Professional Documents
Culture Documents
An Introduction to Standard
Forms
• Traditionally JCT has led the building market while engineering was
dominated by the ICE standard forms.
• ‘Standard forms are designed in a way that is comprehensive, and cover most of the
pitfalls which surround contractual relations in the building industry’
• ‘Standard forms reflect the benefits that are accrued through precedent – this is
achieved by defining benchmark provisions which reflect a generally acceptable
position in practice’
• ‘JCT contracts are developed via a cross-section of the building industry involved in the
contract process. This means that clients (private and public sector), consultants,
contractors, specialists, and sub-contractors are all involved in the development of JCT
contracts’
JCT Website
JCT Design and Build 2016
‘A standard form is supposed to be just that. It loses its value if those using
it or, at tender stage those intending to use it, have to look outside it for
deviations from the standard.’
Frequent amendments
Some basic funder/employer requirements are still missing:
• a single point of responsibility on the Contractor for the ERs and CPs;
• express obligations to prevent nuisance and trespass in carrying out the works; and
• the ability for the Employer to freely assign the contract without the Contractor’s consent.
NEC4
NEC4 Core Principles
‘We recognise the UK supply chain operates differently to France. The French
way is to go for large lump sum turnkey contracts. The UK supply chain is more
complex and relationship based. We’ll use the NEC form as it is more
collaborative and what we want on these plants is good solid relationships.’
‘We’ll be looking closely at how main contractors collaborate with their supply
chain.’
‘Nuclear work is about getting it right first time, every time. What we are doing is
running a marathon. We need to train for the marathon. So getting the right
people is a key issue.’
EDF
NEC4 Engineering and Construction
Contract (ECC)
• Six main options.
• Nine core clauses.
• Three dispute resolution options:
• W1 – Adjudication (where HGCRA does not apply);
• W2 - Adjudication (where HGCRA applies); and
• W3 – Dispute Avoidance Board (and HGCRA does not apply).
• Twenty two secondary options – the X Clauses.
• Three UK-specific options – the Y Clauses:
• Option Y(UK)1 – Project Bank Account;
• Option Y(UK)2 - HGCRA; and
• Option Y(UK)3 – third party rights.
• Z Clauses: ‘Additional conditions of contract’
NEC4 – Main Options
Typical Z clauses:
• The provision of collateral warranties.
• Workmanship, design and prohibited materials.
• Assignment.
• Subcontracting.
NEC4: Early Contractor
Involvement
Consequences:
• Contractor:
• Core clauses 61.5 and 63.7 – If the Contractor did not give an
Early Warning in relation to a Compensation Event then the
Compensation Event is assessed as if the Contractor had given
the Early Warning.
• Client:
If the Contractor does not notify a compensation event within eight weeks of
becoming aware that the event has happened, the Prices, the Completion
Date or a Key Date are not changed unless the event arises from the Project
Manager or the Supervisor giving an instruction or notification, issuing a
certificate or changing an earlier decision.’
Other Forms
FIDIC
• Fédération Internationale Des Ingénieurs-Conseils
• Conditions of Contract for Construction – Red Book
• Conditions of Contract for Plant & Design-Build –
Yellow Book
• Primarily utilised for international engineering and
infrastructure projects
• Red Book is a re-measurement contract; Yellow
Book is a lump sum contract
• FIDIC’s Golden Principles – “encapsulate the
essence of a FIDIC Contract”
• Fitness for purpose
Partnering Arrangements
• Contractual partnering arrangements:
• PPC 2000;
• JCT Constructing Excellence Contract 2016;
• Strategic Forum Model Form of Agreement for an Integrated
Project Team;
• Framework Alliancing Contract (FAC-1);
• Term Alliance Contract (TAC-1);
• NEC4 Alliance Contract.
• Non-contractual partnering:
• JCT Framework Agreement;
• JCT Partnering Charter (non-binding);
• NEC4 Option X12: Multiparty Collaboration.
Major Projects
• JCT Major Projects Construction Contract
• lump sum contract with standard form subcontract;
• initial employer design, developed by the contractor;
• a short document;
• mediation, adjudication, litigation.
• CIOB’s Time and Cost Management Contract Suite
• previously known as the Complex Projects Contract,
• traditional procurement or design and build;
• special conditions for construction management or management contracting;
• pricing might be fixed, target costs, measured term, fixed fee, or
reimbursement;
• partnering or alliancing may be incorporated;
• the focus is on programming, and the use of critical path networks.
Short Form Agreements
• Management Contracting:
• fast track construction providing for the design to proceed as the
works are constructed;
• cost risks and design constraints;
• contractor becomes involved in the “buildability” of the project;
• packages of work let to specialist subcontractors by the management
contractor.
• Construction Management:
• the construction manager is part of the design team;
• packages are let directly by the client upon the recommendation of
the construction manager.
Term Maintenance and Facilities
Management Contracts