SL.NO.

PARTICULARS UNIT
1 VETRIFIED TILE FLOORING

Receiving and Laying Vetrified Tile for Flooring of approved


make, colour and thickness laidover CM 1:6 (1 Cement 6
Msand) of average 30 mm thickness tile back buffering and SFT
cement slurry, tamped, laid to required line & level,
including cutting of tiles.
2 CERMIC TILE DADO

Receiving and Fixing of Vetrified Tile for dado laid with tile
adhesive of specified thickness from FOSROC, BASF or
Equalent make as per manufacturers specification incluing
providing and fixing of tile spacers of 2 mm. Rate including
for bull marking, curing & cleaning etc., SFT
3 VETRIFIED TILE SKIRTING

Receiving and Fixing of Vetrified and Ceramic tile skirting


100mm high laid with 1:3 (1 Cement and 3 Msand) or
Adhesive of 12 mm thickness incluing providing and fixing
tile spacers of 3 mm & washed with suitable effective
cleaning. RMT
4 GRANITE THRESHOLD RFT

Note: The above rates are inclusive of; All material shifting, safety kit for labour, Hacking, and
laying protection
RATE REMARKS

23

25

65
60

labour, Hacking, and


SL.NO. PARTICULARS UNIT RATE REMARKS
1 Granite Counter Work Per Flat 950
2 Ledge Wall Per Toilet 300

SL.NO. PARTICULARS UNIT RATE REMARKS


1 Cement Grout SFT 4
2 Epoxy Grout SFT 5
SL.NO. PARTICULARS
Providing and applying Economy Range Acrylic Emulsion of approved color
as per manufacturer's specification, in two coats to get an even finish and
shade obtained, over three coats of fine cement putty and one coat of
primer, including preparation of surface, cleaning after completion, necessary
sand preparing, scaffoling wherever required, etc., complete, and as directed
by engineer-in-charge. Location: Walls, Beams, Columns,
Fins etc., Complete.

1 Flat 2 Coat Putty, 1 Coat Primer, 2 Coat Paint

2 Soft - 1 Coat Primet, 1 Coat Paint


UNIT RATE REMARKS

SQM 85

SQM 35
Sl.No. Description Unit Rate

VETRIFIED TILE FLOORING


Receiving & Laying Vetrified Tile for Flooring of
approved make, colour and thickness laid over
CM 1:6 (1 Cement 6 M Sand) of average 30 mm
thickness tile back buttering and cement slurry,
tamped, laid to required line & level, including
1 cutting of tiles. SFT 23
Rate to include for Bull Marking. Curing &
Covering to protect tile with 275 GSM - 2 mm
thickness, etc., complete Location: Main flooirng,
Balcony Flooring,
toilet Flooring

CERAMIC TILE DADO

Receiving & Fixing of Ceramic tile for dado laid


with Tile Adhesive of specified thickness from
FOSROC, BASF or Equivalent make as per
2 manufactures spec. including providing & fixing
SFT 25
of Tile Spacers of 3 mm. Rate including for Bull
Marking, Corner Beading, Curing & Cleaning
etc., LOCATION: Master Bedroom toilet & other
bed room toilets.

VETRIFIED TILE SKIRTING

Receiving & Fixing Vertified & Ceramic tile


skirting 100 mm high laid with CM 1:3 (1
3 Cement, 3 M Sand) or Adhesive of 12 mm SFT 23
thickness including providing and fixing Tile
spacers of 3mm & washed with suitable effective
cleaning. LOCATION: Servants Room

4 Granite Cutting, Polishing & Fixting RMT 60

5 Mason 900
6 Helper 600
QTY TOTAL
SL.NO. PARTICULARS UNIT RATE

Providing, laying and finishing cement screed of


1 40mm average thickness with M15 grade concrete, SQM 175
including cleaning the surface, trimming, watering
the surface, laying as per   required levels, etc.,
complete to the required slope, formation & finish.
1 VETRIFIED TILE FLOORING

Receiving and Laying Vetrified Tile for Flooring of approved


make, colour and thickness laidover CM 1:6 (1 Cement 6
Msand) of average 30 mm thickness tile back buffering and SFT 23
cement slurry, tamped, laid to required line & level,
including cutting of tiles.
2 CERMIC TILE DADO

Receiving and Fixing of Vetrified Tile for dado laid with tile
adhesive of specified thickness from FOSROC, BASF or
Equalent make as per manufacturers specification incluing
providing and fixing of tile spacers of 2 mm. Rate including
for bull marking, curing & cleaning etc., SFT 25
3 VETRIFIED TILE SKIRTING

Receiving and Fixing of Vetrified and Ceramic tile skirting


100mm high laid with 1:3 (1 Cement and 3 Msand) or
Adhesive of 12 mm thickness incluing providing and fixing
tile spacers of 3 mm & washed with suitable effective
cleaning. RMT 65
4 GRANITE THRESHOLD RFT 60
5 Toilet counter fixing & including all materials EA
6 Ledgwall granite coping including polishing EA
7 MASON Nos 600
8 HELPER Nos 850
REMARKS
SL.NO. PARTICULARS RATE

The work order has a lump sum value of Rs.4,10,000 for


1 providing and fixing for labour hutments and only fixing for
SRC office + store.

Labour hutment - Providing 5.5-0.6mm thick GI


colour coated sheet for roof and wall areas with MS Rs.4,00,000
pipes, angles, box sections wherever required for
2 supports along with all necessary accessories,
tools and tackles, lead and lift consumables,
transportation etc. The accommodation shall have
1 door per room along with a ventilator/window
opening. The door shall be fitted with tower bolt
and and lock inside and lock outside with handle. 
Rs.4,00,000
SL.NO. PARTICULAT UNIT RATE REMARKS
Receiving and Fixing Sadaralli Granite for
1 Flooring, Landing, Treads SQM 434

2 Raiser RMT 130

Providing 5mm groove of 3 nos. on each steps,


single measurement of 3 groove will be taken
3 for bills RMT 45

Providing bullnosing (Half/Full) including polish


4 as per site Engineer instruction RMT 80

5 Skirting RMT 90
SL.NO. PARTICULAT UNIT RATE REMARKS
1 Granite Steps with polish SFT 55
2 Granite Landing SFT 40
3 Granite Skirting with Polish RFT 25
4 Granite Coping Single Side RFT 35
5 Granite Coping Double Side RFT 45
6 Window Jambs RFT 50
7 Counter Fixing Finishing & Handing over including NOS 800
Receiving & Laying Vetrified Tile for
Flooring of approved make, colour and
thickness laid over CM 1:6 (1 Cement 6 M
8 Sand) of average 30 mm thickness tile
back buttering and cement slurry, tamped,
laid to required line & level, including
cutting of tiles. SFT 22

Rate to include for Bull Marking. Curing &


Covering to protect tile with 275 GSM - 2
mm thickness, etc., complete Location:
Main flooirng, Balcony Flooring,

toilet Flooring

Receiving & Fixing of Ceramic tile for dado


laid with Tile Adhesive of specified
thickness from FOSROC, BASF or
Equivalent make as per manufactures
spec. including providing & fixing of Tile SFT 23
Spacers of 3 mm. Rate including for Bull
Marking, Corner Beading, Curing &
Cleaning etc., LOCATION: Master
Bedroom toilet & other bed room toilets.
9
Receiving & Fixing Vertified & Ceramic tile
skirting 100 mm high laid with CM 1:3 (1
Cement, 3 M Sand) or Adhesive of 12 mm
thickness including providing and fixing Tile RFT 15
spacers of 3mm & washed with suitable
effective cleaning. LOCATION: Servants
10 Room
11 Screed SFT 13
SL.NO. PARTICULAT QTY UOM RATE

Receiving and fixing 40 mm cut to size granite as


per design and specification in cement sand mortar
1 as per mock-up shown and done at site 20000 SFT Rs.50/SFT
Receiving and fixing Granite cladding in adhesive as
2 per design and drawing 10000 SFT Rs.45/SFT
3 Granite 40 mm moulding 10000 RFT Rs.20/-RFT
REMARKS
sl.no Description UNIT RATE REMARKS
Reciving, laying and finishing cement screed of 50mm
average thickness with M15 grade concrete, including
cleaning the surface, trimming, watering the surface,
1 laying in strips to required levels, etc.,
location: Foyers, Kitchen, All
Bedroom, Toilet, Decks, Utility and corridors
SQM 175
2 DAMPBLOCK WORK Per Flat 1500
3 MASON NOS 850

4 HELPER NOS 500


5 PLUMBING PACKING NOS 1500

sl.no Description UNIT RATE REMARKS


Reciving, laying and finishing cement screed of 50mm
average thickness with M15 grade concrete, including
cleaning the surface, trimming, watering the surface,
1 laying in strips to required levels, etc., SQM 175
location: Foyers, Kitchen, All
Bedroom, Toilet, Decks, and corridors

Reciving, laying and finishing cement screed of 50mm


average thickness with M15 grade concrete, including
2 cleaning the surface, trimming, watering the surface, SQM 265
laying in strips to required levels, etc.,
location: UTILITY,
BALCONY
3 DAMPBLOCK WORK Per Flat 1500
SL.NO. PARTICULAT UNIT RATE REMARKS
Receving and Fixing 20 mm thick Sadharalli
1 Granite for staircase landing SFT 45

Receiving and Fixing 20 mm thick Sadharalli


2 Granite for staircase Riser RFT 45

Receving and Fixing20 mm thick Sadharalli


Granite for staircase Treads inculing rates
3 moulding,3nos groove finishing, as per dwg SFT 105

Receving and Fixing20 mm thick Sadharalli


Granite for staircase Skirting 100mm height
4 including polishing RFT 35
sl.no Description
eving , preparing and plastering readymade proprietary Gypsum plaster of
average 12 mm thickness. Gyproc make to internal RCC wall surfaces of
concrete / masonry, including surface preparation, scraping, cleaning, doing
jambs, sills, grooves, wattas, rounding of corners etc. all complete as per Design
Consultants drawing, specification and directed by employer, at all lift, lead and
depth, making gypsum plaster mix as per manufacturer specification, hacking closely concrete
surfaces, apply chemical adhesive coating ( bonding agent) on
1 concrete surfaces, also providing and fixing fibre mesh @ 150 mm wide to all the
junctions of concrete and masonry or other areas as instructed by employer etc.,
Plastering shall be to correct line, levels and plumb to receive the paint, including
all materials, labor, scaffolding, ladders, platforms, staging, tools, plant, curing,
cleaning etc. complete as approved by employer. The quoted rate for internal
plastering shall include for necessary groove to be done above skirting tile.

Receving, preparing and plastering readymade proprietary Gypsum plaster of


average 6 mm thickness. Gyproc make to internal RCC ceiling surfaces of
concrete, including surface preparation, scraping, cleaning, rounding of corners
etc. all complete as per Design Consultants drawing, specification and directed
by employer, at all lift, lead and depth, making gypsum plaster mix as per
manufacturer specification, hacking closely concrete surfaces, apply chemical
2 adhesive coating ( bonding agent) on concrete surfaces, Plastering shall be to
correct line, levels and plumb to receive the paint, including all materials, labor,
scaffolding, ladders, platforms, staging, tools, plant, curing, cleaning etc.
complete as approved by employer.

3 DAMPBLOCK WORK
UNIT RATE REMARKS

sft 15

sft 15

Per Flat 1500


sl.no Description UNIT
Receiving, stacking, cutting and fixing of vitrified tile flooring
confirming to technical specification for areas as specified using
tiles of approved size, colour and laying on 30 to 40 mm thick
cement mortar base of ratio (1 Cement : 6 M Sand) along with
cement slurry for adhesion to line, length and to the required
1 finished floor level with 2 mm spacer joints. sft
NOTE: Rate including pvc or pop
protection sheet laying. The rate shall be including cost of
curing , lift , wastage & all other

Receiving, stacking, cutting and fixing of vitrified tiles for skirting


confirming to technical specification and fixing with 3 to 4 mm
thick tile adhesive of approved brand. 2mm spacer Joints shall be
filled & pointed with the matching cementitious grout of
approved make and colour. Polished vitrified tiles skirting - 100
2 mm high .Tile should be cut by machine only, chipping or edge sqm
due to cutting level variations etc., shall not be accepted. The
quoted rate shall include all material, consumables, labour, lead,
lift, curing, wastages and all other incidental charges etc to
complete the work in all respect as instructed by EIC .

Receiving, stacking, cutting and fixing to pattern ceramic glazed


wall tiles confirming to technical specification (thickness to be
specified by the manufacture) of approved make, colours and
shade, as approved by EIC for toilet dados over 12 mm thick bed
of cement Mortar 1:3 (1cement: 3 coarse sand)& cement slurry
required for pasting. Joints shall 2 mm thick spacer and the joints
grouted with matching cementitious grout of approved make and
3 colour Complete. sqm
The rate shall include labour, lead, lift, curing ,hacking wastages,
protection & house keeping incidental charges etc to complete
the work in all respect as instructed by EIC
RATE REMARKS

235

50

235