EXAMPLE 1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 2 WEEKS
EXAMPLE 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 5 WEEKS
EXAMPLE 3
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 7 WEEKS
EXAMPLE 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 0 WEEKS
RETROSPECTIVE ASSESSMENT
EXAMPLE 1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
After 2 weeks Employer delay taken off, Employer delay no longer critical:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 2 WEEKS
EXAMPLE 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
After 2 weeks Contractor delay taken off, Contractor delay no longer critical:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 5 WEEKS
EXAMPLE 3
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 7 WEEKS
EXAMPLE 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EOT = 0 WEEKS
RESULTS