You are on page 1of 28

T URNKEY T ENDER D OCUMENT FOR

GUARANTEED TECHNICAL PARTICULARS , S COPE OF


WORK & S PECIFICATIONS FOR CIVIL WORKS

A NNEXURE W: TD-SP-CIVIL- 456-R0.

220kV AIS TO GIS CONVERSION AT AAREY EHV S/S

Page 1 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

Technical Particulars
Sr.
Descriptions AEML Requirements (Shall be Filled by
No.
Vendor)
Grade of PCC shall be M15
with minimum Cement
content 240 kg/CUM as per
1 PCC IS 456-2000. Cement shall
be 53 grade ordinary Portland
Cement conforming to IS-
12269.
Grade of RCC shall be M30
with minimum Cement
content 320 kg/CUM as per
2 RCC IS 456-2000. Cement shall
be 53 grade ordinary
Portland Cement
conforming to IS-12269.
Grade of Reinforcement
shall be Fe 500 confirming
3 Reinforcement to IS 1786-2008 and of
make TISCO, SAIL, RINL or
equivalent
Structural steel shall be
4 Structural Steel
confirming to IS 2062-2006
Structural steel shall be hot
5 Galvanization dipped galvanized with 90
microns
Shall be non-skid fully
6 Floor tiles vitrified floor of make
'Kajaria, Asian, Boss etc.

7 Others if any To be provided by vendor

Page 2 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

SCOPE OF WORK

The following scope of civil work is envisaged for proposed conversion of 220kV AIS to GIS
at Aarey R/s.

1. Extension of Existing 220 kV GIS Plinth:- Scope shall includes construction of proposed
extended 220kV GIS plinth towards existing transformers side. The size of proposed extended
plinth shall be approximate 26MX12M. The proposed plinth shall be approximately 1.5 m above
ground level to match with existing plinth level. Also the scope shall covers construction of
5M deep cable cellar & structural steel shed over the proposed plinth.
2. Capacitor Bank Plinth:- Scope shall includes construction of proposed capacitor bank plinth
near existing GIS plinth & near Transformer-4 area The size of proposed capacitor bank plinth
shall be approximate 10MX5M. Total 5 NOS of plinth shall be constructed.
3. 220kV Cable Trench:- Proposed R.C.C. cable trench shall be constructed from existing
capacitor side to proposed extended 220kV GIS plinth. The length of proposed trench shall be
approximate 500m. Also another cable trench shall be constructed from existing transformers
to the proposed GIS plinth. The length of proposed cable trench shall be approximate 150m.
The size of the proposed 220kV cable trench shall be 1.5M(wide) X 1.5M(deep). Minimum 200
mm thick trench wall shall be provided. The top of the trench shall be covered with precast
RCC covers designed to take vehicular loads.
4. 33kV Cable Trench:- Proposed R.C.C. cable trench shall be constructed from proposed
capacitor bank near existing GIS plinth to existing control room building & shall be constructed
from proposed capacitor bank near transformer-4 area to existing control room building The
total length of the proposed trench shall be approximate 200m. The size of the proposed 33kV
cable trench shall be 1.0M(wide) X 1.0M(deep). Minimum 200 mm thick trench wall shall be
provided. The top of the trench shall be covered with precast RCC covers designed to take
vehicular loads.
5. Stainless steel safety railing shall be provided at new 220 kV extended GIS plinth.
6. Asphalt road including kerb stones shall be demolished & re-instated as wherever required.
7. Demolition of existing SWD & making of new SWD as wherever required.
8. Cable termination shall be installed on existing CT structure. If existing structure will not be
capable to the load, new foundation shall be constructed for cable termination structure
nearby the CT foundation.

Page 3 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

9. Construction of 11m high Fire wall shall be constructed for isolation between proposed 220kV
GIS plinth and existing Transformer 1.
10. Proposed foundation for 2 NOS of LM shall be constructed.
11. 50 Mtr cable duct shall be constructed including HDPE pipes, etc for road crossing.
12. 50 Mtr RCC cable trench shall be constructed for Control & LT Cables.
13. RCC culvert shall be constructed near Transformer- 4 to carry vehicular movement during
transportation of equipment’s. such as 220/33kv transformer (@ 200 Tons).
14. Shifting of N2FF panel of Tr-1 to provide space for GIS plinth extension and fire- wall. RCC/steel
framework shall be carried out at new location for N2FF panel.

Page 4 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

1.1.1 The following civil specifications shall be adopted for carrying out required civil work. Scope
shall include all associated civil works required for proposed conversion of 220kV AIS to GIS
at Aarey R/s

1.1.2 CODES & STANDARDS:-

The following codes and standards are made a part of the Specification. All standards, codes
of practice referred to herein shall be the latest edition including all applicable official
amendments and revisions.
In case of discrepancy between this specification and those referred to herein, this
specification shall prevail.

Sr. No. Code No. Name of Code


Specification for coarse and fine aggregates from
1. IS 383
natural sources for concrete
2. IS 456 Plain and Reinforced Concrete - Code of Practice
3. IS 3764 Code of Safety for Excavation work
Handbook on Concrete Reinforcement and
4. SP 34
Detailing
5. IS 1542 Specification for sand for plaster
High Strength Deformed Steel Bars and Wires for
6. IS 1786
Concrete Reinforcement - Specification
7. IS 2212 Code of practice for brickwork
IS 1200 (Part 1 to 28 Methods of measurement of building and civil
8.
) engineering works
Glossary of terms relating to cement concrete: Part
9. IS 6461 ( Part V )
V Formwork for concrete
10. IS 800 General Construction in Steel - Code of Practice
Code of practice for application of cement and
11. IS 1661
cement-lime plaster finishes
Code of practice for painting concrete, masonry
12. IS 2395 ( Part 2 )
and plaster surfaces: Part 2 Schedule
Code of Practice for Bending and Fixing of Bars for
13. IS 2502
Concrete Reinforcement

Page 5 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

Methods of Test for Soils - Part XXIX :


14. IS 2720 (PART-29) Determination of Dry Density of Soils In-place by
the Core-cutter Method
Methods of Tests of Burnt Clay Building Bricks -
Part 1 : Determination of Compressive Strength -
15. IS 3495(PART-1to 4) Part 2 : Determination of Water Absorption - Part 3
: Determination of Efflorescence - Part 4 :
Determination of Warpage
Criteria for Earthquake Resistant Design of
16. IS 1893 (PART-1) Structures - Part 1 : General Provisions and
Buildings
Ductile detailing of reinforced concrete structures
17. IS 13920
subjected to seismic forces - Code of practice
Code of Practice for Anti-Termite Measures in
18. IS 6313 ( Part 2 ) Buildings - Part 2 : Pre-constructional Chemical
Treatment Measaures
Code of Practice for Anti-Termite Measures in
IS-2911-Part-1-
19. Buildings - Part 2 : Pre-constructional Chemical
Section-2
Treatment Measaures
Non-Destructive Integrity Testing of Piles (NDT) -
20. IS-14893
Guidelines

1.1.3 EXCAVATION:-

a. Excavation to required side slopes below ground level in all kinds of ordinary and hard
soils such as Clay, sand, sandy clay, gravel, soft murrum, hard murrum etc. for
foundations, pits, trenches etc. including de-watering, leveling, dressing, protection of
side slopes by proper shoring, strutting as necessary and transporting excess excavated
soil to stack or fill and unloading, stacking, filling, leveling and dressing to required
levels and grades etc. complete as per specifications and as directed by Engineer-in-
charge.

b. In case, if there will be any statutory Royalty charges same shall be paid by contractor
to the concerned Government authorities before commencement of excavation.
Contractor should submit the copy of same to concerned engineer before start of
works. Contractor shall be solely liable for legal and financial issues in this regard.

Page 6 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

c. The stacking of excavation material should be at least 50 mtr away from excavated
trench.

d. Excavation shall be done to the dimensions as required for safety and working facility.
Working space provided shall not be less than as provided in IS: 1200 (Part-1).
Excavation shall be carried out in slopes of 1:4 (1 horizontal : 4 vertical) or alternatively
the excavation profiles shall be widened by allowing steps of 500 mm on either side
after every 2 meters from the bottom

e. The sides of the excavated trenches shall be vertical and in straight line ready for
termite treatment.

f. The contractor at his own expenses shall water very well, ram and thoroughly
consolidate the bottom of all excavations and ground surfaces before the construction
of foundation/footing/plinth beam, filling in basement floor or other work is
commenced. The excavation shall include shoring on both the sides or trenches with
approved timber/steel accessories wherever necessary to prevent the sides from falling
including bailing or pumping out of water if found necessary. If there are any shrubs,
bushes, trees etc., are to be removed, roots of the trees should be removed for minimum
depth 5’0”. All these materials should be neatly stacked at site and to be disposed
appropriately.

g. During excavation, all safety norms should be followed as per statutory requirements
where by labours compulsorily make use of quality safety shoes, helmets, gloves verified
and approved by AEML safety officer. AEML-T being a IMS certified company insist on
strictly adhering to Quality, Environment, Health & safety (QEHS) norms. Strict action
will be taken against the contractor &action will be decided by AEML-T safety officer
in case of violation of QEHS norms

h. Bidders should adhere to MCGM Guidelines

i. The scope shall include

▪ Variation in depth of cable trench


▪ Arrangements for establishing site office
▪ Safety, security arrangements as directed by AEML including lighting arrangement
DG set during night time.
▪ Safeguarding all the underground laid services of all utilities and/or overhead along
the route.
▪ Safety & security of ongoing assets build during the progress of the scheme

1.1.4 BARRICADING:-

a. “Enhancing safety/security by providing barricading on either side of excavated trench


as per standard norms.

1.1.5 RUBBLE SOLING:-

a. Dry rubble packing of 230mm thick laid in two layers of 115mm each with bottom layer
consisting of hard broken stone of required size and top layer consisting of stone
aggregate of size 90 to 40mm blinded with sand / gravel and well compacted to 85%

Page 7 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

of original volume complete as per technical specifications and as directed by AEML


Engineer.

1.1.6 REINFORCED CONCRETE WORKS:-

a. Providing & laying PCC of M-15 below, trenches, plinth etc. including all labour, material
handling, transporting, batching, mixing, placing, leveling, compacting, curing, etc.
complete in all respects as per the drawing, specification & direction of the engineer as
per the relevant IS specifications complete in all respect.

b. PCC(M15) as per IS456 ( up to plinth) Providing, mixing, placing curing as per relevant
IS specification, reinforced controlled cement concrete with coarse sand and graded
stones aggregate of 20mm nominal size and including any admixture like plasticizer
cum water proofing cement it use as required in all kinds of work and of grades as
specified below including all labour, material, handling, transporting, batching,
compacting with mechanical vibrator and as per drawings and specification.

c. RCC(M30) as per IS456 ( up to plinth) Providing, mixing, placing curing as per relevant
IS specification, reinforced controlled cement concrete with coarse sand and graded
stones aggregate of 20mm nominal size and including any admixture like plasticizer
cum water proofing cement it use as required in all kinds of work and of grades as
specified below including all labour, material, handling, transporting, batching,
compacting with mechanical vibrator and as per drawings and specification.

1.1.7 REINFORCEMENT:-

a. Providing and fixing reinforcement for RCC work with high yield strength ribbed cold
twisted tar steel of various diameters of grade Fe 500 conforming to BIS specification
including cutting, bending, fabricating and placing in position according to drawings
and binding the reinforcement with 16 gauge galvanized annealed binding wire of
double fold or 18 gauge GI wires and providing precast cement cover blocks for main
reinforcements to ensure specified cover according to relevant IS code.

b. Bidder shall prepare and furnish to the EIC, bar bending schedules for all RCC works for
his review and approval. No work shall commence without the approval of bar bending
schedule by EIC.

c. Only TMT bars of TISCO, SAIL, RINL or equivalent shall be used.

1.1.8 FORMWORK:-

a. Providing and fixing Plywood with film face formwork (for substructure) of approved
quality for cast-in-situ, plain or reinforced concrete works of any type and section for
any depth below Finished Ground Level, including labour, materials, equipment, waste
for forms, shoring, strutting, scaffolding, staging, tying, nailing, caulking, bolting,
testing, etc. including removal of formwork and staging etc. all complete as per
specifications, drawings and instructions of the Engineer. The contractor shall supply,
fabricate, erect and dismantle (after use) all staging that is required for all activities
covered under ‘Form Work’. If it is so desired by the Engineer-in-Charge, the Contractor
shall prepare before commencement of the actual work, the scheme and submit along
with the supporting design calculations and drawings for formwork and staging and get
them approved by the Engineer-in-Charge. Bidder shall prepare and furnish to the EIC,

Page 8 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

bar bending schedules for all RCC works for his review and approval. No work shall
commence without the approval of bar bending schedule by EIC.

1.1.9 STRUCTURAL STEEL:

a. Structural steel base frame shall be constructed as per 33kV OEM drawing with given
tolerances and erected on proposed R.C.C. cable trench for mounting 33kV GIS boards
or for supporting of incoming/outgoing cables.Levels of the base frames shall be
cheked by laser device jointly with AEML engineer in charge and OEM representative.

b. Structural steel base frame shall be erected on proposed R.C.C. cable trench for
mounting 33kV GIS boards or for supporting of incoming/outgoing cables.

c. Providing, fabricating and placing steel embedded parts, angles, channels, I-beams,
inserts in concrete (including trenches etc.) including labour, material, scaffolding,
handling, welding, bolting, drilling, providing lugs, etc. complete.

d. All structural steel shall be hot dipped galvanized with 90 micron. All welding joints
shall be cold treated with Zinc rich spray.

e. GI chequered plate shall be used for packing of existing cut-outs.

f. 1200mm Stainless steel railing shall be provided around the proposed GIS plinth.

1.1.10 SOLID BLOCK MASONARY WORKS:-

a. Solid block masonry shall be carried out for construction of peripherial wall proposed
plinth in front of GIS boards.

b. Providing and constructing solid concrete block masonry in superstructure with


approved quality site made/factory made blocks having minimum crushing strength 50
Kg/Sq. cm and maximum water absorption 10%, in pre polymerized wet mix jointing
adhesive (Build Fast plus), doing masonry in specified courses, complete with raking out
joints, doing independent double legged scaffolding, complete as per specifications etc.
at all heights, depths and leads. Etc. complete. All material supply in scope of
contractor.

1.1.11 PLASTERING WORKS:-

a. Plastering shall be carried to proposed GIS plinth as per the following details.

b. INTERNAL PLASTER:- Providing and applying 12 mm thick finish cement plaster at all
heights in 1:3 (1cement and 3 fine sand) cement mortar with Recron 3s fibers of
Reliance Industries Ltd. including provision of PVC wire mesh at junction of dissimilar
materials, scaffolding, chipping, roughing up the concrete, curing & finishing smooth.
The plaster surface shall be rubbed with 'iron plate', till the surface shows cement paste
in line and level complete It shall include for scaffolding and curing etc.

c. EXTERNAL PLASTER: - Providing and applying 18 mm thick cement plaster in two layers
at all levels with under layer 12 mm thick cement plaster 1:4 (1 cement: 4 coarse sand)
and top layer 6 mm thick cement plaster 1:4 (1 cement: 4 fine sand) including

Page 9 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

scaffolding, chipping, roughening the concrete surface, curing, providing drip course
etc. all complete as directed by the Engineer-in-Charge. Sika or equivalent water
proofing admixture and Recron 3s fibers of Reliance Industries Ltd to be mixed with
each coat of plaster wherever required. PVC wire mesh to be added at junction between
RCC & brick work.

1.1.12 FLOORING:-

a. Flooring shall be carried out in 33 kV AIS board room at ground floor where existing
flooring got damaged.

b. Providing, supplying and laying 600mm x 600mm - 10mm thick non-skid fully vitrified
tiles flooring of minimum size similar to 'Kajaria, Asian, FERRASTONE' of 'BOSS
'FERRASTONE' of 'BOSS Profile Ltd',(overall 40 mm thick) laid over under bed of 1:4
cement coarse sand in pattern with different colour of tiles as per approved floor
design from the Engineer, including grouting the joints in proper line & level with white
cement and matching pigments, at all floor levels etc. complete All material supply in
scope of contractor only.

1.1.13 BRICK MASONRY:-

a. Providing, supplying and laying in position brick wall 230/345mm thick in 1 : 6 cement
and approved coarse sand mortar in foundation for all depths including supply of first
class bricks (Class-7.5) approved by the Engineer in charge, all materials , labour T & P
etc, and also including scaffolding, staging, curing, racking out joints, leaving necessary
weep holes, openings and making them good, hacking sides and bottoms of old faces
for bonding etc. including finishing smooth as directed at all levels

b. All material supply in scope of contractor.

c. Water absorption shall be as per IS 3495:1992.

1.1.14 DISMANTLING OF STRUCTURAL STEEL:-

a. Dismantling of steel structures, at all elevations including lowering to ground,


transporting the steel to fabrication yard or to Purchaser’s/ Contractor’s site stores
located within the project area as directed by the Engineer

b. After dismantling of existing structural steel, same shall be stacked as per the
instruction of engineer-in-charge.

1.1.15 DEMOLISHING OF BRICK MASONRY:-

a. Demolishing brick masonry in cement mortar including scaffolding, stacking of


serviceable material and disposal of unserviceable materials with all leads and lifts etc.
complete

b. The scope shall includes carting away debries & disposal to MCGM approved disposal
area for all leads & lift. Necessary debris management plan to be obtained by vendor at
his own cost. Necessary letter to MCGM if required shall be given by AEML. The
contractor shall opt SWM permission from MCGM & debries shall be disposed off as per

Page 10 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

the MCGM designated site.

1.1.16 DEMOLISHING OF PCC:-

a. Demolishing of the Plain Cement concrete work in foundation, bedding, grade slab etc,
and stacking out the serviceable material like rubble , etc complete with all tools ,
tackles etc as per instruction of Engineer-in charge.

b. The scope shall includes carting away debries & disposal to MCGM approved disposal
area for all leads & lift. Necessary debries management plan to be obtained by vendor
at his own cost. Necessary letter to MCGM if required shall be given by AEML. The
contractor shall opt SWM permission from MCGM & debries shall be disposed off as per
the MCGM designated site.

1.1.17 DEMOLISHING OF ASHPHALT ROAD:-

a. Demolishing of the Asphalt road portion including stacking of serviceable material and
disposal of unserviceable materials with all leads and lifts etc. complete

b. The scope shall includes carting away debries & disposal to MCGM approved disposal
area for all leads & lift. Necessary debries management plan to be obtained by vendor
at his own cost. Necessary letter to MCGM if required shall be given by AEML. The
contractor shall opt SWM permission from MCGM & debries shall be disposed off as per
the MCGM designated site.

1.1.18 PILING WORK:-

a. Mobilization towards plant, equipment and personnel for cast in situ bored piling work,
under the scope of this contract Sufficient no of hydraulic rigs/As per tender to be
mobilized for completion of entire job as per the time schedule provided in the tender
document. Contractor shall mobilize sufficient spares; cutting tools (e.g. flat teeth bits,
round shank bits, holders, etc) to avoid any stoppage of work.

b. Boring in all types of soil & installing cast-in-situ RCC vertical bored piles of specified
diameter and of specified length for working piles and test piles as per the owners
design, drawings, specification including cost of labour, materials, using ordinary
portland cement 53 grade (excluding reinforcement) with associated plants, tools &
tackles etc. all complete as per the direction of Engineer-In-charge. (Grade of concrete
M30).

c. Provision of permanent/temporary liner / bentonite slurry to arrest collapse of sides in


the bore. Permanent liner shall be provided if mandated by foundation/soil consultant.

d. Breaking of piles up to cutoff levels and removal of debris shall be covered under the
scope.

e. For socketing, Boring in gryeish basalt, weathered rock, fissured rock, soft rock, shale
etc. for socketing as directed and to the satisfaction of Engineer-in-charge.
specification including cost of labour, materials, using ordinary portland cement 53
grade (excluding reinforcement) with associated plants, tools & tackles etc. all
complete as per the direction of Engineer-In-charge. (Grade of concrete M30).

Page 11 of 12
220 KV AIS TO GIS CONVERSION AT AAREY TURNKEY TENDER DOCUMENT

f. After all the piles have been chipped to cut off level, pile integrity testing shall be
carried out on all piles and report submitted for approval.

1.1.19 MURRUM FILLING:-

Providing and Filling of good quality of murrum brought from outside and as directed by
Engineer in Charge. The material shall be free from lumps and clods, roots and vegetations,
harmful salts and chemicals, organic materials, etc. Murum filling shall be done in layers
not exceeding 250 mm in loose thickness each layer being watered, rammed and properly
compacted to achieve a dry density of not less that 90% of proctor's dry density at optimum
moisture content as per IS-2720 ( Part-VII). The work of back-filling will be accepted after
the Engineer is satisfied with the degree of compaction achieved.
The above specification is intended for the general description of quality, workmanship
etc. desired for various items of work under the contract. The specifications are not,
however, intended to cover minute details and all work shall be executed according to
the spirit of the specification and in absence thereof, according to the relevant latest
Indian Standard specification; in absence of the latter, the work shall be executed
according to the best prevailing local public works department practice or to the
recommendations of the American or British Standard specification as may be desired by
the Engineer.

All the Civil works shall be executed/tested/recorded in accordance with Field Quality
Assurance Plan (FQAP) of AEML-T.

Page 12 of 12
Technical Specifications
for
Mono Pole Structure
Doc no- TD-SP-LM-457-R0

1
TECHNICAL SPECIFICATION

FOR

MONO POLE LIGHTNING MAST

CONTENTS: -
Page No.

1.0 Codes and Standards 03


2.0 Technical Requirements for Mono Poles 04
3.0 Installation 12
4.0 Tests 12
5.0 Data and Documentation Requirements 14

2
1.0 CODES AND STANDARDS
The specified material and services shall be furnished in accordance with, but not
limited to, the relevant Indian/international standards, including all addenda, in effect
at the time of purchase order, unless otherwise stated in this specification:
In case Indian standards are not available for any of the items, relevant ASTM codes as
mentioned shall be adhered to manufacturing and installation.

ASTM – American Society for Testing and Materials (OR Equivalent Indian &
international Standards)

A 36 / 36 M Standard Specification for Structural Steel, Book 01.04


A 123. Specification for Zinc (Hot-Dip Galvanized) Coatings on iron and Steel
Products, Book 01.06, 15.08.
A 153. Specification for Zinc Coating (Hot Dip) on Iron and Steel Hardware,
Book01.06.15.08.
A 572/572M Specification for High-Strength Low Alloy Columbium Vanadium Steels of
Structural Quality.
A 780 Practice for Repair of Damaged and Uncoated Areas of Hot-Dip
Galvanized Coatings.

AWS – American Welding Society


D1.1-92 Structural Welding Code – Steel. Specification for Carbon Steel Covered
Arc-Welding Electrodes.
A5.17-89. Specification for Carbon Steel Electrodes and Fluxes for Submerged Arc-
Welding

ASCE – American Society of Civil Engineers


ASCE SEI 48-11 - Design of Steel Transmission Pole Structures.

ISO – International Standards Organization


ISO 9001 Quality System Model for Quality Assurance in Design/Development,
Manufacture and Testing.
ISO 9002 Quality System Model for Quality Assurance in Production, I installation
and Servicing.
ISO 3834-2 Quality requirement for Welding of Metallic Materials.

Indian Standards
IS 5613:1985(or latest version) - for determining the clearance diagrams for the pole.
IS 802:2015(or latest version) - for sag tension and loading calculation.
CBIP Manual.

Full scale testing


IEC 60652 – 2002

These codes and standards set forth the minimum requirements which may be
exceeded by BIDDER, if in BIDDER's judgment and with PURCHASERS acceptance,
superior or more economical designs and materials are available for successful and
continuous operation of BIDDER's equipment as required by this specification.

3
2.0 TECHNICAL REQUIREMENTS FOR POLES

2.1. DESIGN

2.1.1. Line parameters to be considered for Mono Pole Lightning Mast


(a) Voltage Level - 400/220 kV

(d) Basic wind velocity for design - As per IS 802:2015 – Wind Zone-4
- Depending on the location line.
- Reliability level Poles - As per latest Addition of IS
802:2015.
- Terrain Category - As per latest Addition of IS
802:2015.
(e) Clearances - As per IS 5613:1985.

(h) Lightning Mast -400/ 220KV Switch Yard Height @35M

(Note - Extension poles required as per the survey may be designed like +0, +1.5, +3,
+4.5. +6, etc.)

2.1.2 Deflection Limit (As per CBIP Manual)


# Ultimate load condition 5.0% of the height of pole for design consideration.
# Safety Normal condition 2.0% of the height of pole for design consideration.

2.1.3 W/T Ratio for Design


While designing the D/T Ratio and the W/T Ratio should be maintained at an adequate
level to avoid buckling under load and ovality of the individual sections (without any
additional internal supports) of the pole while storing. The allowable stress of Steel
should not get reduced more than 10% of its designated strength (ASCE/SEI 48-11,
Code for Design of Steel Transmission Pole Structures).

2.1.4 Minimum wind gust response factor for Design


Wind Gust response factor on pole structure shall be as per IS:802 Part-1, Section-1,
2015.

2.2 GENERAL

2.2.1. General Requirement

AII designs are to be made in accordance with the information provided herein and on
the accompanying outline drawings. AII outline dimensions are fixed but where no
dimensions are given, the framing, may be modified to suit the Bidder's design, subject
to compliance with all the requirements of the specification.

Manufacturer / Bidder of Mono Poles on offer should have in house Design capability &
Engineering along with Manufacturing and Galvanization plants within India which
have capability for special type of Mono Pole designs. Galvanization plant tank size
shall be declared by Bidder / Manufacturer during bidding process to ascertain the
capability for single deep galvanization capability for tubular section of Mono Poles.

4
Mono Pole Manufacturer who must design and supply Mono Poles should have at least
07 years’ experience for design and manufacturing of 220KV or above voltage class
transmission line Mono Pole structures.

Manufacturer should have type tested at least 02 types of Mono Poles lightning mast
for 220KV or above voltage class in India by CPRI or any Govt. NABL accredited
laboratory. Available Type test reports shall be submitted at the time of Bidding. Bidder
/Manufacturer shall submit minimum 2 work completion certificates and performance
certificates issued by Private/Central/State utility for satisfactory operation of installed
Mono Poles lightning mast for 3 years or more period of 220KV or higher voltage class
level. Bidder shall submit eligible Manufacturer authorization for Design, Supply &
Manufacturing of Transmission Line Mono Poles lightning mast along with bid
documents.

The steel poles design shall be the responsibility of the pole manufacturer. It shall be
designed & manufactured for the configuration, loadings and limitations provided
elsewhere in the tender documents. The Manufacturer / Bidder, at purchaser's request,
shall explain and provide all the necessary information pertaining to the design of any
or all elements of the structure.

Structures shall be designed so that member unit stress does not exceed the yield
point stress of the material. The ratio of major axis of tubular diameter to wall
thickness shall be such that local buckling does not govern member design. Structure
deflection under maximum load condition including overload factors shall be no more
than 5 % of the structure height. Cross section of the pole shall be 12 sided polygons
and shall be tapered from top to the base.

Cross arm member, if required in the Bid Drawings shall be of polygonal cross section
with taper and shall conform to purchaser's general arrangement drawings. The
strength of the attachment of cross arms to the columns shall be enough to develop
the full capability of the cross arm.

Members requiring more than one length of tubular section shall be constructed by
telescoping the sections together with enough overlap to develop the full strength of
the member. Minimum overlap shall be 1.5 times the maximum inside diameter of outer
section at the telescopic joint or as per design calculations, whichever is higher.

Rigging accessories, insulator attachment plates, ladder, lugs for bolted steps and
lighting brackets, and hand line attachment shall be welded to the structure.

2.2.2. Structural Analysis


Elastic methods of analysis shall be used. Stability shall be provided for the structure
as a whole and for each structural element. The load effects resulting from the
deflected shape of the structure and individual elements shall be considered during
design.

The analysis shall include all structural members (including inter pole ties, bracings and
guys, if required) in their actual, manufactured geometry and sizes.

When values for the following are specified in the tender documents, the analysis shall
include differences in support elevation, support movement and erection tolerances.
5
The structural design of the pole shall be done using proper internationally accepted
design software.

2.2.3. Clearance
Poles shall maintain the minimum clearances between conductors and steel structures
as per the standards/codes/rules.

2.2.4. Design Loads


The steel pole shall be designed to withstand the loading conditions and loading input
data provided by the PURCHASER in the tender. These loads are to be factored in while
preparing the loading trees.

The specified/calculated wind load on the steel pole shall be applied on projected steel
area of the pole. The wind load shall be applied throughout the exposed length of steel
pole. The BIDDER shall indicate on the design drawings the magnitude and the location
of the wind forces assumed in the design.

2.2.5. Allowable Stresses


The allowable stresses for tubular members, guys (if applicable) and connection bolts
shall comply with the requirements of ASCE SEI 48-11, Design of Steel Transmission
Pole Structures.

2.3 MATERIALS

2.3.1. General
AII materials shall comply with the requirements of an ASTM specification unless
otherwise specified. Material to be welded shall comply with the requirements of
ANSI/AWS D1.1.

2.3.2. Structural Plates


Plate and "product of a coil" that is used to produce load carrying components shall be
considered structural plate. Material used for grounding plates, identification plates,
pole caps, disposable cage plates and similar components does not need to be
classified as structural plates.

Structural plate less than or equal to 31.75 mm (1.25 in.) in thickness shall conform to
ASTM A36, ASTM A572, ASTM A 633 or ASTM A871.

Yield strength of Plates used for manufacturing the shafts & cross arms shall be
confirming to Gr 65 of ASTM A572 or equivalent grades. Yield strength of Plates used
for manufacturing the Base Plates shall
be confirming to Gr 50 of ASTM A572 or equivalent grades. The silicon content of
plates used for the pole shaft shall be limited to less than 0.06 % to have a better
quality of Galvanizing.

MATERIAL SPECIFICATIONS for Shaft & Base Plate


a. Pole Shaft ASTM A572-65 or Equivalent.
b. Arm & Arm Bracket ASTM A572-65 or Equivalent.
c. Base Plate ASTM A572-50 or Equivalent.

2.3.3. Bolts and Nuts


6
Material for anchor bolts shall conform to grade 6.8 or 8.8 as per the requirement.
Exposed portion of the Anchor bolts shall be galvanized in accordance with ASTM A
153.

Material for headed bolts shall be of grade 6.8 or 8.8 and shall be galvanized in
accordance with ASTM A 153. When inch size bolts are used, they shall conform to
ASTM A307, ASTM A325, ASTM A490 or ASTM A449 when bolt diameter exceeds 38.1
mm (1.5 in.) Threaded rod shall be of grade 6.8 or 8.8. When inch size threaded rods
are used, they shall conform to ASTM A36, ASTM A354, ASTM A449, ASTM A588 or
ASTM A687.

2.3.4. Weld Material


The material used for making welds shall be compatible with the parent material, as
defined by ANSI/AWS D1.1-92 and shall meet the impact requirements specified in
3.2.4 for the lowest toughness requirements of the plates being joined.

2.4 DETAILING OF DESIGN

2.4.1. Typical Details


Telescoping splices joining sections (slip joints) shall be designed to assure a minimum
overlap of 1.5 times the largest inside diameter of the outer section. Anchor bolts for
the pole shall be provided with top and bottom templates to form a cage at job site.
This is to get a proper alignment of bolts during casting of foundation.

2.4.2. Circumferential welds


Shaft-to-shaft, pole shaft-to-base plate, and pole shaft-to-flange shall be full
penetration welds.
Arm shaft-to-arm bracket shall be partial penetration groove weld with fillet overlay,
sized to develop the full strength of the shaft. Other accessories (Lugs and plates for
grounding, jacking, climbing and identification) shall be fillet and/or groove welds sized
to develop the loading requirements of the attachment.

2.4.3. Longitudinal Welds


Longitudinal welds in outer section of slip joints and within 76.2 mm (3") of a full
penetration weld shall be full penetration. Longitudinal welds shall be a minimum of
60% penetration in other locations.

2.4.4. Plate Bends


The minimum inside radius of plate bends shall be such that cracking does not occur.
Care must be taken to prevent the steel from cracking especially at the free ends of
the bend either during the bending operation or subsequently due to residual stresses.

2.5 FABRICATION

2.5.1. General

The Pole manufacturer shall prepare a detailed drawing of the pole and submit it to
PURCHASER for approval. Fabrication shall be performed in strict compliance with
7
PURCHASER's approved detail drawings. Material substitution or deviations from the
final approved drawings shall not be made without written approval from PURCHASER.
The manufacturer shall accurately identify all material to assure proper usage.

2.5.2. Pole Shaft& Base Plate.


The pole shaft shall present the most pleasing appearance possible consistent with the
strength requirements in the specification and drawings. Pole shall be continuously
tapered from top to bottom with a uniform slope. No multi-ply steel plates will be
allowed. For the pole structure fabrication shaft shall be made with number of sections
specified in the Standard Drawings.

The cross section of the pole shall be as specified in the Standard Drawings with all
sides equal.

Minimum requirement for Base Plate -


1) Edge Distance: minimum 1.5 times of the bolt diameter.
2) Bolt to Bolt Spacing: minimum 2.5 times of the bolt diameter.
3) Shaft to Bolt spacing: minimum 3 times of the bolt diameter.
4) Base Plate should be welded to the Pole Base Section with a T-joint along with a
Back-up Ring.

2.5.3. Pole Slip Joint


Pole section shall be made with telescopic slip joints for easy assembly either in air or
on the ground at the construction site. Overlapping shall not be less than 1.5 times the
maximum inside diameter of outer section at the telescopic joint or as per design
calculations, whichever is higher. Manufacturer to clearly mark “Minimum” &
“Designed” slip positions on the pole sections in RED Paint.

At site, slip joints shall be done using proper devises of suitable capacity only to ensure
proper joining of the sections.

The taper of each section at a slip joint should match the taper of the adjacent section
to provide proper splice tolerances. No circumferential weld within a shaft section shall
be permitted. Other type of connection will not be permitted.

2.5.4. Plat Form


Plat form arrangement shall be furnished with hoisting lugs to facilitate construction
and maintenance.

2.5.5. Other pole attachments


Any additional arrangements necessary for installation of Cable etc. shall be included
in design by manufacturer if require.

2.5.6.1. Step Bolts or Climbing Device


Each pole shall be provided with the required set of Step Bolts & Ladders (Ladder
Material: ASTM A572-36 or Equivalent) where maintenance personnel can climb on the
pole face. The step bolts shall be approximately 2.5m above ground level for 2m and
from there on to the ground wire peak.

Step bolts shall have suitable proven connection to the pole considering the safety of
the maintenance personal.

8
The step bolts shall be not less than 16 mm dia, symmetrical head, spaced not more
than 45 cm apart. The bolts or ladder rungs shall withstand without permanent
deformation, a vertical load of at least 137 Kgs. applied at the bolt head and at the
Centre of the ladder rung.

2.5.6.2. Grounding Provision.


Grounding clamps or nuts shall be provided near the top and base of each pole. The
wire lug shall be welded to the exterior of tubular column sections near the top and the
base for grounding, in addition to any other ground wire requirements shown on
PURCHASERS's general arrangement drawing.

2.6 MATERIAL PREPARATION.


Edges shall be in accordance with ANSI/AWS D1.1. Burrs or sharp notches that may be
detrimental to the structure or that pose a safety hazard shall be removed. Re-entry
cuts shall be rounded. Care shall be taken to prevent separation of the outer surface
and reduction of the cross-sectional properties below those required by design. If
separation occurs during bending, it shall be repaired in accordance with ANSI/ AWS
D1.1. MiII scale shall not be considered as the surface.

When hot bending is required, heating shall be done evenly over the entire bend area
and shall be of enough temperature to minimize separation and necking down of the
cross section. The temperature used in hot bending shall be such that the physical
properties of the steel are not diminished.

2.7 WELDING.
Unless otherwise specified herein, or note on purchaser drawings, welding shall
conform to the AISC Specification and weld procedure qualifications shall be in
accordance with AWS D1.1, Section 5 "Qualifications". A written welding procedure
specification as shown in Appendix E of AWS D1.1 (FormsE-1, E-2 orE-3 as applicable)
shall be prepared for each procedure and submitted for review and acceptance by
PURCHASERS when requested. Weld details on BIDDER's shop detail drawings shall
include identification of weld and method to be used for making the weld in
accordance with AWS D1.1, Section 2,"Design of Welded Connections", and Section 4,
Technique.

Preheat and inter pass temperature of AWS D1.1 shall be followed. Welding shall be
done by the shield metal-arc, gas shielded flux core, gas shield metal arc or submerged-
arc processes. Welding

electrodes shall be AWS A5.1, low hydrogen classification E70XX-EXXX, for submerged
arc welding, unless noted otherwise on purchaser’s design drawings. Where steel other
than ASTM is specified electrode selection will be subject to acceptance by purchaser.

The storage of welding consumables (welding wire, electrodes, fluxes and gases) shall
be in accordance with AWS D1.1 and the welding consumables manufacturer's
recommendations.

Care shall be taken in assembling and fitting and welding shall be controlled to
minimize shrinkage stresses and distortion. AII finished work shall be of good quality
and have a neat appearance without
war page. Caution shall be exercised to obtain full penetration welds where specified
9
on purchaser’s design drawings.

When inspection of a weld zone is called for on purchaser’s design drawings,


procedures shall be in accordance with non-destructive testing procedures of AWS
D1.1 and the following additional requirements:

Circumferential and longitudinal welds within the slip joint area of tubular sections
shall be shear wave ultrasonically inspected in accordance with AWSD1.1. Longitudinal
welds in tubular sections, where visual inspection is not adequate, shall be magnetic
particle or dye penetrate tested.

Attachment welds shall be examined by visual inspection. Magnetic particle or dye


penetrate testing in accordance with AWS D1.1 shall be used at questionable area by
visual inspection.

BIDDER shall furnish a shop test report indicating complete test results of all non-
destructive testing and inspection conducted.

Welding of pole sections shall be done using a SAW type welding and pole closing
machine. The pole closing machine shall have the required dimensions so that pole
sections shall move through it during the welding process. The machine shall have the
required jigs from all directions to hold pole section intact while welding to get proper
shape and welding quality.

Open arm type welding machines without automatic jigs for holding the pole during
welding shall not be used for welding of pole sections as they will not provide the
required strength and shape. Welding being the key process of the pole manufacturing,
the manufacturer should have ISO 3834-2 certification of quality requirement for
Welding of Metallic Materials.

2.8 SURFACE PREPARATION AND COATING

2.8.1 Galvanizing

All structural steel shall be hot dip galvanized after fabrication in accordance with
ASTM A 123. Surface preparation by means of seven tank process shall be during
galvanizing. Exposed welds shall be mechanically cleaned.

Fabrication and preparation of material for galvanizing shall conform to the


requirements of ASTM A143. When specified in the drawings or specification,
embrittlement test of designated galvanized material shall be performed in accordance
with ASTM A 143.

All fabrication work on pole sections (including welding of base section with base
plate) shall be completed in all respects before hot dip galvanizing. No cutting,
grinding, welding, fabrication, etc. shall be allowed on any of the pole sections after
hot dipped galvanizing.

Galvanizing shall be done with single dipping method. Cold galvanizing methods shall
not be applied on any of the pole sections while manufacturing / galvanizing. The pole
10
manufacturer must submit a declaration of suitability of its own galvanizing facility for
the work, where the poles are to be galvanized.
Lead content in the zinc solution should not be more than 0.001%. The bidder is
required to indicate the size of galvanizing baths in Pre-qualification form as well as
proof of ownership and test certificate
from Govt. Accredited agency as proof of low lead zinc bath.

Bolts, nuts and washers shall be galvanized in accordance with ASTM A 153.Bolts and
nuts shall be assembled after galvanizing and shall fit with finger pressure only and
nuts shall be interchangeable on any bolts without shake. Wrench tightness or
spinning fit shall be caused for rejection.

Only the exposed threaded portion shall be galvanized in case of foundation Anchor
bolts. Repair of damaged hot dip galvanized surfaces during shipping or handling shall
be in accordance with ASTM A780.

Heavy runs or lumps of excess zinc will not be acceptable in any area where they will
interfere with bolt hole alignment (such as the "drip end" of punched angle braces,
etc.), with matching flat surfaces which are to be bolted together, or are of such size
and location that normal handling or erection may cause them to be dislodged. Sharp,
pointed, "stickers" of zinc which could cause injuries in handling shall be removed.

Straightening of steel after galvanizing shall be accomplished without the use of heat.
Steel so straightened shall be inspected to assure no deformation or cracking of
galvanizing layer.

AII materials shall be cleaned or washed after galvanizing to remove traces of flux, flux
inclusions, preflux slats, acid ash, dross or other extraneous materials. The presence of
wet storage stain (White Rust) shall be caused for rejection.

2.9 PREPARATION FOR SHIPPING AND STORAGE


Each shipment shall include a detailed packing list identifying all items by part number,
including hardware. Special care shall be exercised in the handling, packaging and
shipping of the materials to prevent denting, bending, or any other damage of the
sections, cross arms and anchor bolt cages. Suitable cushioning, protective padding,
dun age or non-metallic spacers shall be used to prevent vangs and flanges welded to
the tubular sections from damaging other tubular parts and to prevent damage and
shifting during transit.

Small parts and fasteners shall be carefully boxed, crated, bagged or otherwise
containerized and protected for shipment. Small pieces shall be bundled, with all the
pieces in any bundle having the same mark. AII small pieces such as bolts, ground wire
and insulator connections shall be packed in boxes. Bolts of different size or length
shall be wrapped in separate sacks before boxing. Description, quantity and marks or
description of contents shall be shown on the outside.

Shipping shall be as specified in the Purchase Order and shall be in complete structure
lots. AII identifications shown on bundles, boxes or other containers shall be included
on BIDDER's shipping

and packaging lists. All Materials shall be arranged to allow safe unloading at site.
Shop painted or galvanized steel will be stored in the field pending erection. BIDDER
11
shall provide storage and handling instructions to minimize damage to painted or
galvanized surfaces.

2.10 MARKING
AII parts of poles shall be appropriately marked or numbered. AII markings shall be
indelible and clearly visible after galvanizing. Each pole shaft shall have a welded
identification tag at 1.5m above ground level, which includes customer name, structure
type, manufacturer name, year and month of fabrication.

Each pole shaft section, cross arm and other separate pieces of structure shall have a
welded identification tag marked with part number and serial number. All letters and
numbers on identification tags shall have a minimum height of 15mmand be legible
after galvanizing.

3.0 INSTALLATION
Experienced engineers of the pole manufacturer shall be available at site while
conducting assembly & installation of poles. Pole manufacturer shall submit the
installation procedure to the purchaser before starting the installation work.

Assembly of pole sections at site shall be conducted using hydraulic jacking devices
and/or suitable chain pulley blocks to achieve proper jacking force.

4.0 TESTS

4.1 GENERAL.
AII materials shall comply with test criteria, and purchaser's acceptance of the steel
poles and its components shall not relieve the BIDDER of his responsibility for meeting
all the requirements of this specification.

The steel poles and its components shall be given the manufacturer's routine shop
tests and quality conformance tests. When specified, these tests shall be witnessed by
purchaser or its representative. Tests results shall be submitted to purchaser. No steel
poles shall be shipped until released for shipment by purchaser.

4.2 MATERIAL.
Manufacturer / Bidder shall furnish four (4) copies of certified mill test reports
covering chemical and mechanical properties of the structural steel. Stock material
may be used with purchaser's concurrence where stock can be satisfactorily identified
with the specified ASTM specification. Bidder shall furnish all shop test reports for
purchaser's review and records.

4.3 QUALITY CONFORMANCE INSPECTION.


This is intended to eliminate defective materials and components of the steel poles.
Each component shall be inspected for conformance to the approved drawings. This
inspection shall include, but not limited to:

a) Ultrasonic inspection of base plate more than 50mm thick prior to welding for
laminations.
b) Visual inspection of dimensions to assure that tolerances are met.
c) Visual inspection of cut edges to ANSI/AWS D.1.1 criteria.
d) Visual inspection of bent surfaces for surface separations (supplemented by
magnetic particle in questionable areas)
12
e) visual inspection of bolt holes to assure that they are cylindrical, perpendicular,
free of burrs and without torn or ragged edges.
f) visual inspection of all welds to ANSIIAWS D1.1 Section 8 criteria.
g) ultrasonic inspection of all full penetration welds.
h) ultrasonic inspection of shaft to base plate weld after galvanizing for base plate
thicker than 50mm (maybe waived if routine audits show no history of defects).
i) visual inspection of all structural partial penetration or fillet welds, in
questionable area use magnetic particle inspection according to ANSI/AWS D1.1
Section 8 criteria.
j) visual inspection of finish Pole.
k) Magnetic thickness measurement of finish coatings.

There will be process inspection by the purchaser at manufacturer’s plant during key
process like, steel sheet bending, seam welding of sections, base plate welding &
galvanizing process as and when necessary. All galvanization to be done only after
inspection of the completed poles in black condition. Further pre-manufacturing
inspection & testing (Mechanical & Chemical) of Steel Sheets will be carried out as &
when necessary to ensure the quality of the steel to be used.

4.4 FULL SCALE TESTS


If required by purchaser, the Bidder / pole manufacturer shall have capability to
facilitate for conducting type testing of the poles to ensure the satisfactory design and
manufacture of steel poles and its components in accordance with the applicable
standards mentioned herein in the specification. This shall be on chargeable basis.

If the poles are being manufactured by using established internationally accepted


software, all type of pole types need not be tested in full scale conditions. While
selecting the sample for testing, pole type having maximum quantity shall be selected
for testing.

Testing of poles shall be conducted in black conditions. Tested poles shall be fully hot
dip galvanized in single dipping method before being supplied to the site.

Full scale testing shall be conducted at either CPRI or any Govt. Laboratory/Test Center
or independent NABL accredited Laboratory/Test Centre. BIDDER's / manufacturer's in-
house test center shall not be used for testing of poles. Selected test center must have
previous experience of testing power transmission steel tubular/polygonal poles.
The pole shall be erected on a rigid foundation and the vertical axis through the center
of gravity shall not be out of plumb by more than two tenths percent (0.2%) of the
height at any level.

The pole structure shall sustain the load including overloads. These loads shall be
applied in increments and shall be held constant for a period of five (5) minutes before
increasing or removing the loads.

The BIDDER shall submit for purchaser's approval his proposed method and facilities of
applying and measuring the loads on the structure. The load measuring devices with
appropriate numbering shall be suitably calibrated prior to and following the test in
accordance with the manufacturer's
recommendation at the presence of purchaser's Structural Design Engineer /
Representative(s).
13
Structure deflections under load shall be measured by suitable procedure at points
designated. Deflection readings shall be recorded for the "before- load" and "Load-off"
conditions.

The Bidder / Manufacturer shall submit, fifteen (15) days prior to the performance of
the tests, his testing programs to purchaser for review and approval. These shall
include test procedures, diagrams or test arrangements showing the points of location
and magnitude of the loads to be applied, the designated points for deflection
measurements, etc.

The pole to be tested shall be inspected in the presence of purchaser's Structural


Design Engineer who shall conduct a visual check and evaluate all parts of the
structure for sign of failure following the completion of each test.

After completion of test, the test structure can be considered failure if the structure
experienced any of the following:

a) After the loads have been removed, the pole structure does not return to its
original position within reasonable tolerance.
b) Failure (i.e. bending, yielding, breaking, etc.) of the material or weld is detected;
and
c) Test structure does not pass all physical and dimensional checks as required in
the test specified in this specification.

Such a failure shall be corrected and tested at the Bidder’s expense. In case of no
failure, tested poles can be used for installation in the line.

4.4.1 TEST REPORTS


The BIDDER shall furnish one (1) copy of a test report in English Language and that
shall include,

a) The designation and description of the pole tested.


b) The name of "PURCHASER".
c) The name of the person or organization (responsible engineer) that specified
the loading, electrical clearances, technical requirements and general
arrangement of the prototype;
d) The name of the Engineer from PURCHASER who attended the test.
e) The name of the Manufacturer.
f) A brief description and the location of the test facilities.
g) The names and affiliations of the test witnesses.
h) The dates of each test load case.
i) Design and detail drawings of the pole, including any changes made during the
testing program.
j) A rigging diagram with details of the points of attachment to the pole.
k) Calibration records of the load-measuring devices.
l) A loading diagram for each load case tested.
m) A tabulation of deflections for each load case tested.
n) In case of failure; Photographs of failure: Loads at the time of failure; a brief
description of the
o) failure; The remedial action taken; The dimension of the failed members; and
Test coupon reports of failed members.
14
p) Photographs of the overall testing arrangement and rigging.
q) Air temperature, wind speed and direction, any precipitation and any other
pertinent meteorological data.
r) MiII test reports of poles used in the test report.
s) Test result of the test coupons taken following the completion of test.

6.0 DATA AND DOCUMENTATION REQUIREMENTS

5.1. GENERAL
Bidder shall furnish data and information on predicted performance, interface
requirements and construction features of all steel poles supplied by the bidder. The
accuracy of such information and its compatibility with overall performance
requirements specified by purchaser are the sole responsibility of the BIDDER.

AII information submitted as part of the Proposal Data will become part of contract
data for successful bidder. Any deviation from such data requires purchaser's approval
for such a deviation to be acceptable to purchaser.

5.2 DATA TO BE SUBMITTED ALONG WITH THE PROPOSAL

a) Description and outline drawings of proposed poles including configuration,


material detail, shapes, sizes and representative connection details.
b) Description of design calculations to be performed and buckling criteria to be
used.
c) Reference list of previous experience of the pole manufacturer and the BIDDER.
d) Proof of experience of the BIDDER as specified in clause no.2.2.1
e) Proof of previous experience of the pole manufacturer for manufacturing of
poles as specified in clause no.2.2.1
f) Certified sample mill test reports
g) Proposed time bar schedule to meet delivery, installation/erection date(s)of the
steel poles and its components.
h) Copy of ISO 9001 Certification of the pole manufacturer.
i) Tentative Quality Control procedures and qualifications, and nondestructive
testing to be performed.
j) Detailed list of all assumptions / exceptions and/or deviations taken by the
Bidder to the requirements of this specification or, if none are taken, a
statement indicating that no exceptions or deviations are taken by the Bidder.
k) Details of equipments available with the manufacturer for making these poles.
l) Dimensions of the hot dip galvanizing facility of the manufacturer shall also be
provided to ensure their capacity. This will be major qualifying criteria.

5.3. DATA TO BE SUBMITTED AFTER AWARD OF CONTRACT

a) Sag tension calculations, clearance diagrams and loading trees.


b) List of Drawings and schedules of submittals.
c) List of Codes used.

d) The final design calculations of all types of pole’s showing design assumptions,
analysis, joint fixity, foundation fixity, eccentricities induced to structure
deflections and assumptions and computations used to determine radius of
gyration and other critical sections.
e) Maximum moments, shears, axial loads and member section modules required
15
and furnished for at least every 20-foot (6.09 m) length, and at ground level,
joints, splices and other critical sections.
f) Detailed assembly and fabrication drawings.
g) Bill of materials and parts list for each type of poles.
h) Dimensions of each section and components of each type of poles including Bill
of materials.
i) Test reports.
j) Calculations of stresses in the ground line, attachment connections, and
moment connections.
k) Maximum horizontal and vertical deflection at top of pole, at shield wire and
conductor attachments, and at cross arm joints.
l) Detailed QA Program based on ISO 9001;
m) Detailed Contract Schedule Activity for the steel poles.
n) As-built shop/erection drawings as finally approved.

Erection drawings shall show only one (1) pole each with its component parts and shall
have an identification mark. The number and length of bolts, with spring type of
washer, nuts and locknut required for the assembly shall be shown at each connection.

A complete list of material listing quantities of all material required for the structure or
part structure shown, including bolts, nuts, locknuts, washers shall be shown on
BIDDER's detail drawings. The bill of material shall include the quantity of pieces
required, mark number, description, size, length, weight and total weight of material
shown on the drawing, and the reference drawing on which the member is detailed.

Detail drawings shall show each individual member's dimensions and tolerances,
welding requirements, connections, identification mark, quantities, material
designation, surface treatment, and a bill of material. BIDDER shall furnish in the
manner, number of copies and within the time set forth in the Contract.

16

You might also like