You are on page 1of 6

TECHNICAL AR TICLE

am a cost consultant and cost esti-


A Spreadsheet Checklist to
I mating project leader for a cost
engineering and project manage-
ment firm; one of our specializa-
tions is preparing building construction
Analyze and Estimate
cost estimates. We are involved mainly in
commercial building construction, and Prime Contractor Overhead
our estimates range from conceptual to
final cost estimates. They are prepared
using one of three cost estimating software
Walter B. Jones, CCC
packages.
As cost estimating project leader, one
of my duties is to prepare the prime con-
tractor overhead cost. To facilitate this
process, I developed a worksheet using PRIME CONTRACTOR OVERHEAD are not directly traceable to the permanent
Microsoft Excel to calculate certain costs installation, yet are required for the order-
and ratios that apply to the different cost Building construction costs are com- ly completion of the installation. These
estimating software packages. I call this posed of indirect and direct costs. Certain costs are indirect costs, and include prime
worksheet the prime contractor overhead material, personnel, and equipment costs contractor overhead. Direct costs are the
spreadsheet checklist. The purpose of this
article is to demonstrate its use in analyz- Table 1—Prime Contractor Overhead Spreadsheet Checklist Organized by Type of
ing and estimating costs for prime con- Overhead Component
tractor overhead.

PRIME CONTRACTOR OVERHEAD


SPREADSHEET CHECKLIST

A prime contractor overhead spread-


sheet checklist is a list of prime contractor
overhead items that usually occur on a
building construction project. The spread-
sheet can perform mathematical calcula-
tions to determine the costs and ratios of
prime contractor overhead.
Using this checklist is analogous to
using assembly or composite pricing.
Assembly or composite-pricing methods
estimate individual items of a certain
building element and divide the total cost
of that element by an appropriate unit of
measure to obtain a composite price per
unit of measure (i.e., $5.50 per ft2 for an 8-
inch/203-mm thick masonry partition).
The total cost of prime contractor
overhead also can be divided by some
parameter, such as direct cost, to obtain a
percentage of prime contractor overhead
to direct cost. Other costs that can be
derived are the prime contractor overhead
cost per month and the prime contractor
overhead cost per gross m2.

22 Cost Engineering Vol. 38/No. 8 AUGUST 1996


costs of installed material and equipment Table 2—Prime Contractor Overhead Spreadsheet Checklist Organized by Type of
elements and material and labor directly Overhead Cost
involved in the physical construction of
the permanent project [1].
Prime contractor overhead can be cat-
egorized many different ways. Deciding
how to organize it is generally left up to
each company. There is no standard
grouping; however, it is a good idea to
standardize within the same organization.

Prime Contractor Overhead Categorized


by Type of Overhead Component
Table 1 is an example of a prime con-
tractor overhead spreadsheet checklist cat-
egorized by type of overhead component.
This prime contractor overhead cost esti-
mate is from one of 20 randomly-selected
cost estimates prepared by a cost engineer-
ing firm in the southeast US. This exam-
ple represents a medical training facility
(1014 gross m2) located in northern
Florida. The project’s duration was 10
months and its direct cost was $1,133,213.
The spreadsheet checklist, which was
developed using Microsoft Excel, calcu-
lates the cost for each prime contractor
overhead item. It also computes the fol-
lowing data:

• the estimated total prime contractor


overhead cost ($138,230);
• the mathematical ratio of prime con-
tractor overhead cost to direct cost
(12.2 percent);
• the prime contractor overhead cost • cost related to the project’s dollar value. increases, then the estimated cost for these
per month ($13,823); and items also increases.
• the prime contractor overhead cost Cost related to the construction duration or Table 2 is the same as table 1, except
per gross m2 ($136.38). time period refers to the cost of supervision, the prime contractor overhead items for the
temporary offices, portable toilets, and tem- sample project have been organized by type
The overhead items in this spreadsheet porary utilities. These costs are usually esti- of overhead cost. The spreadsheet checklist
checklist mix the type of cost under the mated as a cost per week or month. The computes the same data as in table 1.
type of overhead component. A more logi- longer the construction time period, the
cal organization is to combine the same higher the total cost for these items.
types of cost. This reduces confusion when Fixed costs are not related to the proj- A MATHEMATICAL COMPARISON
updating and reviewing the cost of over- ect’s duration or dollar value. These cost OF PRIME CONTRACTOR OVER-
head items. items include mobilization, demobiliza- HEAD COST TO DIRECT COST
tion, surveys, initial schedules, and final
cleanup. Although some of these items Twenty randomly-selected cost esti-
Prime Contractor Overhead Categorized may be priced by the hour, day, week, or mates prepared by a cost engineering firm
by Type of Overhead Cost month, the overall project time or project in the southeast United States were used
Another way prime contractor over- dollar value does not affect their cost. in this comparison.
head can be categorized is by the type of Cost related to the project’s dollar Figure 1 shows the prime contractor
overhead cost, as shown in table 2: value refers to the cost of bonds, permits, overhead cost-to-direct cost percentage
insurance, and home-office expenses. obtained from the spreadsheet checklist for
• cost related to the construction dura- These costs are usually estimated using each of the 20 projects. The mean percent-
tion or time period; rule-of-thumb measurements such as per- age of total direct cost, indicated by the hor-
• fixed costs; and centages of direct cost. If the direct cost izontal line, is 10.1 percent. Eighteen of

Cost Engineering Vol. 38/No. 8 AUGUST 1996 23


the 20 cost estimates (90 percent) are with-
in a 3.3 percent difference of the mean.
This would be a difference of $33 for every
$1,000 of project value.
For programmatic and preliminary
cost estimates, an estimator could use 10
percent as a factor of direct cost to deter-
mine the cost of prime contractor over-
head. However, the variability of overhead
percentages to direct cost indicates that
using this type of rule-of-thumb measure-
ment during later phases is inaccurate.
Therefore, it is recommended that a prime
contractor overhead spreadsheet checklist
be used to more accurately estimate a per-
centage of direct cost.

A MATHEMATICAL COMPARISON
OF PRIME CONTRACTOR
OVERHEAD COST PER MONTH

Figure 2 shows the prime contractor


overhead cost per month obtained from
the spreadsheet checklist for each of the 20
projects. As analyzed in the previous com-
parison, the mean cost per month, indicat-
ed by the horizontal line, is $29,669.
Eighteen of the 20 cost estimates (90 per-
cent) are within $15,000 of the mean. This
represents an inaccuracy of $150,000 for a Figure 1—Prime Contractor Overhead as a Percentage of Direct Cost
project with a 10-month duration.
A mean cost per month of $30,000 is
acceptable for a programmatic or prelimi-
nary type cost estimate. However, the
checklist calculates a more accurate cost
per month for later phases of cost estimates.

A MATHEMATICAL COMPARISON
OF PRIME CONTRACTOR
OVERHEAD COST PER GROSS M2

Figure 3 shows the prime contractor


overhead cost per gross m2 obtained from
the spreadsheet checklist for each of the
same 20 projects. As analyzed in the previ-
ous comparisons, the mean cost per gross
m2, indicated by the horizontal line, is
$99.92. Eighteen of the 20 cost estimates Figure 2—Prime Contractor Overhead as a Cost Per Month
(90 percent) are within $50 of the mean.
This represents an inaccuracy of $50,000 THE APPLICATION OF PRIME architect or engineer is within the project’s
for a project with 1,000 gross m2. CONTRACTOR OVERHEAD budget. Sometimes the cost estimate
2
A mean cost per gross m of $100 is SPREADSHEET CHECKLIST establishes the budget for the project. The
acceptable for a programmatic or prelimi- DATA TO COST ESTIMATES cost estimates also can be used to check or
nary type cost estimate. However, the prime compare actual bids received from the
contractor overhead spreadsheet checklist My company prepares cost estimates prime contractors. Therefore, the cost esti-
calculates a more accurate cost per gross m2 ranging from conceptual to final. These mates chosen for the comparisons illus-
for later phases of cost estimates. are used mainly to identify whether the trated here are cost estimates only and do

24 Cost Engineering Vol. 38/No. 8 AUGUST 1996


spreadsheet checklist has been updated for
a project that is 1,000 gross m2, and has a
10-month duration and a direct cost of
$1,500,000.
To use the prime contractor overhead
spreadsheet checklist, a cost estimator per-
forms the following steps.

• Step 1—enter the project size in gross


m2 in the summary section of the
spreadsheet. This amount is used to
calculate the cost per gross m2.
• Step 2—enter the project duration in
months in the summary section of the
spreadsheet. The computer reads the
value in this cell and enters it in the
detail section of the spreadsheet
Figure 3—Prime Contractor Overhead as a Cost Per Gross m2 where months are indicated. If the
unit of measure for the overhead item
not represent the actual cost of prime con- By using a prime contractor overhead is in weeks, the cell value is multi-
tractor overhead by the prime contractor. spreadsheet checklist, the cost estimator plied by four.
There are many types of cost estimat- can quickly update the current overhead • Step 3—enter the estimated amount
ing software packages available; however, line items in the spreadsheet checklist and of project direct cost in the summary
because of my company’s diverse clien- determine the prime contractor overhead section of the spreadsheet. This cost is
tele, we use three packages to prepare cost lump-sum amount, the prime contractor used to calculate the cost related to
estimates: the US Army Corps of overhead percentage to direct cost, the cost the project’s value and to calculate
Engineers Microsoft Computer Aided per month, or the percentage of any over- the percentage of overhead cost to
Cost Estimating System (MCACES), the head item to direct cost. The checklist also direct cost. Microsoft Excel formulas
US Navy’s Cost Engineering System is good written documentation for the perform these calculations.
(CES), and a cost estimating package used development of prime contractor overhead • Step 4—in the detail section of the
for the private sector—MC-Squared from costs, regardless of the way the estimator spreadsheet, enter zero as the quantity
Management Computer Controls. chooses to present the cost in the estimate. for the items that are not applicable to
Each program requires the user to the current project.
present prime contractor overhead cost • Step 5—review the unit cost in the
differently. Of course, all of them allow a A STANDARD PRIME CONTRAC- detail section of the spreadsheet for
cost estimator to itemize the prime con- TOR OVERHEAD SPREADSHEET items that are applicable and adjust
tractor overhead. The contractor bond, CHECKLIST CATEGORIZED BY them according to the specific proj-
which is part of the overhead costs, can be TYPE OF OVERHEAD COST ect’s location type.
estimated as a percentage of direct cost or • Step 6—in the detail section of the
as a dollar amount in MCACES. MC- The development of a standard prime spreadsheet, enter the price quotation
Squared and CES estimate the bond as a contractor overhead spreadsheet checklist or enter the factor contained in a for-
percentage of direct cost. can be helpful in analyzing and estimating mula for cost related to the project’s
Home-office expense, which is also part prime contractor overhead cost. The fol- value. The factor is usually a rule-of-
of the overhead costs, is estimated as a per- lowing two ways to organize prime con- thumb measurement such as a per-
centage of direct cost in MCACES; CES tractor overhead have also been presented: centage of direct cost.
and MC-Squared do not offer an option to
enter home-office expense as a separate cost. • by type of overhead component; and After completing these steps, the
Builder’s risk insurance, which is • by type of overhead cost. prime contractor overhead spreadsheet
another item included in overhead, can be checklist computes the following informa-
estimated as a percentage of direct cost in Organizing prime contractor overhead tion:
MC-Squared, while MCACES and CES cost by type of cost, as opposed to type of
do not offer an option to enter builder’s component, groups the same types of cost • the total prime contractor overhead
risk as a separate cost. together, making it easy to update and cost;
The remainder of the overhead cost review them. For this reason, the standard • the percentage of prime contractor
can be estimated as a percentage of direct prime contractor overhead spreadsheet overhead cost to direct cost;
cost or as a dollar amount in MCACES checklist is organized by type of overhead • the prime contractor overhead cost
and MC-Squared, while CES estimates cost. per month;
the remainder overhead cost as a percent- Table 3 shows the standard checklist • the prime contractor overhead cost
age of direct cost. organized by type of overhead cost. The per gross m2; and

Cost Engineering Vol. 38/No. 8 AUGUST 1996 25


Table 3—Prime Contractor Overhead Spreadsheet Checklist Organized by Type of • the percentages and costs applied to
Overhead Cost the MCACES, CES, or MC-Squared
cost estimates, accordingly.

The information is used to prepare a par-


ticular cost estimate. If further overhead
cost adjustments are necessary, they can
be accomplished quickly and easily by
using the prime contractor overhead
spreadsheet checklist.

rime contractor overhead can be

P categorized many different ways,


including by type of overhead
component or by type of over-
head cost. Combining the same types of
overhead costs reduces any confusion when
updating and reviewing the cost of overhead
items. Development of a standard prime
contractor overhead spreadsheet checklist
helps to analyze and estimate prime con-
tractor overhead. The costs and ratios gen-
erated from this spreadsheet checklist are
relevant to cost-estimating software pack-
ages; the costs and ratios also can be used in
cost-estimate comparisons. The results from
these comparisons can produce or support
rule-of-thumb measurements.

ACKNOWLEDGMENTS
I would like to thank my wife, Suzie,
for her patience and support in my prepa-
ration of this article. I also would like to
thank Michael C. Ray, PE CCE, for his
inspiration that led to the idea for this arti-
cle. I also wish to acknowledge the assis-
tance and cooperation of Project Time &
Cost, Inc., Atlanta, GA, in providing source
material and background information.

REFERENCES

1. AACE International. Cost Engineers’


Notebook, Vol. 1. Morgantown, WV:
AACE International, 1988.

26 Cost Engineering Vol. 38/No. 8 AUGUST 1996


Walter B. Jones, CCC, in construction technology. He is a certified Index to Advertisers
is a cost and schedule cost consultant and is a member of AACE
consultant for Project International and PMI. He is currently pur- Reader
Time & Cost, Inc., in suing certification as a project management Response
Number Advertiser
Atlanta, GA. He has professional.◆
over 14 years of experi- Back to Table of Contents 200 Project Planner,
ence in cost estimating Primavera Systems, Inc.,
on a wide range of proj- inside front cover.
ects such as barracks, convention centers,
225 Success, U.S. Cost,
courthouses, hospitals, prisons, office build- back cover.
ings, post offices, and warehouses. Mr.
Jones graduated from Louisiana State 916 R.S. Means, page 27.
University in 1981 with a bachelor’s degree

Attention
AACE Members!
Has your address or
phone number changed
in the last year?
Will they be changing
in the near future?
Have you informed
Headquarters?
FPO
If you have moved or will be Please pickup the
moving soon, or have had your 1/2 page, B&W
phone number changed since the R.S. Means
last membership directory was ad from the June ‘96 issue, page 18,
released, and aren’t sure if your
and strip in here.
information has been updated,
please contact AACE Head-
quarters as soon as possible. The Be sure to include the
1996-1997 Membership Direc- Reader Response Number below.
tory will be released soon and we
want to make sure that it is as
accurate as possible.

Call
COST
5
.
0
8
or
8
6
9
2
.
4
0
3
or fax us at
8
7
5
1
9
2
.
4
0
3
with your new address
and/or phone number
today!
Reader Response Number 916

Cost Engineering Vol. 38/No. 8 AUGUST 1996 27

You might also like