Professional Documents
Culture Documents
Document No. & Title:, DBR For Civil and Structural Works
Document No. & Title:, DBR For Civil and Structural Works
KEC-TC318-KNG-90-DBR-105 Page |2
Contents
1.0 GENERAL ..................................................................................................................................................... 6
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 Page |3
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 Page |4
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 Page |5
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 Page |6
1.0 GENERAL
M/s. KEC International Limited has been awarded the contract to construct the 132/33kV
AIS substation at Khungri.This document comprises of design philosophy, standards, codes
of practice reference used for the Civil and Structural works for the proposed substations.
Project Title: Procurement of plant for design, supply, installation, testing and
commissioning of ghorahi - khungri (madichaur) 132 kv transmission line and associated
substations at khungri and ghorahi.
The site of substation located at Province-5, Sunil Smiriti Gaupalika, ward no 7, Khungri, Rolpa
is approximately 75 kilometers Far North-East from Bhaluwang, Dang. The site lies in contact
with Bhaluwang-Libang Highway. The nearest Airport is Kathmandu airport. The nearest port is
Kolkata (India).
2.2 PLANT ELEVATION
Top of Rail Cum Road (Height crest level): 300 mm above FGL
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 Page |7
2.4 DRAINAGE
The maximum velocity for pipe drains and open drains shall be limited to 2.4m/sec and
1.8m/sec respectively. However, minimum non-silting velocity of 0.6m/sec shall be ensured.
The runoff shall be calculated using the ration formula,
Q = C.I.A,
Where,
C = runoff coefficient, I = intensity of extreme rainfall, A= catchment area.
Discharge of the drain shall be calculated using Manning’s formula,
Q = (A.Rh^2/3.S^1/2)/n
Were,
A = Area of cross section of flow, Rh = Hydraulic mean depth, S = slope of drain,
n = Rugosity coefficient.
Peak Ground Acceleration for all steel structures and major equipments.
2.6 ALTITUDE
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 Page |8
2.7 TEMPERATURE
KHUNGRI: KEC-TC318-KNG-90-DBR-106
KHUNGRI: KEC-TC318-KNG-90-DBR-102.
This document presents the overall basis for design of all Civil, Structural &Architectural Works in general
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 Page |9
6 Transformer Foundations -
10 Fire wall -
All scope of works shall be as per technical specification and contract agreement.
Control Room building to be provided at khungri Substation. Control Building shall be Single storied RCC
structure.
Control Room building to be provided at khungri Substation. Control Building shall be double storied RCC
structure.
The firefighting pump house building shall be essentially single storied reinforced cement concrete (RCC)
framed Building. The water pumps for the service/domestic water system as well as for fire protection
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 10
shall be housed in a pump house. Raw Water tank of suitable capacity shall be provided near to Pump
house.
A RCC framed room of size 40 m2 (Shall be as per technical specification, Bid price schedule (BPS) or
actual requirement), with one bedroom, one kitchen and one bathroom shall be provided near gate. All
This comprises the design, supply, and construction of foundations and other RCC constructions for
switchyard structures, equipment supports, trenches, drains, jacking pad, pulling block, fencing,
boundary wall, transformers, reactors, marshalling kiosks, auxiliary equipment’s & systems, rail tracks or
for any other equipment or service and any other foundation/RCC construction required to complete the
work.
4.7.1 Roads
All roads shall be as per the approved GA or requirement complying to the requirement of contract
technical specification.
RCC Storm water drainage system shall be provided as per Technical Specifications. For the drainage of
site suitable R.C.C. open drains shall be provided on one side of the roads. However, where open drains
are not possible and for road crossings pipe drains, concrete. pipe of class NP3 shall be used. For rail
crossings, RCC pipes of class NP4 shall be provided. For design of RCC pipes for drains and culverts,
relevant IS codes shall be followed. Pipe drains shall be connected through manholes provided at an
interval of maximum 40.0m. Refer Cl. 18.5 of this document for other details.
Separate Septic tank along with soak pit to be constructed at Control Building, Staff Quarter
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 11
Building and Security Room respectively. Sewage from buildings shall be collected and
connected to septic tank and soak pit system of suitable size within the stations. The sizing of the septic
tank shall be done as per the recommendation from IS 2470 part 1 unless specified in the technical
specification.
Control building: 10
Staff quarters: 50
Guard house: 05
Minimum free board above the sewage inside the septic tank shall be 300mm.
Cable Trench and Culverts shall be provided as per scope of work and as per Technical
Specifications.
As per Technical Specification all RCC stairs shall have maximum Riser of 150 mm and
minimum tread of 300mm. Minimum width of stair shall be 1500mm.
Hand-railing minimum 900mm high shall be provided around all floor/roof openings,
projections/balconies, walkways, platforms, steel stairs etc. All handrails shall be 32 mm nominal bore MS
pipes (medium class) and shall be galvanised. All Ladder and rungs for ladder shall be galvanized as per
For RCC stairs, hand railing with 20 mm square MS bars, balustrades with suitable MS flats & aluminium
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 12
Details shall be as per clause 15.8 Chapter-20 Civil works of technical specification.
Minimum thickness of external walls shall be 360 mm with 1:4 cement sand mortar. Partition walls if
any shall be of 240 mm thick brick masonry in cement sand mortar (1:4). 110 mm thickness shall be
50mm thick DPC (1:2:4) with water proofing admixture as per recommendation of Manufacturer shall be
The parapet walls on roof shall be of Brick Masonry. Minimum height of parapet walls shall be 750 mm
and thickness shall be 230mm and plastered with cement sand plaster (1:6).
5.4 DRAINAGE
For all buildings and areas, suitable arrangement for draining out water collected from equipment blow
downs, leakage, floor washing, fire-fighting etc shall be provided on each floor. Proper slope shall be
provided in suitable direction on the floor for effective drainage for all buildings.
Drains shall be provided around all buildings to receive the drainage water from roof and floor and lead
Underground structures like pits and cable trenches etc, shall be provided as per Technical
Specification.
All underground structures like water retaining structures, Sump pits etc. shall be provided
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 13
Antiweed treatment shall be done before gravel spreading as per the technical specification.
Anti-termite treatment shall be carried out as per recommendations of IS 6313 part 2: 2001.
6.1 GENERAL
All structures shall be designed for the most critical combinations of dead loads, imposed loads,
equipment loads, crane loads, wind loads, seismic loads and any other loading conditions which
can occur during the design life of the facility.
Dead loads consist of the weights of the structure complete with finishes, fixtures, partitions,
wall panels and all equipment and shall be taken as per IS:875.
The following unit weight of material shall be considered for computation of loads:
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 14
Live Loads reduction for analysis shall be in accordance with the provisions of IS: 875 & IS: 1893.
Static and dynamic loads of major equipment shall be based on the manufacturer's data of the specified
equipment. However, where the uniform floor live load adequately accounts for the equipment moving
weight, the weight of such equipment as a dead load shall not be considered e.g. switchgear and control
room floors are usually designed for a live load that includes the equipment weight.
erection loads, operation / maintenance loads etc. The loads considered shall not less than
The loads listed here under are minimum loads for the areas involved. Special use areas
shall be investigated, and loads revised upward as necessary. Floors and supporting
members which may be subjected to heavy equipment live loads shall be designed on the
basis of the weight of equipment or specifically defined live loads, whichever is greater.
c) Flat Roof (Accessible without Equipment’s) - 1.5 kN/m2 + hung loads (if
any)
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 15
f) Walkway - 3 KN/m 2
g) Control Room- - 10 KN/m2
Live Loads reduction for analysis shall be in accordance with the provisions of
IS: 875 & IS: 1893.
Wind loads on structures shall be calculated as per provisions of IS: 875 (Part 3)-2015. The wind shall be
assumed to blow in any direction and most unfavourable condition shall be considered. Sample design
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 16
The following coefficients have been adopted for calculation of design wind speed:-
K2= Terrain height & structure size factor= As per IS-875, part 3-2015
The internal pressure co-efficient will be as per IS: 875 (Part 3))-2015.
Seismic forces shall be As per IS: 1893-2015 - Part- 4 & IS 1893-2016 - Part-1 seismic
SEISMIC PARAMETERS
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 17
In the calculation of seismic load, the dead load, permanent equipment load, and appropriate percentage
of floor live load will be considered. Roof live load will not be considered. For the calculation of seismic
load, the percentage of live load shall be based on general live load on that area.
Earth pressure for all underground structures shall be calculated using coefficients of earth pressure at
rest: co-efficient of active or passive earth pressure (whichever is applicable). However, for the design of
Earth pressure coefficients shall be calculated based on the Ø value of the soil mentioned in approved
soil report. For the design of underground structures, the effect of water table shall be considered
In addition to earth pressure and ground water pressure etc., a surcharge load of minimum 2 T/sq.m shall
also be considered for the d e s i g n of all underground structures including channels, sumps, tanks,
trenches, substructure of any underground hollow enclosure etc., to account for the vehicular traffic in
The following basic load cases shall be considered for the analysis:
The nomenclature shall be as follows
WL - Wind Load
SL - Seismic Load
CL - Crane Load
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 18
Building structures shall be designed for the most critical combinations of dead loads, super- imposed
loads, equipment loads, crane load (if any), wind loads and seismic loads.
a) All structures shall be designed for the worst combination of dead loads, live loads, wind
b) The design of steel structures for the buildings shall be done by IS 800:2007 preferably by
c) The design of R.C.C. structures shall be done in accordance with IS: 456:2000
d) Permissible stresses for different load combinations shall be taken as Per relevant IS Codes
Steel Structures
Load combinations for analysis and design of steel framed structure shall be as per IS:800 : 2007 (limit
state design).
The load combinations mentioned below for RCC structures are applicable for steel structures also.
RCC Structures
Load Combinations for Structural Design of Beams and Columns For Concrete Buildings
(Factored Forces)
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 19
Note: - **In addition to above other loads shall be applied depending upon the type
of building.
All designs of RCC structures shall be carried out by limit state method as per IS:456 unless use of working
stress method is specifically mentioned. Design strength of materials and design loads shall be calculated
using appropriate partial safety factors over characteristic strength and characteristic loads as per IS: 456.
Soil Data shall be provided after completion of Soil Investigation at Site and after receipt of Soil Report.
RCC water retaining structure like storage tanks, Oil Pits and Sump etc. shall be leak proof and designed
according to IS : 456 & IS:3370.
Bearing capacity of the soil shall be allowed to increase under seismic/wind load condition
as per provision of IS: 1893-2002 & IS: 875.
Piles shall be RCC Bored Cast-in-situ piles or Precast as per IS 2911. Water Table – as per Geotechnical
Report and to be considered for analysis and design of foundations accordingly.
All the underground structures shall be designed as cracked sections with maximum crack width of0.2mm
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 20
for liquid retaining structures and 0.3mm for other structures according to Cl.35.3.2 of IS456.
Settlement limit of various foundation types shall be as listed below as per IS 1904-1986, Table 1:
Limiting value of deflection for steel structures shall be governed by Clause 5.6.1 of IS800 /NBC. In
addition to the above the structures should generally satisfy the following limiting deflections.
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 21
The cable trench walls shall be designed for the following loads.
1) Dead load of 155 kg/m length of cable support + 75 kg on one tier at outer edge.
Cable trench cover shall be designed for self-weight of top slab + concentrated load of 150 kg at centre of
span of each panel.
The following minimum grades of concrete as per IS: 456 shall generally be used for the type of structures
noted against each grade. Cement shall be used for all structures as per TS.
Nominal Mix (1: 4: 8) PCC Fill Concrete, PCC below foundations, trenches and
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 22
Nominal Mix (1: 3: 6) PCC Minimum thickness of the layer shall be 75 mm below
foundation of firefighting water tank.
Grade M25 RCC All R.C.C. members except where other grades are
specified e.g. Foundation and super structure, grade
beams, pedestals, ground floor slabs, roof slabs, cable
and pipe trenches, Water retaining structures below and
above ground & Piles.
The concrete composition of PCC below ground floor slab and plinth protection shall be as per
7.4 REINFORCEMENTS
Reinforcement bars shall be as per the following codes: Reinforcement steel shall confirm to
IS 1786. Grade of Reinforcement Steel shall be TMT of HYSD of grade Fe- 500.
The minimum cover to the reinforcement for all the structures, shall be as per IS-456 based on
Footing 50mm
Column 40mm
Bottom of plinth beam in 40mm
contact with earth
Other beams above Ground 30 mm
level
Slab on grade 40 mm for earth face & 25mm for
top face
Slabs above Ground level 20 mm
Walls in contact with earth 40 mm for earth face & 25mm for
inner face
Pile cap 75 mm
Piles 75 mm as per IS:2911, part 1 Sec. 2
Firewall 40 mm
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 23
All structures shall be designed for worst combination of dead loads, live loads, wind loads,
loads due to deviation of conductor, loads due to unbalanced tension in conductor, erection loads &
short circuit forces. Wind loads on switchyard structures shall be calculated as per IS 875(Part 3)-2015.
Switchyard steel structures like towers and girders shall be designed to confirm IS:802 1995 with
mentioned factor of safety. The towers and girders shall be modelled together and analysed as truss
elements in STAAD.Pro in 3d with all the loads applied accordingly. Member design checks are performed
All structural steel members including Anchor bolts, etc., shall be hot dip galvanized after fabrication.
Weight for zinc coating shall be at least 610 gm/m2 and in case of members under 5mm but not less than
Dead load includes the self-weight of gantry including all electrical accessories. It also includes
the maintenance load of 150 kg (weight of man with tool) at each phase of the girder.
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 24
Fwt = Pz x Cf x Ae
Where
Fwc = Pz x Cf x d x L
Where
Fwc = Pz x Cf x Ae
Switchyard gantry structures shall be designed for Broken wire condition. The design
of all structures shall be based on the assumption that stringing is done only on one
side i.e., all the three (phase) conductors broken on the other side.
Switchyard gantry structures shall be designed for short circuit condition. The design
of all structures shall be based on the assumption that stringing is done only on one
side i.e., all the three (phase) conductors broken on the other side.
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 25
STRESS: Ultimate allowable stress of steel sections are considered as per IS:802
Material: Structural steel conforming to IS: 2062 having minimum guaranteed yield
stress 2550 kg/sq cm for Mild steel (E250 Gr. A) and 3570 kg/sq. cm for High tensile
steel (E350 Gr). The minimum thickness of galvanized structural members shall be
as follows:
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 26
Bracings, Belts - 4 mm
Redundant - 4 mm
Bolts used for connections shall confirm to property class 5.6 as specified in IS: 1367 &
follows:
Anchor bolts for Towers and Equipment however shall confirm to IS 5624 and
material shall confirm to IS 2062 (Grade 4.6)
Gantry Structure
(a) Broken wire condition = Normal Tension from conductors + wind Load on tower, conductors
& insulators + dead loads.
(b) Short circuit condition = Short Circuit Tension from conductors + wind Load on tower,
conductors & insulators + dead loads (due to combination of two
accidental loads simultaneously)
Where,
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 27
The supporting structure for equipment of Tertiary equipment shall be comprised of lattice
structural steel conforming to IS 2062. The design of lattice type support structure shall be
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 28
Wind Load = Ae x Pz x Cf
Dead load: - weight of equipment with all accessories, weight Structure and bus &
the weight of man with tools & kit = 150Kgs.
The supporting structure for 220kV & 132kv equipment are of PIPE structure. PIPE TYPE
supporting structure for equipment shall be comprised of G.I pipe of grade Yst 22 or higher
grade (higher grade will be used in case of restriction of dia. Of pipe and higher imposed loads)
of confirming to IS 1161 – 1979. The design of pipe type support structure shall be carried out as
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 29
Wind Load = Ae x Pz x Cf
Dead load weight of equipment with all accessories, weight of structure and bus &
the weight of man with tools & kit = 150 Kg.
Note: Additional dynamic loads shall be considered for circuit breaker wherever
applicable.
The design and supply of CB structure would be in the scope of vendor. Only design
of foundation is in contractor’s scope.
The design of foundation would be done considering a factor of safety of 1.5.
BASIC LOAD CASES
1. Dead Load
2. Wind load
3. Short circuit force (SCF)
UNFACTORED LOAD COMBINATIONS
1. Dead Load + Wind load
2. Dead Load + Wind load + SCF
FACTORED LOAD COMBINATIONS (Applicable only for design of lattice structures)
1. 2 x Dead Load + 2 x Wind load
2. 1.5 x Dead Load + 1.5 x Wind load + 1.12 x SCF
Work covered under this Clause comprises the design and construction of foundations and other RCC
constructions for switchyard structures, equipment supports, trenches, drains, jacking pad, pulling block,
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 30
bus supports, transformers, reactors, marshalling kiosks, auxiliary equipment & systems, tanks, rail tracks
or for any other equipment or service and any other foundation/RCC construction required to complete
the work. The design of foundation shall be done as per Limit State Method according to IS 456:2000. All
foundations are designed for most critical loading combinations transferred from super structure. For
switchyard structure foundations, anchor bolt with template will be provided along with foundation
concrete.
All tower/gantry structures, lightning mast foundations and equipment supporting structures
shall have foundation bolts and base plate type of connection for transferring load from the
INPUTS:
Load data: -
Vertical Loads, shear Forces & moments calculated from design of structures for Normal
condition and for Short Circuit condition.
DESIGN METHODOLOGY
A) Safety Checks:-
2) Check for overturning & sliding: - The foundation is designed to resist forces due to Overturning
and sliding. The factor of safety against overturning and sliding is Considered as 1.4 for (NC) and (SCF).
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 31
B) Designs:-
1) Maximum thickness of the raft shall be provided at the face of the column and minimum thickness
(150 mm) of the base slab shall be at the extreme edge of the raft.
2) Base slab shall be designed for maximum bending moments due to Net bearing
pressure.
The maximum shear is calculated at a distance equal to half of effective depth of footing from the face of
the pedestal.
The calculated shear stress should not exceed the values of 1.25 N/sq mm for M25 grade of concrete.
Partial Safety Factors is considered = 1.5 as per IS 456, limit state method
A RCC Rail cum road system integrated with the transformer foundation to enable installation and the
removal of any failed unit. The rail cum road track with a width as per design shall be provided all along
the length of the transformer area covering all the poles so that any failed unit can be moved from its
foundation to the nearest road. If trench/drain crossings are required then suitable R.C.C. culverts shall
be provided in accordance with I.R.C. standard / relevant IS. The permanent transfer track system shall
have RCC raft type foundation integrated with the converter/POWER transformer foundations. The road
cum rail track shall be of RCC construction and the surface shall be rendered smooth and suitable
drainage system shall be provided. Each Transformer /Reactor including oil conservator tank and cooler
banks etc. shall be placed in a self-sufficient pit surrounded by retaining walls (Pit walls). The clear
distance of the retaining wall of the pit from the Transformer/Reactor shall be 20% of the Transformer
/Reactor height or 0.8m whichever is more. The oil collection pit thus formed shall have a void volume
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 32
equal to 200% volume for 220 kV & above and 130% for 132 kV & below of total oil in the
Transformer/Reactor. The oil collection pits below the Autotransformer/Reactor shall be suitably
A fire wall shall be erected between each transformer (in the case of single-phase equipment) to protect
each one from the effects of fire on another.
All fire walls between transformers and reactors shall be of RCC framed structure with filler walls of RCC
construction.
The firewalls around transformers shall have a minimum fire resistance of 3 hours as per
IE rules.
The firewall shall extend 600 mm on each side of the transformer and 600 mm above the conservator
tank or safety vent.
The building walls, which act as firewalls, shall extend at least 1 m above the roof in order to protect it.
STANDARDSIS CODES
All the Indian Standards referred to shall be the latest revision (including all
amendments
issued thereto at the time of execution.
LOADS
IS: 875-2015 Code of Practice for design loads (other than earthquake) for
buildings (all parts) and structure (all relevant parts)
IS: 1893 -2016 Criteria for earthquake resistant design of structure (All Parts)
FOUNDATIONS
IS: 1080 - 1985 Code of Practice for design and construction of shallow
foundations insoils (other than raft, ring and shell)
IS: 1904 - 1986 Code of Practice for design and construction of foundations in
soils :General requirement
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 33
IS: 2950 - 1981 Code of Practice for design and construction of raft foundations;
Part
–I: Design.
IS: 8009 Code of Practice for calculation of settlement of foundations:
-Part-1, 1976 Shallow foundations subject to symmetrical static vertical loads
RCC
IS: 456 :2000 Code of Practice for Plain and Reinforced Concrete
IS: 3370 Code of Practice for Concrete Structures for the Storage of liquids
- Part-1, 1965 General Requirements
- Part-2, 1965 Reinforced Concrete Structures
- Part-4, 1967 Design tables
IS: 3414 - 1968 Code of Practice for design and installation of joints in buildings
IS: 4326 - 1993 Code of Practice for earthquake resistant design and construction
ofbuildings
IS: 13920 - 1993 Code of Practice for ductile detailing of reinforced concrete
structuressubjected to seismic forces
STRUCTURAL STEEL
IS:808 - 1989 Dimensions for hot rolled steel beam, column channel and angle
IS:816 - 1969 Code of Practice for use of metal arc welding for general
constructionin mild steel
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 34
MISCELLANEOUS
IS:1172 - 1993 Code of basic requirements for water supply, drainage and
IS:2527 - 1984 Code of Practice for Fixing rain Water Gutter & Downpipes for
roofdrainage.
IS:2835 - 1987 Specifications for Flat Transparent Sheet Glass.
IS:3067 - 1988 Code of Practice for general design details and preparatory works
for damp proofing and water proofing of buildings
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works
132/33/11kV KHUNGRI AIS
DOCUMENT NO. SUBSTATION CIVIL
KEC-TC318-KNG-90-DBR-105 P a g e | 35
Note: The above list is suggestive and not exhaustive. Apart from these basic codes any
other related codes shall also be followed wherever required.
Document No. & Title: KEC-TC318-KNG-90-DBR-105, DBR for civil and structural works