You are on page 1of 3

PROSPECTIVE ASSESSMENT

EXAMPLE 1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delays: 5 weeks

Employer delays: 3 weeks + 4 weeks = 7 weeks

EOT = 2 WEEKS

EXAMPLE 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delays: 3 weeks + 4 weeks = 7 weeks

Employer delays: 5 weeks

EOT = 5 WEEKS

EXAMPLE 3
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delays: 5 weeks

Employer delays: 3 weeks + 4 weeks = 7 weeks

EOT = 7 WEEKS

EXAMPLE 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delays: 3 weeks + 4 weeks = 7 weeks

Employer delays: 5 weeks

EOT = 0 WEEKS
RETROSPECTIVE ASSESSMENT
EXAMPLE 1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

After 2 weeks Employer delay taken off, Employer delay no longer critical:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delays: 5 weeks

Employer delays: 3 weeks + 4 weeks = 7 weeks

EOT = 2 WEEKS

EXAMPLE 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

After 2 weeks Contractor delay taken off, Contractor delay no longer critical:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delays: 3 weeks + 4 weeks = 7 weeks

Employer delays: 5 weeks

EOT = 5 WEEKS
EXAMPLE 3
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delay never critical.

Contractor delays: 5 weeks

Employer delays: 3 weeks + 4 weeks = 7 weeks

EOT = 7 WEEKS

EXAMPLE 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Employer delay never critical:


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay

Contractor delays: 3 weeks + 4 weeks = 7 weeks

Employer delays: 5 weeks

EOT = 0 WEEKS

RESULTS

Total Employer Prospective Retrospective


delay EOT EOT
Example 1 Employer delay longer Contractor delay first 7 2 2
Example 2 Contractor delay longer Employer delay first 5 5 5
Example 3 Employer delay longer Employer delay first 7 7 7
Example 4 Contractor delay longer Contractor delay first 5 0 0

You might also like