Professional Documents
Culture Documents
Richard Patterson
NEC and Procurement Specialist
Mott MacDonald
27 April 2022
Richard Patterson
BA MBA CEng FICE
Mott MacDonald NEC
Advisory Services
33 Years with
Mott MacDonald
26 Years with
NEC….and FIDIC
• We always do it
this way.
Account: EVA1
Environment Agency
Account: AOC1
Martha Taylor
Central
Matt Fox
Account: CON1
Contractors
Charlie Bell
Account: AOS1
South
Dan Rouse
To start ‘NEC’ is now a ‘brand’
APM website
• NEC basics
• NEC collaboration
• NEC4 for process contracts
• NEC climate change
• NEC3 to 4 – use it!
• NEC basics
• NEC collaboration
• NEC4 for process contracts
• NEC climate change
• NEC3 to 4 – use it!
Flexibility
Prof’l Services
High ECC TSC
Contract
PSC
Engineering and Construction Contract Term Service Contract
Complexity ECS
Project Engineering and Construction
Subcontract
ECSC
Prof’l Services
Short Contract
PSSC TSSC
Engineering and Construction
Short Contract
Term Service Short Contract
ECSS
Engineering and Construction
Low Short Subcontract
Framework Contract
Adjudicator’s Contract
business design construction operation
case
NEC3 family
Prof’l Services
TSSC
Management
Alliance Contract
Subcontract
(Feb 2021)
High
PSSC
Facilities
FMC
Contract
Term Service
Subcontract
DBOC
Complexity
Design Build and Operate Contract
Project
Short Contract
Management
(Feb 2021)
FMSC
Facilities
Low
X10
X11
X12
X13
X14
X15
X16
X17
X18
X20
X21
X22
X8
X9
X1
X2
X3
X4
X5
X6
X7
secondary options
F Management contract
Depends on subcontracts used
Accepted
communications
Programme
compensation
early warning
events
< 8 wks
Contractor notifies
PM instructs quote
1wk
ECC3: 3wk
or
PM silent?
C notifies; PM says no Contractor quotes
PM has further
2 wks; 2wk
otherwise
‘treated as PM replies
accepted’
• NEC basics
• NEC collaboration
• NEC4 for process contracts
• NEC climate change
• NEC3 to 4 – use it!
Collaboration
• NEC basics
• NEC collaboration
• NEC4 for process contracts
• NEC climate change
• NEC3 to 4 – use it!
• NEC basics
• NEC collaboration
• NEC4 for process contracts
• NEC climate change
• NEC3 to 4 – use it!
• NEC basics
• NEC collaboration
• NEC4 for process contracts
• NEC climate change
• NEC3 to 4 – use it!
Gender neutral
Some ‘fixes’
Priced
Contract A B
Target
Contract C D
Cost
Reimbursable E
Management
Options also in
Contract
Professional Services F
Contract (PSC)
Contractor
share share
- the ‘Contractor’s share’ percentage ranges
50
tendered % ‘pain’
total of the Prices – the moving target! 100 %
the
Prices 35 ‘gain’
%
80 %
amount 0
Employer
compensation %
events
Works or
Works
Information /
Information/
Scope form of
Scope for
Contractor's agreement CDM PCI
Site design
Information constraints
activity
conditions of
schedule
contract
(Options factual info
Core A and C)
Options
Option Z (boq
(Options
incorporates by ref.
Schedule(s) B and D)
of Cost
Components optional
Accepted
Programme
(c) Mott McDonald : NEC for British Water requires info.to be stated in 40
What we have on NEC
• Richard Patterson
• worked for Thomas Telford (TT) in 2007 on global business
development and training
• part of NEC4 drafting team
• Gives NEC Training’s 4 day ECC PM accreditation course
• helped develop MM business in NEC in Hong Kong
• Extensive publications on all things NEC
• has trained on NEC in UK, Australia, NZ, Germany, France,
Ethiopia, USA
• Alec Kowalski
• 10 years experience as ECC Project Manager
• Gives NEC Training’s 4 day ECC PM accreditation
course
• Petter Siljehag
• Extensive NEC experience as ECC PM and Supervisor