1 General
ZFW20-145 ( L ) /T3150-40 gas insulated metal-enclosed switchgear ( ZFW20-145 gas insulated metal-
enclosed switchgear or GIS for short )is a kind of high voltage switch equipment that three-phase in common
case designed and developed by New northeast electric(Shenyang)high voltage switch Co.LTD
The product can be included : the basic components such as bus,disconnecting switch,earthing switch,circuit
breaker,expansion joints,voltage transformer,current transformer,lead-out bushing,Zinc oxide lightning
arrester,control cabinet as required.
ZFW20-145 gas insulated metal-enclosed switchgear is the important transmission and transformation
equipmen of the areas such as electric network transformation、steel, chemicals, mining.It has specialties such
as cover a small area,low noise,no fire risk,long maintenance cycle,safe and reliable running and suitable indoor
and outdoor.
According to the different needs of users, it could be in a variety of ways of single bus ,double bus.
2 Operating ambient condition1)
a)Ambient air temperature:-30℃~+40℃;
b) Air humidity : relative humidity :daily average should be no greater than 95% ; Monthly average
should be no greater than 90%;
Saturated vapor pressure:daily average should be no greater than 2.2 kPa;Monthly average should be
no greater than 1.8 kPa;
c)Elevation should be no greater than 1000m;
d)Pollution level Ⅲ;
e)Wind speed should be no greater than 34m/s(corresponding to 700Pa on the cylindrical surface);
f)Ice level 10;
g)Seismic fortification intensity 9,horizontal acceleration 0.3 g (sine resonance wave);
PS:1)Special order could be suitable for special ambient condition
3 Technical indicators
3.1 Technical parameters
3.1.1 Technical parameters of ZFW20-145 gas insulated metal-enclosed switchgear
Main technical parameters are shown in table 1 to table 3
Table1 Rated parameters
Items Parameters
Depict Rated voltage kV 145
Rated frequency Hz 50
Rated current A 3150
Check
Rated short time withstand current kA 40
Rated duration of short-circuit s 4
Used basemap No
Rated peak withstand current kA 100
Basemap No.
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:2
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:3
Table 3 (to continue )
Items Parameters
Main loop to the earth greater than MΩ 2000
Resistance of
Auxiliary circuit and control circuit to the earth
insulationa)
greater than MΩ 2
a) Insulation resistance of main loop o the earth is measured with 2500 V shaking table;
Insulation resistance of auxiliary circuit and control circuit to the earth measured with 500 V shaking table
Circuit breaker with spring operating mechanism, technical parameters are shown as table 4 to table 5
Table 4 Main parameters of circuit breaker
Items Parameters
Rated short circuit breaking current kA 40
Rated short circuit making current (peak value) kA 100
Short-line fault breaking current kA 30,36
Rated line-charging breaking current A 50
Rated out-of-phase breaking current kA 10
Rated short time withstand current kA 40
Rated duration of short-circuit s 4
Rated peak withstand current kA 100
Rated operating sequence O-0.3s-CO-180s-CO
Mechanical life (operating cycles) times 6000
Distance of travel of contactor of circuit mm
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:4
Table 5 (to continue )
Items Parameters
Rated voltage V 220
Heater(AC)
Rated power W 50(ordinary)
Disconnecting switch and earthing switch of ZFW20-145 GIS include three modules:
b) 3 station switch composed by disconnecting switch and earthing switch (DS/ES), it composes the
function of disconnecting switch ( DS ) and earthing switch ( ES ) , with motor operating
mechanism of 3 stations;
c) Fast earthing switch ( FES ) with short-circuit making capacity , with motor spring operating
mechanism of 2 stations;
Main technical parameters of disconnecting switch and earthing switch are shown in table 6 to table 8
Table 6 Main technical parameters of disconnecting switch and earthing switch
Items Parameters
Rated bus switching current A 1600
Rated bus switching voltage V 30
Opening time s ≤1
closing time s ≤1.8
Biggest difference of contact time when opening ms ≤100
Biggest difference of contact time when closing ms ≤100
Mechanical life (open-close operating cycles) times 6000
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:5
Table 8 Main technical parameters of operating mechanism
Items Parameters
Rated voltage of motor spring operating mechanism(FES) V DC 220/110
Rated
V voltage of motor operating mechanism(DS,DS/ES) V DC 220/110
Voltage V AC 220
Parameters of heaters in 50(ordinary)+200(temperature
Control cubicles
control cubicles and and humidity control)
Power W
mechanism cases Mechanism cases with
15
DS,DS/ES and FES
The maximum power of 60(within 10% of the total number of required revolutions,120N is allowed)
manual operation N
Depict
Check
Used basemap No
Figure 1 casing interval
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:6
Depict
Check
Used basemap No
Basemap No.
Sign
Figure 4 protection and measurement inverval
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:7
Depict
Check
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:8
Operating principle of spring operation mechanism is shown as the included 《 Installments and operating
instructions of spring operation 》
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:9
4.3.1 Three station switch(DS/ES) combined by disconnecting switch and earthing switch
and its operating mechanism
a) Three station switch(DS/ES) combined by disconnecting switch and earthing switch
The strcture of three station switch (DS/ES) combined by disconnecting switch and earthing switch is
shown as figure 9.It combines the function of disconnecting switch(DS) and earthing switch(ES),they
share a same moving contact (2),with three stations mechanism,could be operated by electric and manul.
Figure 9 Three station switch(DS/ES) combined by disconnecting switch and earthing switch
The driving force of output shaft of three stations mechanism(5)transmits to insulating rod(4), through
the transmission system drives the moving contact (2) act .
Depict
Check
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:10
After the moving contact(2) contacts with the static contact of earthing switch(3) fully,makes the earthing
switch closing,shown as figure 10 ( c ) .At the moment , if the moving contact(2) moves reversely, it
makes earthing switch to do opening operation to be opening,moving contact(2) is in the middle position,
shown as figure 10(b).
When disconnecting switch(DS) of three station switch(DS/ES)is opening only, earthting switch(ES) of
three station switch(DS/ES)can do closing or opening operation.The same, when earthting switch(ES) of
three station switch ( DS/ES ) is opening only, disconnecting switch(DS)of three station
switch(DS/ES)can do closing or opening operation.
b) Operation mechanism
The appearance of motor operating mechanism for three stations switch is shown as figure 11.There are two
motors drive the mechanism,each for disconnecting switch and earthing switch,Transmits driving force of
motor through transmission components such as toothed wheel to the common output shaft to realize the
three station operation of switch.
The mechanism has interlock function, when DS is opening only, ES can operate. The same, when ES is
opening only, DS can do closing or opening operation.
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:11
Depict
Check
Used basemap No
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:12
Depict The appearance of motor operating mechanism for three stations switch is shown as figure 14.There is a
motors drive the mechanism,transmits driving force of motor through transmission components such as
toothed wheel to the output shaft to realize the opening and closing operation of switch.
Check
Used basemap No
Basemap No.
Sign
Remove the cover plate of lock device of mechanism,as shown as figure 4.15,turn wrench of lock
device of DS(3)to“manul”,then insert hand crank to rabbet of hand crank of DS(2),shake it according
to the direction indicated on the plate to closing or opening operation of DS.
Turn wrench of lock device of DS(3) to the position of lock or unlock,then pull out lock latch of DS(1),
The functions of DS when wrench of lock device(3) are in the position manul,unlock and lock are as the
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:13
4.3.3 Fast earthing switch
Fast earthing switch(FES)with electric spring operation mechanism, fast earthing switch and electric spring
operation mechanism is a whole module unit. Fast earthing switch can do closing and opening operation,the
structure of FES is shown as figure 16.FES does opening operation,at the same time ,the closing spring stores
energy,when the closing spring release,achieves rapid closing.
Depict
Check
Figure 17 Lock device of fast earthing switch
Operating mechanism of fast earthing switch also has locking functiong,shown as figure 17.open the
Used basemap No protective cover of mechanism,remove the protective piece(2), pull out the wrench of lock device(3),
turn it to the position of manul,then insert hand crank into rabbet of hand crank(4), shake it according to the
direction indicated on the plate to closing or opening operation of FES.
Basemap No. Turn wrench of lock device(3)to the position of lock or unlock,then pull out lock latch, lock FES in the
position of lock or unlock with padlock.
The functions of DS when wrench of lock device(3) are in the position manul,unlock and lock are as the
Sign same as three stations operating mechanism.
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:14
Depict
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:15
Depict
Check
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:16
Depict
Check
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:17
c) Before installation, should remove the dust and water which stored during transport and storage on the
surface of all GIS components;
d) In the transport process, the basin insulator plus shield to prevent the basin insulator be affected with
damp and broken.So should not remove the shield before installation.
6.3 Installation of GIS
Installation of GIS should be based on the bus step by step.
a) If the number of intervals is large,the interval in the middle position may be the first installation
interval ; If the number of intervals is small,the interval on one side may be the first installation
interval。After installation of the first interval ,should adjust the level carefully ,at the same time,
should also make center line of interval and the based center line of the interval no difference as
possible,put away the gas of bus after that, remove the cap on both ends ,clean up the sealing surface
and sealing ring.
b) When installing the second interval ,clean up the sealing surface and install sealing ring too ,adjust
levelness well,make the flange is of alignment to the flange of the first interval.Also the third and the
fourth interval.
c) If it is with expansion joints,sealing surface should be according to the above method.Because of
reasons of transportation or limit of hoisting equipment,the sealing surface of the parts must be
disassembled need to be cleaned up and install sealing ring.
d) For connecting of the flange of GIS tank with the basin insulator,avoid bolting is tightened excessively
or insufficiently.For the basin insulator installed , When tighten bolts,should be followed
up,down,left,right then tighten center in order. When tighten two or more bolts, bolts should not be
tightened once, should repeatedly tightened. In reference torque and fastening order of bolts may refer to
table 9 and figure 21.
e) When install or remove the bolts in the tank , must be very careful.When tighten and loosen the
bolts,there may be metal sundries,these sundries is very dangerous in the tank,so after completion of the
work,use vacuum cleaner to clean up carefully,ues “glabrous paper”wipe again.
Force moment
Thread specificati Steel or stainless steel threads Copper, brass or aluminum alloy threads
on
M8 14 12 10 9.5 8 6.5
M12 55 45 35 36 30 24
M16 115 95 75 70 60 50
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:18
Depict
Figure 22 Installation of adjust expansion joints
6.4.2 Installation of the bushing
Check When there are installations of out-line and in-line bushing,porcelain casing should be installed after the
completion of installation of the other parts.Must be careful to prevent scratching porcelain bushing when
lifting porcelain bushing.During installation , install inside shielding cover firstly,ensur reliable contact of
Used basemap No
contact joint.The upper and lower sealing surface of porcelain bushing should be handled well.
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:19
6.4.3 Installation of cable terminals,SF6 gas-oil separation bushing
Installation of cable terminals,SF6 gas-oil separation bushing used to be installed under help of staff of
manufacturer after installation of GIS.
6.4.4 Considerations of installation of lighting arrester,voltage transformer
Generally,lightning arrester,voltage transformer should not be connected to GIS in power frequency withstand
voltage test.In terms of lightning arrester,in order to avoid the influence of voltage hysteresis effect on ZnO
elements,test voltage should be lower than rated voltage of lightning arrester,more than two consecutive test
voltage applied, the time interval should be more than an hour. In terms of voltage transformer,it should be
avoided voltage of primary parts makes magnetic flux saturation of coil of iron core to affect the precision of
the transformer.take the method that apply frequency doubling of AC voltage from secondary terminal to do
insulation test.
6.5 Auxiliary installation
After installation of each component,the install the following components in turn.
a) During installation of secondary line of elements such as circuit breaker, disconnecting switch, earthing
switch,current transformer,voltage transformer,check the wiring with buzzer, multimeter,confirm the
connection parts are in good condition.
b) During installation of SF6 gas pipeline of each gas chamber,clean up the pipeline inside carefully, install
sealing ring of O type.
c) Ensure the cover of GIS earthing reliably.The electrical connection plate between the flange of the both
sides of corrugated pipe should be connected well.Connect the ground wire on earthing flange of product.
6.6 Installation process
a) Before connecting various elements,remove the protective casing of the basin insulatour use glabrous
paper dipping in acetone to wash surface of basin insulator and surface of embedded conductor
carefully,to ensure the sealing of the connection and contact of conductor are reliable,and install sealing
ring;
b)Installation of sealing ring
Remove protective shield of seal surface,check whether there is damage on sealing surface and the surface
of the seal groove or not.If it is the slight damage,polish it with NO.1000 sandpaper or sharpening stone
carefully.If the situation is serious,must replace a new one;
Check whether there is any any manufacturing quality problems if there is a phenomenon such as
deformation, crack, damage, must replace a new one.
Clean up sealing face,sealing groove and sealing ring with glabrous paper dipping in alcohol carefully.
c) Replace adsorbent
Adsorbent is affected with damp easily,so the adsorbent in the GIS must be through dring
processing .Drying temperature is 400℃,Drying time is 2h. Dried adsorbent should be put in sealing and
dry container to install immediately after cooling to room temperature within the GIS ,it is no more than
10 min to exposed in the air.
If adsorbent installed into GIS, tank could not be sealed and vacuumed immediately,it should be dealt with
again after more than 4 hours.
7 Debugging
As the GIS have been debug in the factory, so mechanical dimension measurement on site is not carried
on, Only carry on mechanical operation and mechanical properties test ; measurement of resistance of
main loop;characteristics test of Current transformer, voltage transformer, lightning arrester ;moisture
Depict content measurement of SF6 gas;sealing test and insulation test.
Check
Used basemap No
Basemap No.
Sign
Date
Mark No. Modified document Sign Date
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:20
1decompressor 2cylinder valve 3joint 4 globe valve 5SF6 gas cylinder 6gas-pressure meter 7 gas supply valve
Depict 8 gas density relay 9 gas supply pipe 10 globe valve 11 Vacuum gauge 12 globe valve 13 vacuum pump
Check Figure 23 Diagram of vacuum and filling SF6 gas
Used basemap No
Basemap No.
Sign
Date
Mark No. Modified document Sign Date
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:21
When vacuum and fill SF6 gas ,the following points should be paid attention to:
a) When vacuum there must be specially-assigned person , when the pump is stopped because of power
outage or other unforeseeable reasons,close globe valve 12 immediately,and open the exhaust valve of the
vacuum pump to prevent the lubricating oil in the vacuum going into GIS;
b) If the vacuum pump need to stop pump during the work , close globe valve 12 firstly , before
disconnection vacuum pump power supply, open the exhaust valve of the vacuum pump;
c) Gas pipe line must be kept clean to prevent moisture or impurity into the tube.
7.2 Inspection before debugging
a) The anchor bolts are tight or not;
b) Each connection bolts are tight or not;
c) All globe valves are in the work positions or not;
d) All kinds of instrument are normal or not;
e) Earthing lines are effective or not;
f) SF6 gas pressure reaches the specified value or not.
7.3 Mechanical operation and mechanical characteristics test
7.3.1 Mechanical operation and mechanical characteristics test of circuit breaker
Circuit breaker must filled SF6 gas of rated pressure before mechanical operation.Circuit breaker should
slowly close and open twice by manul without bad phenomenon before electrical operation.Then the
storage energy of operating mechanism reaches to the specified value,mechanical characteristics test
should be accord with table 4.
Mechanical operation test is shown as table 10.
Table 10 Order of mechanical operation test
Percentage of the operating voltage to the
Number of
NO. rated supply voltage Operating mode Note
operations
Open Close
1 100% 100% O、C Each 30 Reliable action
2 65% 80% O、C Each 5 Reliable action
3 120% 110% O、C Each 5 Reliable action
4 100% 100% O-CO 5 Reliable action
5 30% O 3 No action
6 30% C 3 No action
No debugging and abnormal phenomena allowed during operation.If there is any fault,recalculate the
number of operations after debugging.Supply 80% and 100% rated voltage of energy-storage motor,5
times of energy-storage operations should be normal under closing.
7.3.2 Mechanical characteristics test of disconnecting switch and earthing switch
Time and speed of opening and closing of disconnecting switch and earthing switch should be
accord with table 6, 7.
Mechanical operation test is shown as table 11.
Depict
Check
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:22
Table 11
Percentage of the operating voltage Times of opening and closing by
O or C Times
to the rated supply voltage manul
C 10
110%
O 10
C 10
85% 3
O 10
C 50
100%
O 50
No debugging and abnormal phenomena allowed during operation.If there is any fault,recalculate the
number of operations after debugging.Supply 80% and 100% rated voltage of energy-storage motor,5
times of energy-storage operations should be normal under closing.
7.3.3 Measurement method of time and speed of opening and closing
Time and periodicity of opening and closing of circuit breaker,disconnecting switch,earthing switch is
measured by oscilloscope, speed of opening and closing of circuit breaker,disconnecting switch,earthing
switch is measured by resistance measurement device,calculation method is shown as figure 24, figure 25.
Depict
Check
Used basemap No
Basemap No.
Sign
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:23
Figure 25 Measurement of closing speed of fast earthing switch
Check
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:24
Check
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:25
Gas pressure (1) Read the value of pressure (1) No strabismus to density relay
Check
(1) Confirm contact state (1) Begin from the end of the control
Auxiliary switch
circuit terminal blocks
Wiring (1) Bolts of terminal row are loose or not (1) Tighten the joint of wire
Used basemap No
Gas leakage test (1) Gas leakage test of mechanism and gas pipeline Leak detector
and so on
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:26
Achieve the specified times of 1.Overhaul,cleaning and replacement brittle The specified times of
operation parts of arc extinguish chamber or fracture operation is shown as
2. Inspection, cleaning, and replacement table16 、 main point of
parts of necessary parts maintenance is shown as
table 17
Anomaly in patrol inspection and Maintenance of necessary parts,process and Shown as table 18
general inspection replace parts
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:27
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:28
4) Auxiliary 4) Poor contact of auxiliary · adjust the angle when closing and
switch switch opening actions of crank arm of
auxiliary switch are not accord with
indication.
· When contact area of contact of
auxiliary switch becomes
small,larger contact surface is need
or replace a new one.
· Poor contact caused by loosenes of
fastening screws of auxiliary,tighten
the fastening screws
4 Alarm of Motor Fault of motor · Repair or replace(please contact with
motor over- our company)
current
5 Automatic 1)MCB Short circuit · Repair shout-circuit point
opening of 2)Wiring
MCB 3)Motor
PS:
(1)SF6 gas leak
Leaking interval and leaking parts should be detected timely,when density relay send out alarm signal.find out leaking
reasons and deal with leaking parts,refill gas after meeting requirements.Refilling can be used SF6 gas cylinder directly or
gas recovery unit.
Attention:If a serious leak,start the fan firstly to discharge SF6 gas indoor ,until oxygen concentration indoor is more
than 18%,dispose is allowed.
(2)Dispose of other faults
If there is major fault,please contact with manufacturer in time,detail the cases about on-site fault and protect scene, so that
manufacturer send someone to check and deal with.
8.6 Main points of inspection of circuit breaker
Inspection records of circuit breaker are according to table 17 , related inspection records of circuit
breaker are according to table 19~22,result records of leaking detection of circuit breaker are according to
table 23,records of acting value of SF6 gas density replay are according to table 24.
Table 19
Rated short circuit breaking
Product model kA
current
Manufacturing serial Rate short time withstand
kA
number current
Depict Operating mechanism
Manufacturing time
model
Rated voltage kV SF6 gas pressure MPa
Inspection
Main points of inspection Results of inspection note
parts
Used basemap No
Basemap No.
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:29
Table 19(to continue)
Inspection
Main points of inspection Results of inspection note
parts
Check
Filling gas pressure(MPa) Temperature(℃) Results Measuring instruments
Sign
Date
Modified document
Mark No. Sign Date
No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:30
8.7 Flow chart of on-site maintenance
8.7.1 General flow chart of general maintenance
Disconnected from main circuit,both ends
is earthing
↓
Check terminals of main circuit,measure insulation
resistance
↓
Operating characteristic test
↓
Cut off the operating
power
↓
┌————————————————— ┴
———————————————————┐
Check and clean porcelain bushing and Check the control cabinet of
tighten bolts operating mechanism
↓ ↓
Supplement of SF6 gas |
└—————————————————┬————————————————
─┘
Measurement of resistance of main circuit, the
operating characteristic test
↓
Wiring of main circuit
Sign
Date
Modified
Mark No. Sign Date
document No
YFWJ0804
ZFW20-145 Installments and operating instructions
Page:31
↓
The vacuum
↓
Fill SF6 gas
↓
Sealing inspection of SF6 gas
↓
Measurement of
moisture
↓
Measurement of circuit
resistance
↓
Spring mechanism store energy
↓
Operating characteristic
test
↓
Wiring of main circuit
9 Attached documents
The productions should be with the following documents when leave the factory:
a)Certificate of qualified products, certification of auxiliary engine;
b) Installments and operating instructions;
c)The delivery and packing list;
d ) Ngineering drawings ( layout drawing,foundation drawing,air bound drawing,phase sequence and
circuit resistance drawing,disintegration and packing drawing,packing drawing of transportation,
secondary principle drawing and secondary terminal drawing).
Depict
Check
Used basemap No
Basemap No.
Sign
Date
Modified
Mark No. Sign Date
document No