12 Chrome
– 5 Chrome 400–550 ∘ F
– 9 Chrome 550–650 ∘ F
– 12 Chrome over 650 ∘ F
● Naphthenic Acid Attack of Gas oils with high Naphthenic Acid concentrations
(total acid number [TAN] > 1.0)
– Above 450 ∘ F/high velocity, the 316 SS has experienced excessive corrosion
– Sulfur species can “help” form a passive layer on the base metal improving
resistance
– Typically, 317 Stainless Steel (>2.75% Moly) mitigates the problem
● Hydrogen embrittlement – due to “wet” Hydrogen Sulfide or High Hydrogen
Partial Pressure/Elevated Temperatures
– Up to about 400 ∘ F, Carbon Steel is good for all hydrogen partial pressure
applications
– Over 450 ∘ F, need to look at the “Nelson Curves” that plot hydrogen partial
pressure vs. Temperature (warning, the 0.5% Chrome should be same as carbon
steel)
Customer’s Name:
Project name:
Unit:
Project #:
PFD#: Simulation case description:
Stream No. 1 2 3
Stream phase Vapor or liquid Vapor or liquid Vapor or liquid
Pressure (psig)
Temperature (F)
Total mass rate (lb/h)
Composition (wt%)
Component 1
Component 2
Component 3
Component 4
HOR
X-100 X-134 X-127
Temperature XX F
DUTY XX Btu/hr
Pressure XX psig DUTY XX Btu/hr DUTY XX Btu/hr
Feed Temperature XX F
Mass Flow XX Ib/hr Feed Temperature XX F Feed Temperature XX F
Product Temperature XX F
Specific Gravity XX Product Temperature XX F Product Temperature XX F
X-100
5 Reb
12B 1 1st 10
FCV loop 12B X-100 8
Temperature XX F 12A MIX-102 TEE-101 Temperature XX F
11
Pressure XX psig
Temperature XX F
2 9
X-127 Pressure XX Molar Flow XX Ibmole/hr
TCV X-127 MIX-100 psig
vap X-134 Mass Flow XX Ib/hr
3 Line loss and other unknowns
12 bypass
V-100 8
HOR Mass Flow XX Ib/hr Pressure Drop XX psi
X-134
11
A pump HOR to 13
H-1 Line loss and
X-125 drum
ADJ-1 dis TEE-102 energy 12 bypass X-189 7
MIX-101 other R
dis unknowns RCY-1
12 6 7
P-100 X-125
Pump H-1 TEE-100 4 X-189 Mass Flow XX Ib/hr
suction
P-100 H-1 energy X-125 X-189
Delta P XX psi Heat Flow XX Btu/hr DUTY XX Btu/hr XX Btu/hr
pump DUTY
Power XX hp 12 Feed Temperature XX F Feed Temperature XX F
Temperature XX F Product Temperature XX F Product Temperature XX F
Pressure XX psig
Some unfinished studies from previous phases should be finished in this phase. If
the data are available, the study can be completed in this phase. If not, the timeline
is discussed with the customer and the study is to be completed in the next phase of
the project.
Some of the studies, such as flare studies, were not able to complete because of
lack of the data in the previous Phase 1, the process engineer can complete such
studies in Phase 2. If the data are still not available, the process engineer can initiate
a request for the data, and the customer can start gathering the information needed.
Sometimes to complete a study, information is needed from the technology company.
During the progress of Phase 2, there could be a need for several additional studies.
Some studies can be quickly completed in Phase 2, and some may not be approved,
such studies that cannot be completed are carried forward to the next phase of the
project. As discussed previously, the preparation of the study approval process and
the documentation are similar to process mentioned in Phase 1.
Blowdown, lb/hr
Equipment tag #
Chemicals, lb/hr
Nitrogen, SCFH
Plant air, SCFH
Service
P-100 Feed 50 0 0 0 0 10 0 0 0 0 0 0 0
pump
E-100 Columns 0 0/15, 0 15, 0 0 0 0 0 0 0 0 0
reboiler 255/0 255
Idea # Title:
Status: Approved Y/N Description of idea:
Date submitted: Created by: Project phase:
Originating office: Project#: Customer name:
Hazardous L M H L M H L M H
event o e i o e i o e i
likelihood w d g w d g w d g
h h h
Minor Serious Extensive
Hazardous event severity rating
(a) One Level 3 SIF does not provide sufficient risk reduction at this risk level. Additional modifications are required to reduce risk.
(b) One Level 3 SIF does not provide sufficient risk reduction at this risk level. Additional review is required.
(c) SIS independent protection layer is probably not needed.
(d) This approach is not considered suitable for SIL 4.
carried out. The HAZOP is a risk assessment methodology for evaluating hazards
involved in the process. If there are hazards involved, then the recommendation is
made by the team. The recommendation is captured by the process engineer quickly,
and the P&IDs are marked that way if it is easy. If it is a complex recommendation,
then a hold note is added to the P&ID, and it is followed up in the next phase of the
project.
Later “issued for design” datasheets for all the equipment are used by mechani-
cal engineers to develop mechanical datasheets. Process engineers add details to
the P&IDs based on the sizing of the equipment, heat and material balance, and
information from the licensor vendor. These preliminary P&IDs are reviewed by the
customer engineers and other disciplines. The comments provided in this meeting
are later picked by the process engineers and the P&IDs are “issued for HAZOP.”
Once the hazard operability study (HAZOP) is complete, the HAZOP provides a list
of recommendations to the process engineers. Process engineers go through the rec-
ommendations and update P&IDs and the design of the equipment as necessary.
Process engineers later issue P&IDs for design.
It is important to know that the quality of information provided by the process
engineer in this phase is much better than in the previous phases because lot
of information is available for process engineers to produce a good engineering
design. Sometimes the information is not available and process engineers are
required to assume or make a good engineering assumption. At the same time,
the piping engineers and design team develop a 3D model based on the P&IDs.
Based on the progress of the P&IDs, the process engineers are required to assess the
requirement of relief valves in this phase and come up with a preliminary sizing
and mark it on the P&IDs. Apart from all the work, the process engineer should
participate in several meetings, lead the workshare meetings, provide input to all
the disciplines, and also meet with the customers and resolve when comments or
questions are asked.
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
52 4 Phase 3 (Scope Development)
plot-space drawing, and the information of the new equipment is based on the design
being done in this phase.
If it is a new pump, preliminary pipe lengths are estimated based on a preliminary
arrangement of the equipment with additional design margin to account for the
fittings and elbows. Once the hydraulics are done, the process engineer provides
information to the entire project team and the customer. Depending on the service
of the pump and experience of the customer with that pump service in other units,
the customer may ask to perform or double-check the hydraulics assumptions based
on the detailed isometric drawings. Note that in the timeframe of Phase 3, the piping
isometrics for the new section of the piping may not be easily available. The process
engineer requires isometric drawing from piping design. Process engineer checks
the hydraulics one more time based on the very preliminary isometric drawings to
make sure early assumptions were all correct. If the assumptions are somewhat con-
servative and simple in nature and do not affect the mechanical design of the pump,
the process engineer is not required to update the design of the pump because by that
time or toward the end of Phase 3, mechanical engineers may have selected vendor
and finalized the model for the pump. So, it is a rework for mechanical engineers
for a small change if it is not required and it is made. On the other hand, based on
the checking if found that the earlier design was not conservative or underdesigned,
then the process engineer is obligated to update the previous design and notify
mechanical engineer accordingly to stop previous work and modify the design as
necessary.
to account for few unknowns (such as fouling rate increase over time), to provide
some flexibility to the operations, and to provide some future expansion capabili-
ties. Below are some overdesign factors considered for design of a new pump. Note
that the design margin for few services, such as reflux pump, is somewhat higher
than other services. This is because these services are more critical to the operation
of the unit. Table 4.1 shows examples of design safety margins used for few pump
services in a refinery.
Velocity (ft/s)
Comments
𝚫P/100 ft
Line No.
Service
54 4 Phase 3 (Scope Development)
Other equipment, such as heat exchangers, vessels, and columns, are managed a
little differently than pumps. It is necessary and important for the process engineer
to complete the design of such equipment as accurately as possible.
When designing the heat exchangers, the processing engineer uses software called
heat transfer research institute (HTRI). The process engineer should make sure that
design for all the simulation and heat and material balance cases must come up with
a conservative design after adding additional design margin, as required by the cus-
tomer. In addition to that, process engineers must keep in mind the fouling factors
based on the services. Table 4.4 provides few examples of fouling factors used in the
industry. Excessive falling fouling factor can overdesign the exchanger vastly and
lower fouling factor usage can under design the heat exchanger. In such cases, it is
important for the process engineer to note down all the fouling factors that he or she
planned to use in their design and get approval from the plant engineers to make sure
they agree with the fouling factors. Also, the customer can provide valuable feedback
on the fouling factors for different services based on the existing plant operations.
Also, there are some criteria as laid out by the customer regarding how much pres-
sure drop a process engineer can allow on shell or tube side of the exchanger based
on the viscosity of the fluid. There are some thumb rules process engineers must
know, which also come with experience. Table 4.5 lists some thumb rules used in
the industry for the shell and tube heat exchangers. As an example, high fouling
Table 4.5 Thumb rules used for choosing the side of a shell and tube heat exchanger.
services, such as vacuum bottoms, should be placed on a tube side because tube
sides are easy to clean compared to shell sides.
4.2.2 Vessels
Vessel is a storage and separation equipment used in all chemical and refining
plants. There are two types of vessels. One type provides a hold-up time and second
type does the actual separation between two or three phases. Process engineers
should follow the guidelines provided by the customer’s design guideline manual,
and design the drums accordingly. It is important for the process engineer to
understand the implications of not following the guidelines. Below are some
examples of implications:
Example 1 – The hold-up time for many vessels required is 10 minutes to protect
the downstream or upstream equipment. The feed drum of a processing unit is
designed for 10 minutes of residence time to provide the adequate residence time
needed. If the upstream process unit is tripped in this situation, the reactor feed
pump, connected to the feed drum and delivering liquid to a reactor, can provide
adequate time to the reactor for safe shutdown. Essentially, this provides a critical
time for the operator to safely shutdown the reactor.
Example 2 – Another example is the reflux drum connected to the column overhead
system. Adequate residence time is provided to the reflux drum to provide ade-
quate reflux to the column just in case the condenser fails. This scenario provides
the operator with crucial time needed to safely shutdown the column without
causing any upsets or damage to the column trays or packing.
Example 3 – Another example of the separation of three phases in the amine flash
drum. In the amine flash drum, hydrocarbons gases dissolved in the rich amine
are separated from the trace amounts of oils present in the rich amine. To design
the amine flash drum correctly, the vessel is typically sized to provide 30 minutes
of residence time to provide adequate separation time between hydrocarbons and
the amine. If the rich amine flash drum is not designed adequately to separate
trace amounts of hydrocarbons from the amine, the hydrocarbons can carry over
to the lean amine and further may end up in an amine acid gas. This amine acid
gas further feeds to the sulfur recovery unit, and any trace amount of hydrocar-
bon can cause the sulfur recovery unit to experience severe process upsets due to
higher concentrations of hydrocarbons. So, it is important for the process engineer
to understand the implication of not designing as per the guidelines
4.2.3 Columns
Similarly, for the columns, the process engineer should understand the implications
of not designing a column correctly. For example, if the column is not designed cor-
rectly, the flooding number might exceed 80% and column trays might flood. This
has a direct impact on product specification in the column, and the operator may not
be able to meet the product specification needed if the original design is incorrect.
4.3 Input to Line List and the Process 57
MSDs Isometric
Line drawings
list
P and IDs Relief valve
input design
and
Equipment Piping Basis
datasheets output
documents
Pipe
specifications Paint and insulation
specifications
Figure 4.1 Line list input and output tree. UFD, utility flow diagram.
58 4 Phase 3 (Scope Development)
Process Engineer’s
Item # responsibility Description
1 Description of This explains Fluid Services, e.g. vacuum bottoms, and raw
service crude
2 Type of fluid This explains a group of fluid service codes. The type of fluid
in the piping system could be, e.g. steam, water, and crude
3 Specify blowdown This shows whether or not the line is blowdown or relief line
or relief line
4 Specify slug flow This shows whether or not the line is expected to be a slug
or not flow
5 Phase of the fluid The phase of the fluid contained in the piping system at
(Liq/Vap/Mix) normal operating conditions, e.g.
liquid/vapor/mixed/slurry/solid
6 Density The density of the process fluid at normal operating
conditions should be specified. This is a determining factor
in the weight analysis of the piping line. For mixed phase,
density of vapor and liquid shall be provided (i.e. 0.03/62.4)
along with normal average density
7 Vibration This density is used for calculation of maximum 𝜌V 2
8 Toxic/Lethal Intended to inform piping design per ASME B31.3
9 Erosive Indicates whether or not the line has an erosive fluid
10 Corrosive Indicates whether or not the line has a corrosive fluid
11 Normal operating This is the normal process or utility fluid pressure that the
pressure equipment and piping system will be exposed to in routine
operations
12 Normal operating This is the normal process or utility fluid temperature that
temperature the equipment and piping system will be exposed to in
routine operations
13 Mass flow rate The mass flow rate is used to calculate velocity and
maximum 𝜌V 2 , which is used as a starting point for
evaluating if a line experience vibrations
14 Velocity Flow velocity shall be specified
15 𝜌V 2
Supply 𝜌V 2 (consider worst-case and add other child
diameters as necessary for the line), which is used as a
starting point for evaluating if a line may be subject to
vibration concerns. Engineer must also consider other
modes of vibration, such as high-frequency
acoustic-induced vibration (AIV), pulsation study for
reciprocating compressors/pumps, and hydraulic transients
(water hammers)
16 Alternate Alternate operating case definition is per project
case – (upset) requirements – steam out, catalytic regeneration,
pressure blowdown/relief, etc.
If no alternative operating scenario enters N/A
4.3 Input to Line List and the Process 59
Process Engineer’s
Item # responsibility Description
Process Engineer’s
Item # responsibility Description
Process Engineer’s
Item # responsibility Description
● Cold Conservation
● Personnel Protection
● Sound Attenuation
● None
34 Heat tracing type The type of tracing to be used to maintain a predetermined
temperature. This should be determined at the beginning of
the project and will not change during the course of the
project.
Based on customer criteria. Typical examples:
● Steam Tracing
● Electric Tracing
● Glycol Tracing
● Steam Jacketing
● Freeze Protection
● Other
● None
35 Tracing HOLD The temperature that must be maintained inside the piping
Temperature by the heat tracing applied
36 Tracers – Number Assign the number to identify the tracers
37 Tracers – Size Enter size of tracers
38 Notes/Remarks Specific comments related to the piping system as required
by Process, Piping Design, or Piping Engineering
Process Notify
piping Piping design to Notify Process engineer
engineer adds process
design add basic line to add process
new lines to engineer
information information
P and IDs
Revise Notify
piping
Line list status Yes engineer
changed to No
approved and Piping engineer
IFC issued Specification
adds their
burst?
information and
Piping design to perform flange
use the final list rating calculations
for development
of isometric
drawings
Table 4.9
Table 4.8
Table 4.7
psig Press Fluidphase
Upset Conditions
psig Coin. Upset Press Max Temp @ Existing Pipe
Paint Spec
Coincident Pres
Max Temp Basis
Color Code P&ID No.
Short Term Basis
Piping design responsibility columns of the line list.
Type Insulation
°F Temp
Type
sibility columns in the actual line list document for different disciplines.
Tracing
Lvl °F Maintenance Temp
Stress Analysis
Calc. No. Remark
guidelines. Note that the customer must sign off or agree on a deviation before the
deviation can be implemented into the project. Tables 4.7–4.9 show different respon-
4.4 Create Change Orders and Report Any Changes to Project 63
Customer’s name
Project No.
Project name
Location of plant
Unit No.
Change originated by Change submitted date MM/DD/YY
Originator discipline Originator lead’s name
Change requested by Customer/EPCC Project manager handling
the CON
Service description
Process comment
Instrument type
Maximum flow
Checked by
Fluid name
Flow units
P&ID No.
Tag No.
Rev
Process comments
Shut off D/P (PSI)
Instrument type
Tag number
P&ID No.
Fluid
State
4.5 Process Data for Inline Instruments 65
Table 4.13 Template for control valves and pressure regulators instrument data.
Line/equipment no.
Equipment number
Critical pressure
Instrument type
Failure position
Design T, deg F
Viscosity, CP
Tag number
Checked by
Norm flow
P&ID No.
Max flow
Function
Pipe spec
Min flow
Revision
Remark
Fluid
State
balance table. The maximum flow rate is 110% of the normal rate, and the mini-
mum flow rate is about 50% of the normal flow rate. Before working on the actual
datasheets of the control valves, process engineers should reach out to the customer
and make sure the philosophy of the flow rate is agreed upon.
For inline meters, the same maximum and the normal flow rate philosophy is
used, and the pressures are based on the hydraulics of the control valve. The on–off
valve and the shutdown valves are very simple instruments and do not have the pres-
sure drop as they are fully open valves. The flow rates for the on–off valves are similar
to the logic mentioned earlier for the control valve.
Notify Process
Control system Notify
New instruments control engineer
eng. creates data process
added to P and ID system adds data
request engineer Notify
by a process eng.
spreadsheets control
engineer Process system
engineer engineer
to revise
No Control system
Controls system
eng. performs
Notify eng. prepares Result preliminary
process official datasheets Yes ok? calculations
engineer
Revise
Squad No
check Data
Datasheets Receive
acceptable? Yes quotes from
to vendors
vendors
Control system
Input to cost
prepares cost index
estimate
spreadsheet
Controlling scenario
Item (most likely)
Table 4.15 Examples of relief valve inlet and outlet pipe sizes
based on PSV size.
1D2 2 3
1.5G3 2 4
2H3 3 4
2J3 3 4
put on the P&ID with the hold note saying that “this is preliminary sizing and to be
confirmed in the next phase.”
Isometric piping drawing information for the relief valve may not be available in
Phase 3. The primary objective of Phase 3 is to figure out the need for a relief valve
and a preliminary relief valve size. As the piping isometric drawings are not avail-
able in Phase 3, there is not much effort put in place to estimate the PSV inlet and
outlet pipe sizes. If it is existing relief valve, the process engineer may quickly check
the adequacy of existing PSV inlet and outlet pipe sizes. If the pipe size for the exist-
ing system is inadequate, the process engineer could flag the pipe changes on the
P&IDs and notify piping design. If none of the information is available, which is
more likely, the process engineer may assume one line size higher for the inlet and
outlet based on the relief valve flanges, and preliminary sizes are marked on the
piping and instrumentation diagram (PIDs.) Few examples of relief valve inlet and
outlet piping sizes are shown in Table 4.15. Table 4.16 shows an example of tracking
spreadsheet for the PSVs.
68 4 Phase 3 (Scope Development)
Discharge location
PSV number
Comments
Scenarios
P&ID No.
PSV size
Service
Once a process engineer completes a design of equipment, it first goes through the
checking process. If there is a comment from the checker, the process engineer picks
up those comments and gives the design folder back to the checker for final approval.
Once the checker finally approves the design, the process engineer is ready to issue
the datasheet to mechanical engineer. If there is a need to make changes to the
equipment or updates after this point, the process engineer updates the design folder
internally without any formal issue.
The process engineer must issue datasheet to the mechanical engineer as well as
the customer. For the first revision, the datasheet goes out to the mechanical engi-
neer as well as the customer, and then two weeks are given for the review and com-
ments. After two weeks, the comments are picked up by the process engineer, and
the datasheet is revised to Rev. B, and issued for information. Any further changes
after that point are clearly marked in a different color under datasheet to distinguish
from the previous marks and are issued as Rev. C and Rev. D. Once the P&IDs are
issued for approval (IFA), the datasheet is issued as IFA, capturing any comments
until then and clearly marking them in a different color to distinguish from the pre-
vious revisions. Once P&IDs are issued for design toward the end of Phase 3, the
datasheet is issued as Rev. 0. This Rev. 0 is issued for design datasheet, and this
means the mechanical engineer can take this datasheet and go out to the vendor
to get the vendor quotes. Any further changes after this point are marked as Rev. 1,
Rev. 2, and properly notified to mechanical engineers as needed. Table 4.17 shows
different revision cycles for mechanical equipment datasheets.
It is important that process engineer should carefully add notes to the datasheet
to avoid any confusion. For example, there have been cases where process engineer
does not add clarification on the net positive suction head (NPSH) margin added for
the pump datasheet, and this datasheet goes on to the mechanical engineers. It is
4.7 Prepare and Issue Equipment Datasheets 69
interesting to note that mechanical engineers have their own guidelines to add NPSH
margin if it is not clearly noted on the P&ID or datasheet. So mechanical might end
up adding the NPSH safety margin in addition to the process engineer’s margin. This
could be a double-dipping in the design margin that has additional costs associated
with it. Process engineers should be careful with the notes and the clarifications just
to make sure there is no overkill in the design, and clear communication is made
with other disciplines.
Once all the issued for design (IFD) datasheets are issued for all the equipment,
IFD design folders are issued to the customer. Any further updates, such as change
in nozzle sizes, are made during the close-out documentation. Figure 4.4 shows a
workflow process for developing mechanical datasheets.
Revise
No Issue for review
Yes (IFR-Rev. A)
No datasheet to
IFI-Rev.C mechanical
If any
changes Comments? engineering and
customers
Issued for
Datasheets information
issued for (IFI) – Rev.B
approval Issued for
(IFA) along design (IFD- Mechanical Vendor performs
with P and IDs
Rev. 0) engineering prepares calculations
vendor packages and
send to vendors
Any process
updates after Quotes
Mechanical from
IFD-Rev. 0 IFD-Rev. 1
engineering takes vendors
issue?
the revised data and
sends to vendors
Input to cost
estimate
Likelihood
Consequence
low flow, and HAZOP team then talks about what will happen if no safety majors are
not available. Then the HAZOP team lists down all the safety measures available to
mitigate the hazard concerns. Also, the HAZOP team should go through the severity
and likelihood for each node. For high severity and likelihood items, the team pro-
vides a recommendation of adding a new safety device or an instrument. Table 4.18
mentions the severity and likelihood of an upset event.
Process engineers should prepare following documents for HAZOP. It is important
to be as prepared as possible because the HAZOP team is looking for quick answers.
● Line list document
● Pump deadhead calculation summary
● P&IDs drawings
● Process-Flow Diagrams (PFDs) drawings
● HMB tables
● Utility summary table
● Design pressure and design temperature diagrams
● Design basis
● Battery limit table
● Equipment datasheets
Table 4.19 Phase 3 revision cycles for P&IDs/PFDs/MSDs (including tie-in/demo P&IDs).
TP TP
x x
(a) (b)
Figure 4.5 Example of (a) demolition (demo) and (b) tie-in P&ID drawings.
Table 4.20 Segregation of the process systems by P&ID number and by service.
Raw crude tank farm area Raw crude tank DN-1, DN-2, DN-5
Utilities to raw crude Utilities UDN-5, UDN-6
tank farm area
Raw crude preheat area Raw crude preheats DN-6, DN-9, DN-10
Utilities to raw crude Utilities UDN-7, UDN-10
preheat area
As mentioned earlier, in every phase, the process engineer must update the design
basis as the design progresses. Similarly, toward the end of Phase 3, the process engi-
neer must issue IFD quality design basis document. This document has an update
from any previous phases. This document contains the design information basis
information for equipment, preliminary relief valve calculation summary, a basis
for instrument data, a basis for heat and material balance, summary of any studies,
and any items that are to be followed up in the next phase.
any revisions in Phase 3. But it may be necessary to update the overall HMB for the
project depending on any simulations and updates from the licensor.
For some of the HMB, areas may not be available, for example, the utility area may
not have a HMB, for this area, typically utility summary and usage are issued and
considered as a HMB document.
D-100
Design pre: 150 psig
Feed tank
Design temp: 150 f
D-100
Deadhead pre: 142 psig
Design temp: 150 f
P-101
Design pre: 150 psig
Design temp: 150 f
P-101
Feed pump
for providing input to the line list and control system-related instrument work.
Figure 4.6 shows an example of a DPDT diagram for a very simple system.
D-100 Shell: cs
Feed tank ca 0.065ʺ
Casing: cs
impeller: ss316
D-100 Piping specification
cs 0.065ʺ ca
Piping
P-101 specification
cs 0.065ʺ ca
Piping specification
cs 0.065ʺ ca
P-101
Feed pump
Figure 4.7 An example of a material section diagram (CS: Carbon steel metallurgy,
CA: Corrosion allowance, SS: Stainless steel).
Process engineers, including other disciplines, are responsible for adding marks to
the P&IDs. A team of drafting (also known as CAD team) drafts (or cad) all the draw-
ings on the project. The team could be the workshare office or home office. The
process engineers are responsible for timely completion of drafting and correctness
of the drawings. When the drawings are ready for drafting, the process engineer pre-
pares list of drawings to be drafted and gives that list to the drafting coordinator or
CAD person. The CAD coordinator gives this list to the drafting team and provides
DATE:
SIGN DATE
ORIGINATOR
CHECKER
ORIGINATOR
BACKCHECKED
CHECKER
BACKCHECKED
78 4 Phase 3 (Scope Development)
them with a deadline and set of guidelines required by the customer. If there are
questions from the CAD team, those are either addressed by the CAD coordinator or
by the process engineer. When the questions are answered, the CAD team completes
the drafting and gives the drafted drawing copy, as a PDF, to the process engineer for
backchecking. Once the backchecking is complete, the process engineer returns the
backchecked copy with any comments and adds initials in the check box. This cycle
repeats until no further comments are required and finally the process engineer signs
off on the drawing. Tables 4.21 and 4.22 show record box samples for a document
and drawing, respectively. The CAD coordinator, who has a list of P&IDs, prepares a
transmittal package as per project guidelines and issues out the drawings as per the
distribution matrix. Table 4.23 shows a typical distribution matrix used on projects.
Figure 4.8 shows a drafting work process followed on a project.
DATE:
SIGN DATE
ORIGINATOR
CHECKER
ORIGINATOR
BACKCHECKED
CHECKER
BACKCHECKED
Table 4.23 Distribution matrix (note only two functions are shown. There should be more
than two disciplines on any project).
LEGEND
RC: Review and comment
AS: Approval and sign
IF: Information only
NN: Not needed Customer side EPCC side
Document names Distribution Name Name Name Name Name Name Name
code (DC) Role Role Role Role Role Role Role
Project management
Estimate basis PM-DC-XX RC RC RC IF IF IF IF
Procurement plan PM-DC-XX AS RC AS IF IF IF IF
Process
Design basis PR-DC-XX RC RC AS IF IF IF IF
Process-flow diagram PR-DC-XX RC RC AS IF IF IF IF
4.19 Input to 30% Model Reviews and Plot Plan Development 79
Revise
No
Drafting
Process
coordinator Drawing
engineer
issues issued through
sign-off
document
control
by each discipline as required. Once the resolution is provided, the engineer who
resolved the action item provides a resolution comment to close it out.
particular unit. This information may be available to the project management, and
they can bring this up during the scheduled planning meeting.
No. of Engineering
Item# Description items manhours estimated
1 Design Basis
[example]→Mention basis for Process Design Criteria and Area Design
Summary
2 Studies
[example]→Mention studies carried out. Firewater study needs one engineer
working full-time for 6 wk
3 Heat and Material Balance (HMB)
[example]→Mention how many cases of simulations and HMB tables
4 Process-Flow Diagrams (PFDs) and Material Selection Diagrams (MSDs)
[example]→PFD/MSD count and manhours are shown on detailed estimate
sheet
5 P&IDs
[example]→ P&ID count and manhours are shown on detailed estimate sheet
6 Process Equipment Specifications
[example]→ Equipment count-based detailed count shown. Planned to make
design folders
7 Process Instrument Data and Control System support
[example]→ There are A0 numbers of control valves. A1 hour for each control
valve and A2 hour for FE (Count A3). A4 min for on–off valves (count A5), A6
min for analytical devices (count A7), A8 min for level devices (count A9), A10
min for temperature devices (count A11), A12 min for gauges (count A13), A14
hours is added for control system support on
interlock/cause--and-effect/sequence activity
8 Process Data to the Line List
[example]→ Line number count is B1
∼B2 minutes to fill out data for one line + B3 min for checking
9 Pressure Relief Systems
[example]→ Estimated C1 new PSVs and evaluate C2 existing PSVs. C3 hour per
PSV. Planned to make C4 design folders that cover all C5 PSVs. C6 hours added
per PSV to prepare C7 new datasheets.
10 Design Hazard Review
[example]→ D1 hours for HAZOP preparations +1 process engineer for D2 days
11 Engineering Support
[example]→ Set at E1% of total manhours
12 Field Trips
[example]→ Plan for tie-in work
13 Meetings
[example]→ This covers regular meetings outside of planned reviews
14 Report Preparation
[example]→ Already covered in equipment design and relief valve design folders
15 Vendor Data
[example]→ F1 hour per equipment
84 4 Phase 3 (Scope Development)
Table 4.26 Budget preparation – estimating manhours for PFDs/MSDs (detailed sheet).
G1 PFDs G3 G1 × G3
G2 MSDs G4 G2 × G4
Table 4.27 Budget preparation – estimating manhours for P&IDs (detailed sheet).
Table 4.28 Budget preparation – estimating manhours for Equipment (detailed sheet).
Engineering
Count of Hours manhours
equipment TYPE per item estimated
J1 AGITATORS K1 J1 × K1
J2 OTHER VESSELS, SMALL TANKS K2 J2 × K2
J3 BAGHOUSES, PRECIPITATORS K3 J3 × K3
J4 BELT CONVEYORS, FEEDERS K4 J4 × K4
J5 BINS, HOPPERS, SILOS K5 J5 × K5
J6 BOILERS, STEAM GENERATORS K6 J6 × K6
J7 BUCKET ELEVATORS K7 J7 × K7
J8 CENTRIFUGES K8 J8 × K8
J9 CHUTES, LAUNDERS K9 J9 × K9
J10 CLARIFIERS, THICKENERS K10 J10 × K10
J11 COLUMNS K11 J11 × K11
J12 COLUMNS (Existing, modified) K12 J12 × K12
J13 COMPRESSORS, VACUUM PUMPS K13 J13 × K13
(Continued)
4.21 Budget Estimate, Schedule, and Staffing Plan 85
Engineering
Count of Hours manhours
equipment TYPE per item estimated
Constant process engineering work is needed to move the design and meet the
scheduled deadlines. Workshare is a big part of the process engineering to meet
the deadlines for the lead process engineer. There are lots of activities that can be
given to the workshare office, such as relief valve evaluation, markup of P&IDs,
drafting the P&IDs, the line list, designing equipment, and filling out datasheets.
There are at least two meetings in a week for the lead process engineer just to check
on the progress of the workshare office and also to provide them with some helpful
information along the way and answer their questions. At the beginning of the
project, the lead process engineer prepares the workshare execution plan. Process
engineers can utilize below guidelines to prepare a workshare execution plan.
A
A Demo-
Tie-in-
drawing-no.1
drawing no.1
TP-3
TP-3 B TP-1
B TP-1 TP-2 8ʺ ¾ʺ TP-2
TP-4 TP-4
A Demo- A Tie-in
drawing no.2 drawing no.2
B B
8ʺ 8ʺ 8ʺ
¾ʺ
TP-5 TP-5
Figure 4.9 Different steps involving multiple tie-in and demolition drawings for different
phases of the project.
Step 3 – For demo drawing no. 2, the 3/4′′ bleed is demolished at tie-in number 5
to accommodate future expansion. Previous 8′′ installation at tie-in point 5 and
isolation valve on pump B discharge are shown with a dotted cloud, as the work
was done previously in step 2.
Step 4 – For tie-in drawing no. 2, new 8′′ isolation valve and a control valve are added
at the tie-in point 5. The new addition of items is shown with a solid cloud.
PSI issue
Phase title Work performed by the process engineer
The audit report goes through a detailed checklist for each deliverable item for
process engineering. Following are some of the examples from the deliverable list.
1. Design Data
1.1 Equipment tag should include the following info:
• Equipment number, name, or service
• Dimensions (diameter and height/length)
• Design pressure and temperature
• Material of construction
1.2 Data by or in the equipment symbol should include:
• Nozzle and manway sizes
• L/N/H liquid levels
• Skirt elevations
• Piping trim
• Insulation type/thickness
2. Process and Safety
● Are connecting line sizes, specifications, service, insulation, etc., indicated?
● Are liquid level bridle connections for high liquid level (HLL), normal liquid
● Shown with setpoint and size, including orifice size? Example: 8T10
1. Have the PFDs been issued to the Customer for Design, Rev. A?
2. Are the following items shown on the Rev. A PFDs?
● All major process equipment excluding spares
3. Has a full-size set of PFDs (stamped “Master”) been set up, in Bluebeam? Are
they being retained by process? (Auditor to visually confirm)
4. Did EPCC or the Customer prepare the Heat and Material Balance Cus-
tomer(HMB) document?
5. When PFDs are provided by the Customer:
● Is/are controlling case(s) for equipment and piping design clearly shown?
● If not, have obvious PFD deficiencies affecting safety or operability been found?
95
Compared to the previous phase, this phase has the final hazard operability study
(HAZOP), and the controlling scenario documents for the relief valve, vendor, and
seal plans information. Although it is preliminary, lot of vendor information is also
available at this stage of the process. Lots of seal plants have been selected for pumps,
other rotating equipment are finalized, and the design pressure design temperature
(DPDT) diagrams are available. All this information feeds into the detailed design
HAZOP. Also, in this phase, the HAZOP facilitator should make sure that all the pre-
vious hazard items identified are captured in the design and resolved. There should
be very minimal amounts of recommendations coming out of this HAZOP in Phase
4, as the design has progressed significantly.
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
96 5 Phase 4 (Detailed Design)
for construction (IFC), which do not have holds, and hold onto few P&IDs, which
have holds on to them. Later, these hold P&IDs can be issued IFC in a separate batch,
once comments are resolved.
Table 5.1 Template for level indicator and level transmitter (LI/LT) instrument data.
Upper fluid dielectric constant
Lower fluid dielectric constant
Design pressure, internal/
Operating pressure, PSIG
Operating viscosity, CP
Upper fluid & phase
Material Build-up
Process comment
Interface level, ft.
Instrument type
Operating S.G.
external, PSIG
Max temp, F
Tag number
Lower fluid
Dust/foam
P&ID no.
Unit/Area Number Date revised Function
Function Equipment number
Table 5.4
Table 5.3
Table 5.2
Table 5.5 Template for temperature indicator and gauge (TI/TG) instrument data.
Density (LB/FT3)
Process comment
Instrument type
Viscosity, CP
Date revised
Tag number
Fluid phase
Fluid name
P&ID No.
Function
Data by
5.5 Squad Check of Process and Vendor Data
Once the process engineer fills out the requested data from the control system
engineering, the control system engineers transfer the process information into
the formal instrument datasheets. They will create multiple Bluebeam sessions
for squad checking the instrument datasheets. Squad check notifications usually
go out to all the disciplines on the project. Since the instrument datasheet has
process-related information, process engineers are the ones who check the cor-
rectness of the datasheets. Once the process engineer has provided comments,
the control system engineer will update the instrument datasheets based on these
comments and issue out control system instrument package to the vendor for
pricing and quotes.
Once the vendor has all the information they need, based on the delivery time
and the schedule, each vendor will start providing information on the design for
all the instruments. Information received from vendors to the control system is
transmitted to all the disciplines and customers on the project for checking. This
time, process engineer is checking the adequacy of instrument design and making
sure that the vendor has a sound design that works. If comments are provided
on the vendor packages, the package is returned to vendor, which has options
approved/rejected/acceptable with no comments. If vendor package is rejected,
the vendor is expected to revise their design and provide the revised data to the
engineering, procurement, construction, and commissioning (EPCC) company,
and the cycle repeats. Figure 5.1 shows a vendor data review cycle and process
engineering efforts for offline instruments.
5.6 Finalize Safety Valves Design and Issue IFD Datasheets 99
Control system
eng. creates data Notify Process
IFD P & IDs are engineer
issued by process request process
spreadsheets for engineer adds data Notify
engineering offline instruments control
system
engineer
Datasheets No Comments? Controls system
To vendors Squad eng. prepares
check official datasheets
Yes
Receive Revise Revise
quotes from
vendors No
Data Yes
Document acceptable?
control issues to
all the Control system prepares
disciplines cost index spreadsheet
and gives to cost estimate
Figure 5.1 Vendor data review cycle and process engineering efforts for offline
instruments.
now highlight a set of relief valve P&IDs with inlet and outlet piping, and issues
a request to the piping design to get isometric drawings for those pipes. Once the
piping isometric drawings are available, these drawings are then used to confirm the
PSV inlet and outlet line sizes. Sometimes, the PSV type needs to be changed without
affecting the outlet line size. It is important to size the PSV inlet/outlet lines conser-
vatively early on in Phase 3 to avoid changes in Phase 4. Figure 5.2 shows the PSV
checking and vendor data review cycle.
Also, once vendor has completed the sizing calculations, vendor provides the final
design detail for the relief valve to the control system engineer and process engineer.
Process engineer reviews the vendor selection and does a quick look at the updates
that he/she had made based on the piping isometric drawings. If no comments or
changes are needed, the relief valve design folder can be issued to the customer
for design. If any comments or changes could affect the sizing of the relief valve,
the process engineer decides whether to change the pipe sizes of the relief valve or
change the size of the relief valve altogether. Accordingly, the process engineer will
communicate and act to minimize the change.
5.8 Input to 60% and 90% Model Reviews 101
Typically, closeout checklist is available from the customer side, if not, EPCC can
provide a checklist. Toward the end of Phase 4, the process engineers should make
sure that he/she issues out all these documents. Table 5.6 shows a list of documents
that are required for closeout of the project.
At the beginning of Phase 4, 60% model review is completed when some of the
vendor information is available, and piping, civil, mechanical, control system, and
electrical engineering has made significant progress with the 3D modeling. Process
engineer participates in the model review meetings and answers any questions and
comments if required. One could expect normal to minor comments from this meet-
ing. Sixty percent refers to 60% accurate modeling.
Ninety percent of model review is done when most of the vendor information
is modeled and available. Comments from this meeting are very minor in nature,
such as moving a valve or changing the orientation of the valve. After this model
review, the disciplines issue out IFC drawings. Ninety percent refers to 90% accurate
modeling.
102 5 Phase 4 (Detailed Design)
Customers/
operations eng. – 3D modeling Electrical eng. – electrical
review and comment motors, substation, cable
development and
of 3D model trays modeling
meetings
Once IFC drawings are issued by process engineering, the P&IDs are then handed
over officially to the construction team, and project management has a responsibility
at this stage for further revisions. The computer-aided design (CAD) coordinator also
puts all the latest IFC P&IDs on one common Bluebeam session where everybody,
including construction team and the customers, can see the latest version of IFC
P&IDs.
5.12 Leading MOC Meetings 103
Figure 5.4 Discipline work status diagram for the line list document.
During Phase 4, the piping engineering team is busy checking the lines for process
conditions against the pipe specification design limitations. If there is a specifica-
tion burst, the process engineers are notified and requested to take corrective action.
Process engineers either need to update a piping specification or adjust the line con-
ditions and later notify piping engineering to review the revised information. Once
piping engineering checks the line and approves it, they flip the status of the line
from modified to approved. Figure 5.4 shows a work status diagram for the line list
document.
Also, there will be addition of new lines in the detailed design. Process engineers
are required to keep up with the notifications from piping design to fill out pro-
cess data for the new lines, and later notify piping design to review their portion
of the work.
Line list is something that the workshare office can help with effectively and effi-
ciently as all they need is some guidelines and weekly communication.
MOC is management of change procedures. In detail design, after the P&IDs are
issued for design, every discipline is expected to markup the P&IDs as per the
MOC procedure. The procedure protects the marks from being incorporated into
the design without being officially reviewed by the customer engineers. Since the
detailed design is getting closer to the actual building of a plant, it is important to
monitor such changes to make sure that the design changes make sense.
In the MOC meeting, each discipline explains the mark they have added to the
P&IDs and the reasoning behind it. If the marks and the reasoning are appropriate,
the customer approves the marks. Later, the red line marks will then officially be
104 5 Phase 4 (Detailed Design)
Approved
by Customer
HAZOP process Approved
MOC Change Reason for Change required, engineer by EPCC
No. description change category Y/N Y/N team Y/N
drafted and incorporated into the design. There are regular MOC meetings in Phase 4
depending on number of P&IDs. Table 5.7 shows an example of a MOC log and
associated items.
Change category
Category A – Minor drafting changes, such as spelling correction
Category B – Medium changes that alter the design, such as addition of a pump or a
valve
The customer identifies whether to have a HAZOP or not for a MOC item. If the
HAZOP required is identified, later the HAZOP team ensures that the HAZOP for
the item is completed.
MOC meetings and P&ID drafting are coordinated by the CAD coordinator. Dur-
ing the initial stages of Phase 4, the CAD coordinator creates Bluebeam session and
notifies all the discipline leads from EPCC industry. All leads are expected to add
marks to the P&IDs in Bluebeam as per MOC procedure prepared for the project.
Once all marks are added to the session, process engineer usually notifies CAD
coordinator to setup a MOC review meeting with the customers and discipline engi-
neers. CAD coordinator creates a MOC package (consisting of marked P&IDs and
MOC log) and sends a meeting invite. During the MOC review meeting, the cus-
tomer reviews the marks, and each lead needs to explain marks added to the P&IDs.
Once approved, the CAD coordinator marks them as approved. If not approved, the
marks are rejected and the EPCC discipline lead needs to remark as per comments
in the Bluebeam session for the next round of MOC review meeting. The CAD coor-
dinator takes the approved P&IDs and sends them for drafting. The MOC review
meetings constantly take place in Phase 4 until the discipline runs out of marks
or till the end of Phase 4. Figure 5.5 MOC approval cycle for a P&ID in detailed
design.
5.13 Cause-and-Effect Table 105
Drafting coordinator Notify Users add marks to Once adequate MOCs are
creates a Bluebeam users the P & IDs as per marked, process engineer
session MOC procedure notifies drafting coordinator
to set up a MOC meeting
Unit/Area
Area # 1
Interlock No. 1 2 3
FALL-XXXX
BAL-XXXX
HS-XXXX
Tag No.
XX-XX
Fiame failure in main
Cause
Emergency shut-
down sru
burner
flow
Effect
Manufacturer
PO number
P&ID No.
Item type
Line No.
Remark
Vendor
SP No.
Model
Unit
Size
5.14 Input to SP Items and Tie-in Forms 107
Project title XX
Project number XX
P&ID number Associated P&ID number
New and existing line numbers New line number (for Existing pipeline
flange or new pipe) number
Description Tie-in service
Tie-in number XX Revision #: XX
Customer technical approval Signature Date
Customer operation approval Signature Date
Customer construction approval Signature Date
EPCC process approval Signature Date
EPCC piping design lead approval Signature Date
EPCC piping design approval Signature Date
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
110 6 Phase 5 (Construction and Support)
Commissioning:
Dry-out Flare system
Pressure test
Oxygen freeing
Pre- Rotating equipment
Sequencing System
hydrotest Safety systems
systems definition
punch list Utility systems
Chemical cleaning
Electrical systems
Instrumentation
Commissioning Turnover plan
Tie-ins
plan Construction
performs
testing
Material Initial start
loading up
Mechanical
completion
Mechanical
start
completion
Startup Turnover
Cons to Function Performance
plan procedure completions test test
turnover
Training
Classroom
plan
training
understand the history of the design before accepting minor changes or making a
change during the construction phase, if beneficial to the project.
Some questions have the potential to change the original design. Other questions
from the construction team are like changing minor design from the original design.
They want to consult the process engineer to make sure there are no implications.
The process engineer in this case may have to do a quick hydraulic study to confirm
that there are no implications.
One of the examples, in the original design, was proposed to add a new 16-in.
nozzle to a vessel. This 16-in. nozzle has a thickness of standard (STD). During
the construction phase, the fabricator provided a pipe thickness of schedule 80 for
16-in. nozzle. As the actual fabricated piece was a little different than the origi-
nal design, the process engineer was asked to confirm whether this is acceptable.
6.4 Updating P&IDs as Needed 111
In this case, the process engineer does some hydraulic checks and confirms that it is
acceptable to go with design made by the pipe fabricator.
Another example is checking the pressure safe valve (PSV) inlet and outlet pres-
sure drops. Initially, in Phase 4, the piping length for a relief valve was designed
and checked with an 80-ft length and four 90∘ elbows. But during the construction,
the construction manager noticed that this pipeline length had to be increased to
102 ft and six 90∘ elbows to accommodate space restrictions. Again, for this case,
the process engineer is asked to confirm whether this change has any implications
on the design of a relief valve. So, in this case, process engineer checks the relief
valve design and confirms that there are no implications. Note that it may not always
be acceptable to make a change in the construction phase and still acceptable. For
this example, the pressure drop for the relief valve on the inlet side was originally
designed conservative, so additional few feet of pipe length and a few elbows fittings
did not alter the original design.
Steam trap requirements changes per pipe layout. Sometimes, the construction
team is required to add or delete some of the specialty items (SP) items, such as steam
traps. The process engineer may not have to spend a lot of time on such questions.
The construction team, operation, and engineers from the customer side are also
involved during the construction. So, the construction team may have questions
regarding the operation of the equipment or routing information of the pipe. The
process engineer can reply to such requests by providing a piece of information from
the procedures and manuals that he/she may have prepared or mark or highlighting
a set of P&IDs and writing a short note to the team.
As the construction is in progress, the operation team from the customer side may
request and ask other questions related to the equipment design and its function. In
this case, the process engineer can provide the design information to the customer.
There is a list of pressure safety valves (PSVs) for the project previously prepared by
the process engineer. Before the startup of a plant, once all the relief files are deliv-
ered to the site, it is required to test these safety valves at their set pressure to ensure
the original design is maintained. For such activity, the gas or vapor service safety
valve is tested using nitrogen gas. The liquid service safety valves are tested using
water. The process engineers are required to supervise and certify the testing. The
actual physical testing is done by the customer operators or technicians. In follow-
ing example, shown in Figure 7.1, assuming a gas service relief valve, high-pressure
nitrogen greater than 150 psig pressure is connected to the 3/4′′ relief valve inlet drain
connection, and 4′′ inlet isolation valve is closed. Assuming the main 6′′ PSV out-
let connection is not available and 6′′ gate valve is closed. In such case, 3/4′′ tubing
connection is made, and the test pressure can be relieved to a safe location. The PSV
test pressure should be recorded in the portable pressure gauge (PG) attached with
the 3/4′′ tubing connection. The PSV passes the test if it pops at 150 psig as per its set
pressure. Note that a regulator on the nitrogen cylinder can be used to regulate the
inlet pressure to the PSV.
Similarly, a list of equipment is prepared previously by the mechanical engineer.
The process engineer should collect all the equipment internal drawings and enter
all the equipment to ensure that all the internals are installed correctly. Also, the
process engineer should certify that all these internals are correctly installed. If some
of the internals are missing, the process engineer should mention that in the report
and the appropriate corrective action will be taken by the technician as needed.
One of the interesting tasks performed by the process engineer is a plant walk-
through of the lines or following the lines system by system depicted on the P&IDs.
While the process engineer is going through the walkthrough of the system, he/she
is required to highlight the P&IDs and confirm that all the elements, such as the
drain valves, control valves instruments, temperature gauges, and equipment, are
installed appropriately as mentioned on the P&ID’s. If he/she finds something is
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
114 7 Phase 6 (Commissioning and Startup)
4P6
SET @ 150
¾” Tubing
PSIG PG
Scale: 200 PSIG
Water source 6”
Note 1 CSO 4”
for liquid relief
CSO
valve service
Nitrogen gas ¾” Tubing
cylinder for Process system
gas relief valve
service
There are several checklists that the process engineer should go through before
starting a plant. These checklists are divided into pre-startup and safety checklists.
Pre-startup checklist is associated with plant operations and the safety checklist is
associated with the safety of the plant. Table 7.2 shows some lists of checklists and
high-level overview of each checklist. Note that the list of checklists may vary
depending on the plant type or processing products.
7.2 Prepare and Complete Pre-startup and Safety Checklists 115
Activity or Pre-startup
checklists or safety Actions Objective
Compressor – The gas compressor needs the process gas to test it. If the gas is not
available for testing, the compressor loop is typically pressured with the nitrogen
gas, and compressor is slowly started with the help of recycling line. So, this way
the compressor can be tested for its performance.
Pump – All the pumps can be tested based on the liquid in the upstream system.
If the liquid in the upstream vessel is not available, water can be added to the
upstream vessel and the pump can be tested. The seal systems are also commis-
sioned making sure the parameters match the design values.
Heater – Fired heaters are tested using a standard procedure. Initially, the cold cir-
culation of the process fluid is carried out and system is tested for any leaks.
Then, slowly the firing of the fired heater is started, and the temperature is slowly
increased until it reaches its design point.
Exchanger – Exchangers may not be able to test their performance at full capacity
since all the fluid streams may or may not be at their ideal temperature or the
desired temperature. But, if possible, the process fluid flow rates and temperatures
are increased to reach the design capacity of the exchanger, and the performance
of the exchanger is monitored.
Column – Performance of a column, especially distillation column, is tricky. The liq-
uid is introduced in the column then the reboiling is started to get the vapor–liquid
traffic started. Once enough reflux is accumulated in the reflux drum, the column
will be put on full reflux, boiling is maintained at a certain temperature with full
reflux, and feed is cut off to check the performance of a column.
It is necessary to make sure that all the elements of control system loops are function-
ing as per design for any safety and operational upsets encountered during startup.
The testing will make sure that all the designed instruments, the logic, alarm, and
interlocks are functioning to best of their performance compared with the design.
So, the task of checking the control system loops and instruments is primarily led by
control system engineers. This task is certified and supervised by the process engi-
neers or customer process engineers. Following tasks and details explain the role of
process engineering in the control system look testing area.
7.5 Leak Testing 117
Verify cause and effects – For this task, the control system engineer simulates a cause
mentioned in the cause-and-effect table, the process engineer should make sure
that the simulation changes the position of affected valves as per cause-and-effect
table. Also, it is important to make sure that all the safety interlocks are working
as per the design.
Verify all the alarms – On this one, the control system engineer adds an alarm, and
process engineer makes sure that the alarm is shown on the distributed control
system (DCS) and confirms the values and the alarm as per the design.
There are several piping systems in a processing unit. Usually, the customer oper-
ations and process engineers lead the task of leak testing all the pipes in the plant
for a project. A process engineer should certify that there is no leak in the section of
pipe by witnessing the leak test physically in the plant.
As this activity is planned, the process engineers are asked to highlight and cre-
ate set of P&IDs to prepare for leak testing. Figure 7.2 shows an example of loop
highlighting needed for leak testing. The engineer may have to segregate the entire
process system by the service, the phase of the fluid, sometimes by the P&ID num-
bers, and unit numbers.
Gas loops are pressure tested with nitrogen depending on the pressure rating of the
piping. So, for example, if the piping class is 300#, high-pressure nitrogen at 250 psig
can be used to test the piping.
Liquid loops are pressure tested with water. If the pipe service is liquid, these loops
are pressure tested using water at the design pressures. Process engineers need to
certify after monitoring no leaks.
E-01
V-01
T-01
P-01
Gas loop
Liquid loop
Process engineers can supervise a part of the process, while the operator is making
slow changes as designed. Startup is a very slow process, especially for the first time
for the unit, and any additional help is appreciated by the customer. The role of a pro-
cess engineer from the engineering procurement, construction, and commissioning
(EPCC) industry is to supervise many process operations performed by the process
operators and operations.
119
Part III
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
121
There are total of six levels of hierarchy for process engineering in the engineering,
procurement, construction, and commissioning (EPCC) industry. Each level brings
a specific set of skills, and expectations are different for each level. Some levels are
directly exposed to customers and internal disciplines, and some are not so. Few
levels are expected to lead projects, and few are expected to support the leads.
Entry-level process engineers perform very simple tasks, such as data entry, checking
the data, and doing very simple calculations. They are not expected to know the
EPCC industry software or tools immediately. They are not assigned any project but
could be helping other junior to mid-level engineers on multiple projects. They are
constantly learning new tools and procedures.
Mid-level process engineer performs mostly medium complexity level tasks, such
as medium level calculations. Example of medium calculations involves sizing of a
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
122 8 Role by Process Engineer’s Position
new pump or a new exchanger. They are expected to have gained greater competency
in EPCC industry software or tools. They may be assigned a project but could be
helping other lead engineers on multiple projects. Even though they have gained
greater competency in software, they still need little supervision.
They can lead mid-sized projects and provide supervision to junior-level engineers.
They are expected to perform complex calculations, such as sizing a distillation col-
umn or setting up a simulation. They are expected to provide guidance and help
to other junior and entry-level process engineers. They are also expected to lead
mid-sized projects independently with minimal supervision.
They can lead mid-sized to larger-size projects and provide supervision to mid-level
engineers. They are expected to perform complex calculations, monitor schedule,
progress of the project, budgeting, supervisory role, workshare activities, and mentor
other engineers.
They can lead big projects and provide supervision to everyone. Provides technical
leadership for the department. Everyone in the process department looks up to them
for guidance or any technical questions. They are expected to know majority of the
process engineering knowledge. They are also expected to bring more business to
the EPCC industry by utilizing their knowledge and customer contacts.
Table 8.1 shows a guide to the competency required for process engineers at different
levels.
Competency rating scale: 2 – Some exposure; Capable of completing task with
assistance; 4 – Capable of working independently with close supervision; 6 – Capable
of working independently with minimal supervision; 8 – Capable of working inde-
pendently and providing supervision to other more junior engineers; 10 – Capable
of leading the discipline for a project or providing technical leadership within the
department
Table 8.1 Competency guide table for process engineers at different levels.
The leads for all the disciplines on the project report to project management. Each
discipline lead may have a team of workshare and local supporting engineering team
to support the project design activities. Also, each discipline lead should interact
with different vendors and other engineering procurement, construction, and com-
missioning (EPCC) industries, if involved, on each project. Drafting of process deliv-
erable drawings is completed by the drafting team reporting to process engineering
lead. The drawings in other disciplines are typically drafted by the supporting engi-
neers within the disciplines. The licensor and customer work directly with process
engineering lead to develop scope of the project. Figure 9.1 shows a detailed project
tree diagram.
Estimating
Drafting
Construction Control Electrical Civil
Document
team system engineering engineering
controls
engineering lead lead
lead
Interaction with other EPCC and vendors, workshare, and other supporting engineering team
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
138 9 Interaction of Process Engineers with Others
9.2 Customer
Table 9.1 shows interaction of a process engineer with a customer.
IFE, issued for estimate; IFR, issued for review; IFH, issued for hazop; IFA issued for approval; IFD,
issued for design; IFC, issued for construction; PFD, process flow diagram; MSD, material selection
diagram; MOC, management of change; HAZOP, hazard operability analysis; SP, specialty items.
Role of Role of
Document process mechanical
versions Work engineer for engineer for
(applicable completed mechanical process
Item in phases) in phases engineer engineer
9.4 Projects
Table 9.3 shows interaction of a process engineer with project management.
Document
versions Work Role of process Role of electrical
(applicable completed engineer for engineer for
Item in phases) in phases electrical engineer process engineer
Document
versions Work Role of process Role of civil
(applicable completed engineer for engineer for
Item in phases) in phases civil engineer process engineer
9.13 Licensor
Document
versions Work Role of process Role of Licensor
(applicable completed engineer for for process
Item in phases) in phases Licensor engineer
Table 9.14 Interaction of a process engineer with CAD and drafting coordinator.
Role of
Document Role of process document
versions Work engineer for control for
(applicable completed document process
Item in phases) in phases control engineer
Questions
Chapter 1
1. If the EPCC does not have a talent in certain area, what should they do to support
a project?
2. Installation of hoppers and bins falls under which type of project given below:
a. Non-process engineering
b. Engineering needs related
c. Both options a and b
d. Profit based
3. P&IDs are developed in which phase?
4. Which key factors determine the need for workshare?
5. What is the role of a lead process engineer working in a home office when
working with workshare office?
Chapter 2
1. What affects the duration of the study in phase 2?
2. Why good engineering assumptions are important when performing process
studies in phase 2?
3. What contents are included in the process study in phase 2?
4. If the EPCC process engineer cannot narrow down the technology options to
2–3 in phase 2, what steps are taken?
5. What are some technology selection criteria?
Chapter 3
1. How is PFD different than BFD?
2. Choose below options for the statement “IFE P&IDs are utilized to get ------”?
a. funding for the next phase
b. cost estimate
c. design reviews with the customers
d. all the above
3. Why it is important not to spend too much time developing design in Phase 2?
4. Why is choosing the correct metallurgy important in early phases of the project?
5. What is difference between LOPA and HAZOP meetings?
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
148 Questions
Chapter 4
1. Explain the importance of design safety margin for an equipment design?
2. Why choosing the side of the heat exchanger is important for fouling services,
such as vacuum bottoms?
3. How control system engineer uses the process data provided in phase 3?
4. Mention the revision titles for PFD/MSD/P&IDs in phase 3?
5. Determine number of full-time process engineers required for below example
Duration of schedule = 16 mo, Budgeted manhours = 9500
Chapter 5
1. Check if the statement is true or false: “HAZOP is done in the early phase 4”?
State your reasoning.
2. State typical offline instrument names?
3. Why it is important to size the PSV inlet/outlet lines conservatively early on in
Phase 3?
4. When P&IDs can be issued for construction?
5. Who approves the MOC marks and decides if the HAZOP is required for the
MOC items on the P&IDs?
Chapter 6
1. What are some common questions to the process engineer from the construc-
tion team?
2. State if this statement is true or false: “P&IDs can be changed in Phase 5.”
Chapter 7
1. Below statement falls under which checklist? “Go through the list of utilities
and their pipe connections.”
a. Safety
b. Pre-startup
2. Which two tasks fall under “control system loops” testing?
3. Why it is important to remove water and oxygen from the pipelines?
Chapter 8
1. What is the software usage competency of the mid-level process engineer?
2. Who is expected to bring business to the EPCC industry?
Chapter 9
1. What is the role of process engineers for project regarding schedule and budget
concerns?
2. What is the role of process engineers for piping engineering regarding pipe
service index?
3. What is the role of process engineer for electrical engineers regarding area
classification?
149
Answers
Chapter 1
1. Hire local if labor cost permits. Preferred option would be to get talent from
within the global pool of talent.
2. c.
3. Phase has IFE P&IDs that are mostly redline drawings. Phase 3 is implementa-
tion of completed design on the P&ID drawings. Phase 4 further incorporates
detailed design elements of the project.
4. High cost of labor, project workload, and labor shortage.
5. Lead process engineer should provide guidance, goby’s, and check the work of
the work-share engineers.
Chapter 2
1. Typically, a simple study can take anywhere from two to four weeks. A complex
study can take anywhere from 4 to 12 weeks.
2. All assumptions are important because without the assumptions you can’t
proceed with the design or complete the study.
3. The first page of the study report should clearly mention the product number,
the project name, the name of the unit, the date, the revision, engineer’s name,
the name of the checker, and the name of the approving personnel. The other
pages of the report should include a clear executive summary, background of
the stud, basis or assumptions to complete the study, the results of the study,
any calculations values or graphs, supporting conclusion, and list of references
documents.
4. In such cases, the EPCC process engineer meets with the customer and dis-
cusses, and narrows down options as much as possible. Action items are taken
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
150 Answers
from this meeting and EPCC process engineer would resolve these actions items
to come to 2–3 options.
5. Some of the common factors are emission data, the capital investment needed,
the turnaround time, delivery time, quality of material used, and any prior appli-
cation of the technology in the industry.
Chapter 3
1. PFD contains all the equipment, the connections to each equipment, and the
basic information of flow pressure and temperature is shown on their streams.
Each dream is identified by specific number usually shown in a diamond shape.
Block flow diagrams are very simple diagrams that show a simplified version of
the process.
2. h.
3. Phase 2 is a scope definition phase where process engineer spends time in
high-level processing engineering activities. Also, it may not be sure if the
project is going into the next phase 3, in that case, too much time spent on the
design development in phase 2 may not be worth it.
4. If the metallurgy is not chosen correctly in the early phases, it is OK to make
a mistake in choosing the metallurgy in Phase 2 but more than likely this mis-
take is going to carry forward into the next phase. The cost impact of chang-
ing the metallurgy in the next phases is going to be more expensive for the
project.
5. LOPA study is performed at the earlier stages of the design phase and HAZOP
is done in the scope development and the detailed design phases. The HAZOP
is more detailed analysis of the processing system compared to LOPA where a
high-level hazard analysis is carried out.
Chapter 4
1. The safety margin provides some flexibility to the operations and provides some
future expansion capabilities.
2. If the wrong side is chosen for the vacuum bottom’s fluid, then the fluid being
viscous can solidify with temperature changes and create excessive fouling over
time. Increased fouling, reduces the heat transfer necessary for the process.
3. They use the process data to get budgetary quotes from the vendors. Once bud-
getary quotes are received, quotes are then fed into the overall cost estimate of
the project.
Answers 151
5. Hours spent by one engineer in a single month = 40 hours × 4 weeks = 160 hours.
Chapter 5
1. False HAZOP is done in late phase of Phase 4 when most of the information from
process engineers and vendors is available to do an effective HAZOP meeting.
2. Level indicator and level transmitter, pH analyzer, pressure gauge and pressure
transmitter, sight glass, temperature indicator, and gauge.
3. To avoid changes in Phase 4, changes made in Phase 4 had a major cost impact
on the project and should be avoided at possible cost by making conservative
assumptions in previous phase.
4. After the model review is complete, and after all the MOC marks have been
approved, and HAZOP is completed.
5. The customer.
Chapter 6
1. Some questions are like changing the original design and its implications. Other
questions from the construction team are like changing minor designs from the
original design.
2. False as the design is frozen after IFC issue.
Chapter 7
1. b.
2. Verifying cause and effect tables and alarms.
152 Answers
3. It is important to remove oxygen and water from the process to make sure there
are no unwanted reactions with the new catalyst or process fluid, and to avoid
corrosion later.
Chapter 8
1. They are expected to have gained greater competency in EPCC software or tools.
2. Process managers.
Chapter 9
1. Communicate.
2. Develop, support.
3. Support and provide process data.
153
Acronyms
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
154 Acronyms
Appendix
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
157
Appendix A
Initially in Phases 1 and 2, since mainly process engineers are involved in devel-
oping the project scope, the budget required is quite small. But as other disciplines
are involved in Phases 3 and 4, additional project budget is needed to support the
engineering design efforts and purchase order for all the components of the design.
During Phases 5 and 6, the project budget mainly comes from the commissioning
and testing of equipment and instruments. It is important to note that the project
should always be completed within the scheduled budget. From the figure, the actual
budget or expensed budget should always be smaller than the planned project budget
to have a successful project.
Planned
project
completion
Planned
budget
Actual
budget
Project budget
Project timeline
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
158 Appendix A Project Conceptual Diagram
Rate of document
production
Initially, in Phases 1 and 2, very few documents are produced by the process engi-
neer and few may be provided by the customer to develop a scope of the project. In
Phase 3, process engineer develops several design documents as mentioned earlier
that feed other disciplines. Phase 4 has the highest production of documents as the
vendors are involved in this phase, and they are developing detailed design docu-
ments for all the components and different areas of the project. In Phases 5 and 6,
few documents are produced by the piping design, and process engineer develops
several procedural and training materials as needed.
1 2 3
Engineering Purchase and Drawings for
drawings and document control construction
documents
• Contractor
• Design • Logistics • Commissioning
engineers • Vendors engineers
• Vendors • Buyers • Design team
• Buyers • Auditor
correction, record, and approval. In Phase 6 and later Phase 5, contractors are
involved in erecting the plant, engineering teams are commissioning different areas
of the plant, the design team is helping with solving design issues, and the auditor
is making sure every step is going according to the plan.
Process engineer in Phase 1 starts with some basis previously put together by the
customer. The information available to the process engineer during initial phases of
the project is very limited as the scope has not been developed. As the project makes
progress, the information from other disciplines and vendors is available more and
Expected flow
of information
Actual flow of
information
available to process
Flow of information
engineer
Figure A.4 Flow of information available to process engineer vs. different phases of the
project.
160 Appendix A Project Conceptual Diagram
more to the process engineer. For example, for Phase 3, the vendor information is
not available to the process engineer, so the process engineer needs to develop their
design and produce several engineering deliverable documents based on prior sim-
ulation studies, calculations, and good engineering assumptions. Ideally, the flow of
information should be available to the process engineer linearly as the graph shows,
but it is never true in reality. The actual flow of information curve is non-linear with
several disruptions. In Phase 3, the process engineer would be needing design infor-
mation of a new pump and piping isometric drawings to complete the hydraulics, but
those are never available. As the design of pumps is very critical for delivering pumps
on time on site, process engineer makes good engineering judgments, e.g. using plot
plan multiplier, to come up with a sound design. Another example is during Phase
4, the process engineer is expected to complete design of a relief valve and provide
pressure safety valve (PSV) datasheets to control system engineer. In this example,
the process engineer would not have information on instrumentation and piping
isometric drawings. In this case, the process engineer issues out PSV datasheet with
somewhat conservative assumptions and later in late Phase 4 checks the validity of
those conservative assumptions.
From Figure A.5, the baseline cost estimate, shown by a dotted line, is the expected
cost of the project. The overrun (means higher than the baseline cost) and underrun
Overrun and
underrun cost
uncertainty
Baseline cost
Cost estimate
overrun
Project cost
uncertainty
estimate
Cost estimate
underrun
Figure A.5 Project estimate uncertainty vs. different phases of the project.
A.6 Explanation of Figure A.6 161
(means lower than the baseline cost), cost estimates are some percentage factors of
the baseline costs. As there are several unknowns. In Phases 1 and 2, the project cost
estimate is very uncertain and cost estimate overrun and underrun are on higher
side. As the process engineer and customer make significant progress in Phase 1
and 2, several unknowns, such as type of a process or licensor, are known by start of
the Phase 3, but the vendor information is still unknown. Cost estimate overrun and
underrun in phase 3 are still higher than in phases 1 and 2 but lower than in phase 4.
In phase 4, since all the vendor information would be available, the uncertainty has
reduced tremendously at this point and overrun and underrun cost estimates are in
single digits.
Operational
risk
Figure A.6 Project risk level vs. different phases of the project.
162 Appendix A Project Conceptual Diagram
Ability to
impact cost
Cost of design
changes
Ability/Cost
Figure A.7 Ability to change cost and cost of design vs different phases of the project.
163
Appendix B
The figure shows a typical schedule page used to monitor the project schedule and
activities. Tasks or activities are arranged by different disciplines, such as installation
and configuration. The duration column represents the time remaining to complete
the activity. The start and finish dates represent the actual start and finish dates for
the activity. Over to the right of the figure with different bars show the breakdown
of duration as per different activities.
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
Figure B.1 Project schedule template (https://www.findwordtemplates.com/project-schedule-templates.html).
165
Appendix C
The plot plan layout of a unit consists of main components of a process plant. In
above example, the main components are admin blocks, electrical buildings, D2 O
GR plant, stack, reactor buildings, and station buildings. All these components are
interacting with each other to make a successful process unit.
North
18 M wide road
(const)
SAB - 38
Service building
RB4 RB3
RAB RAB
Control’
SAB - 4A
SAB - 3A
bldg. P&C
P&C
dg.
. bl brdg. brdg. T.G
T.G Ele
. bl
dg.
bay c. b
Elec. ay
d
roa
ide
Mw
5.5
Admin. block Parking
area
2 M wide road
RB-3 : Reactor building unit-3 RAB : Reactor auxiliary building
RB-4 : Reactor building unity-4 W.M. : Plant: waste management plant
T.G. bidg : Turbo generator building SAB : Station auxiliary building
Figure C.1 Plot plan layout of a unit. Source: R. K. Sinha et al., 2010/With Permission of
Elsevier (https://www.sciencedirect.com/topics/engineering/plant-layout).
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
166 Appendix C Project 3D Model and Plot Diagrams
Above picture shows a plot layout of an entire refinery plant. Although the picture is
not clear, it is important to the concept of this drawing. The blocks marked in square
shapes represent process units perhaps dependent on each other. All these units are
placed next to each other to minimize process pipeline lengths as these units will
be receiving raw materials and delivering products to one another. Off to the right
top corner of the figure shows some tanks to either receive a product or deliver raw
materials to the units.
Figure C.2 Plot plan of an entire plant. Source: Adapted from http://environmentclearance
.nic.in/writereaddata/online/RiskAssessment/07122016O3TKM30QAnnexure-
documentofRiskAssessment.pdf.
C.4 Explanation of Figure C.4 167
Motor
1 2 3 4 5 6
E - 194.000
E - 195.600
E - 196.500
E - 199.000
E - 201.500
E - 204.000
E - 205.200
E - 206.500
Plant
A
N - 90.000 North
N - 86.200
FM-C-40
N - 82.400
B
N - 78.600
FM-H-05
N - 77.340
E - 200.850 FM-F-30
N - 74.800
C
N - 71.000
FM-H-105
N - 67.200
D
6 5 4 3 2 1
E - 206.500
E - 204.000
E - 201.500
E - 199.000
E - 196.500
E - 194.000
T.O.S.
EL.1 36 200
FM-F-30
EL.131800 EL.1 31 600
FM-H-05
EL.1 31 100
4th floor
EL.1 29 200
FM-C-40
EL.123100
3th floor
EL.121900
Section A-A
(Looking South)
Appendix D
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
A B C D E F G H I
EH-123 A/B
CASE: FIRE
Boiler Feed Water Cooler SIZE: 1 D 2
B A
Duty: 510 kW SET: @ 3,800 kPag
1 Type: Multi-Tube
Outer Tube Design: 3,800 kpag (F.V) @ 98°C/–29°C PSV 4×2
123
Inner Tube Design: 1,450 kpag @ 160°C/–29°C
4”-RF-A-4101
RO Trim: Outer/Inner Tube-B/A
123 2×1
Boiler Feed Water 3” 2”
3”-BFW-B-1200 CSO
PID-10-110 H 40-GT
FP
From Flow Control Valve 2”-BFW-B-1251 H 40-GT
3”-BFW-B-1203
2 TY TIC
CASE: THERMAL 123 123 ROUTED TO
SIZE: 1 D 1 SAFE LOCATION
SET: @ 1,450 kPag
TV
PSV 123 Cooling Glycol
124 Return
3” 3/4” 3” 3”-CGR-A-1821
H 40 PID-80-805
2×1
2×1 3/4” 3”-300# TO Return Header
2”-RF-A-4102
3
FP 3/4” FO
PG
3” 126
H 40
2”-BFW-B-1251 CSO TG
126
PG 3/4”
123 3/4”
HPV
TG
123
4 ROUTED TO
SAFE LOCATION PP-50
EH-123 A
40-GT
PP-50
PG
5 124 PP-50
TG
Cooling Glycol Supply 3/4” 124 EH-123 B
3”-CGS-A-1820 3” 3/4”
PID-80-805 PP-50
From Supply Header 3/4”
2”
TT
TG 123
125
TE
PG 3/4” 123
6 125 3” Cooling BFW
3”-BFW-B-1201
H 40-GT PID-10-105
3/4” To Desand Vessel
3” NC
TITLE
8
PROJ NUMBER DRAWING NUMBER
Figure D.1 Example of a P&ID. Source: Toghraei, Moe, 2019/John Wiley & Sons (https://onlinelibrary.wiley.com/doi/book/10.1002/9781119329503).
To Tail gas
sheet no 9317 1 Water
10 11
2
Air
Filter 8
Compressor 2A Absorber
1A 3 Steam
Cooler
5
Ammonia 1 6 9
14
4 Filter
From
sheet no 9315 vaporiser W.H.B. 7 12
Reactor
(oxidiser) Condenser Mixer
13
Product
Line no. 1 1A 2 2A 3 4 5 6 7 8 9 10 11 12 13
Stream Ammonia Ammonia Filtered Oxidiser Oxidiser Oxidiser W.H.B. Condenser Condenser Secondary Absorber Tail(2) Water Absorber Product C & R Construction Inc
component feed vapor air air feed outlet outlet gas acid air feed gas feed acid acid
NH3 731.0 731.0 731.0 Nil Nitric acid 60 percent
O2 3036.9 2628.2 2628.2 935.7 (935.7)(1) 275.2 Trace 408.7 683.9 371.5 Trace Trace 100,000 t/y
N2 9990.8 8644.7 8644.7 8668.8 8668.8 8668.8 Trace 1346.1 10,014.7 10,014.7 Trace Trace Client BOP chemicals
NO 1238.4 (1238.4)(1) 202.5 202.5 21.9 Trace Trace SLIGO
NO2 Trace (?)(1) 967.2 967.2 (Trace)(1) Trace Trace Sheet no. 9316
HNO3 Nil Nil 850.6 1704.0 2554.6
H2O Trace 1161.0 1161.0 29.4 1010.1 29.4 26.3 1376.9 1136.0 2146.0
Total 731.0 731.0 13,027.7 11,272.9 12,003.9 12,003.9 12,003.9 10,143.1 1860.7 1754.8 11,897.7 10,434.4 1376.9 2840.0 4700.6
Press bar 8 8 1 8 8 8 8 8 1 8 8 1 8 1 1 Dwg by Date
Temp. °C 15 20 15 230 204 907 234 40 40 40 40 25 25 40 43 Checked 25/7/1980
Figure D.2 Example of PFD and H&MB. W.H.B., waste heat boiler (https://processdesign.mccormick.northwestern.edu/index.php/Process_flow_diagram).
174 Appendix D Process Engineering Diagrams
Control
system
Loop diagram
Process
datasheets
Instrument
datasheets
Mechanical
datasheets Construction
and dynamic control system interface. P&ID serves as a basis for preparation of
operating guidelines for the manufacturing plant and can be used for analysis of
safety incidents. In summary, P&IDs are engineering documents that are used by
everyone on the project to develop the design and in the meetings.
175
References
1 National Master. Cost of living Stats: compare key data on India & United States.
https://www.nationmaster.com/country-info/compare/India/United-States/Cost-
of-living (accessed 14 May 2022).
2 Patel, H. K. J. (2020). LOPA: A comprehensive analytical tool for deriving
SIL targets and applicability review. Hydrocarbon Processing https://www
.hydrocarbonprocessing.com/magazine/2020/february-2020/environment-
and-safety/lopa-a-comprehensive-analytical-tool-for-deriving-sil-targets-and-
applicability-review (accessed 14 May 2022).
3 Mazzoldi, A. and Oldenburg, C. (2014). Leakage Risk Assessment of CO2
Transportation by Pipeline at the Illinois Basin Decatur Project, Decatur, Illinois.
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
177
Index
Managing Engineering, Procurement, Construction, and Commissioning Projects: A Chemical Engineer’s Guide,
First Edition. Avinashkumar V. Karre.
© 2023 WILEY-VCH GmbH. Published 2023 by WILEY-VCH GmbH.
178 Index
g j
gas compressor 7, 116 junior process engineer 121
gas loops 117
grassroot project 5–6, 34 k
KG tower 40
h
Hazard and Operability Analysis l
(HAZOPs) 10, 49, 51, 95 Layer of protection analysis (LOPA)
action item close out and hold items 49–50, 148, 152
95–96 lead process engineer,6 7, 49, 80, 81, 84,
closeout checklist 101 87, 88, 91, 122, 147, 151
Index 179
lead workshare meetings 87, 88, 102 piping and instrumentation diagrams
level indicator and level transmitter (P&IDs) 10, 36, 37, 38, 41, 50, 51,
(LI/LT) instrument data 96, 153 67, 69, 72–74, 95, 96, 104–106, 117,
licensor 5, 8, 44, 45, 47, 51, 70, 75, 137, 173, 174, 176
144, 163 demo or demolition 89–90
line list help instrumentation 173
input and output tree 57–63 importance of 173–176
piping design responsibility columns tie-in 89
61–62 piping design 4, 5, 8, 13, 21, 39, 52, 57,
piping engineering responsibility 61, 67, 70, 72, 79, 80, 90, 91, 93,
columns 61, 63 100, 103, 106, 140, 160, 173
process engineer responsibility piping designers 4, 5, 8, 10, 173
columns of 61–62 piping engineer 4, 5, 8, 10, 51, 57, 61, 63,
process responsibility and description 70, 91, 103, 141
58–61 piping engineering 57, 61, 63, 70, 91,
line-by-line P&ID review 73 103, 141
liquid loops 117 piping engineering team 103
liquid service safety valves 113 piping systems 117
planning 23
m flowchart 25
management of change (MOC) interaction with customer 25
13, 102–105, 111, 139, perform feasibility studies
148, 153 duration 24–25
material selection diagrams (MSD) types 23
72–73, 76–77, 84, 148 preliminary scope reports preparation
mechanical engineer 4, 5, 8–10, 15, assumptions 26
design document 26–28
39–40, 42, 51, 52, 55, 68, 69, 70, 88,
technology selection 28–30
113, 139
plant visits 88
mechanical engineering, estimate
plot plan layout, unit 167
39–40, 42, 70, 88
plot space 38, 39, 52, 170
metallurgy
pre-startup 114–115, 118
importance 44
preliminary equipment design 40
refinery operations 43
preliminary horsepower 41–42
selection 42–44
pressure gauge and pressure transmitter
special consideration 43
(PG/PT) instrument data 96–97
mid-level process engineer
pressure safety valves (PSV) 36, 66–68,
121–122
96, 100, 111, 113, 114, 162
process audit 91–93
n process engineer 10, 14, 51, 57, 68,
net positive suction head (NPSH) 69, 159–161
104 with CAD and drafting coordinator
145
o with civil engineer 142
off-line instrument data 96–98, 102 with construction team 143
oxygen freeing 118 with control system engineer 141
with cost estimating 143
p with customer 138–139
pH analyzer instrument data 96–97 with document control 146
physical testing 113 with electrical engineer 142
pipe service index (PSI) 90–91 with EPCC engineer 145
180 Index