EKTECH SYSTEMS ENGINEERING SDN BHD

ELV SYSTEM INSPECTION FORM


Project: 507 NEXUS CHERAS
Job No.: Location:

Contractor: Drawing Ref:

Received By: Date/Time:

Block No. Insp. Date:

No. Items to be checked Acceptability Remarks

Contractor Rep. COW

YES NO YES NO

1 Setting-out / Location

2 Type

3 Brand & Model

4 Protection

5 Cable Type & Size

6 Position & Conduit in Good Condition

7 Drawing layout Attached

* Note : The ELV System Inspection form must be attached with Part Construction Drawing.
: Compulsory Standing Supervision for ELV System works.

Comments After Re-inspection

SUBMITTED BY : INSPECTED BY : VERIFIED BY :

(Contractor Rep.) ( Project Executive / COW) (HOP / Project Manager)

SIGNATURE : SIGNATURE : SIGNATURE :

NAME : NAME : NAME :


DATE : DATE : DATE :

MKHBHD-PM-F37 Rev. 0