Professional Documents
Culture Documents
3. net present value the sum of the present values of expected future cash
(NPV) flows from an investment minus the cost of that invest-
ment; difference between an investment's market value
and its cost
4. net present value An investment should be accepted if the net present value
rule is positive and rejected if it is negative.
5. NPV formula
13. discounted pay- the length of time until the sum of the discounted cash
back period flows is equal to the initial investment
18. Average Ac- an investment's average net income divided by its average
counting Return book value
(AAR)
21. Disadvantages of 1. Not a true rate of return; time value of money is ignored
AAR 2. Uses an arbitrary benchmark cutoff rate
2/9
Capital Budgeting
Estudia en línea en https://quizlet.com/_7pnzbk
3. Based on accounting net income and book values, not
cash flows and market values
23. internal rate of the discount rate that makes the NPV of an investment
return (IRR) zero; the discount rate that one would choose to set the
present value of all future cash flows equal to the cash
outflow at time 0
24. IRR rule an investment is acceptable if the IRR exceeds the re-
quired return. It should be rejected otherwise.
IRR>k: accept
IRR<k: reject
27. IRR and non-con- when there are multiple sign changes in cash flows, there
ventional cash is no unambiguously correct answer
flows
28. multiple rates of the possibility of more than one discount rate making the
return problem NPV of an investment zero
29. mutually exclu- a situation in which taking one investment prevents the
sive investment taking of another; higher IRR might not have higher NPV
decisions
32. financing type outflow, then inflow -- more typical, use normal IRR rule
cash flows
35. modified IRR modify cash flows, then calculate IRR; controversy around
(MIRR) this -- gets rid of multiple rates of return problem but
questionable if it's actually measuring anything all that
relevant or more useful than just calculating NPV
36. Discounting Ap- discount all negative cash flows back to present at re-
proach (MIRR) quired rate of return and then add them to initial cost; this
eliminates the multiple rates of return problem
37. Reinvestment compound all cash flows except the first out to the end of
Approach (MIRR) the project's life, then calculate IRR; "reinvest" cash flows
an don't take them out until very end
39. Profitability In- present value of an investment's future cash flows divided
dex (PI) by initial cost
aka benefit-cost ratio
measures "bang for your buck"
4/9
Capital Budgeting
Estudia en línea en https://quizlet.com/_7pnzbk
43. cash flow identity cash flow from assets = cash flow to creditors + cash flow
to stockholders
44. cash flow from the total of cash flow to creditors and cash flow to stock-
assets holders, consisting of the following: operating cash flow,
capital spending, and change in net working capital
45. operating cash Cash flow that results from firm's day-to-day activities of
flow producing and selling.
46. capital spending the net spending on fixed assets (purchases of fixed as-
sets less sales of fixed assets)
47. change in net Net change in current assets relative to current liabilities
working capital for the period being examined.
48. cash flow to cred- interest paid less net new borrowing
itors
49. cash flow to dividends paid out by a firm less net new equity raised
stockholders
50.
5/9
Capital Budgeting
Estudia en línea en https://quizlet.com/_7pnzbk
relevant cash a change in the firm's overall future cash flow that comes
flows for a pro- about as a direct consequence of the decision to take that
ject project
51. incremental cash the difference between a firm's future cash flows with a
flows project and those without the project
52. incremental cash consist of any and all changes in the firm's future cash
flows for project flows that are a direct consequence of taking the project
evaluation
any cash flow that exists regardless of whether or not a
project is undertaken (sunk cost) is not relevant
53. stand-alone prin- the assumption that evaluation of a project may be based
ciple on the project's incremental cash flows
54. sunk costs costs that have already been incurred and cannot be
recovered; irrelevant to decision whether to take on project
55. opportunity cost the most valuable alternative given up if a particular in-
vestment is undertaken; should be considered in project
decisions
57. erosion negative impact on cash flows of existing product from the
introduction of the new product
58. projects usually closely resembles a loan as firm supplies working capital
involve an invest- at the beginning and recovers it at the end
ment in net work-
ing capital
59. financing costs financing costs, such as interest/dividends, are not rele-
and capital bud- vant in determining the future cash flows of a project
geting
61. pro forma finan- financial statements projecting future years' operations;
cial statements summarize much of the relevant info for a project -- in-
cludes sales, fixed costs, variable costs, depreciation,
EBIT, taxes, net income
62. project cash flow project operating cash flow - project change in net working
capital - project capital spending
63. project operating earnings before interest and taxes + depreciation - taxes
cash flow
64. salvage value the estimated value of a fixed asset at the end of its useful
life
65. Bottom-Up Ap- starts with accountant's bottom line (net income) and add
proach to Calcu- back depreciation
lating Operating
Cash Flows OCF = net income + depreciation
66. Top-Down Ap- start at top of income statement with sales and work down
proach to Calcu-
lating OCF OCF = sales -costs-taxes
68. depreciation tax the tax saving that results from the depreciation deduction,
shield calculated as depreciation multiplied by the corporate tax
rate
69. depreciation per (purchase price - salvage value) / years of useful life
year
70. Initial Investment acquisition price +net working capital change - salvage
Calculation value after tax
7/9
Capital Budgeting
Estudia en línea en https://quizlet.com/_7pnzbk
71. EBIT operating income - depreciation
73. Terminal Cash salvage proceeds from the asset + recovery of net working
Flow capital
74. How to solve 1. find NPV of each project over initial life
EAA problem 2. Determine the annuity cash flow that has a PV equal to
the project's NPV
3. Choose project with higher EAA
75. forecasting risk aka estimation risk; the possibility that errors in projected
cash flows will lead to incorrect decisions
76. sources of value should be able to point to a specific source of value such
and NPV as better product, efficiency in production, niche, etc.
78. sensitivity analy- investigation of what happens to NPV when only one
sis variable is changed; useful in pinpointing areas where
forecasting risk is especially severe; if small changes in
projected value of some component of project cash flows
causes large changes in NPV (high sensitivity), then fore-
cast risk with that area is high; steeper slope = more
sensitive
82. soft rationing the situation that occurs when units in a business are allo-
cated a certain amount of financing for capital budgeting
83. response to soft should try to get larger allocation; should only be a
rationing one-time thing, if not there is a problem in the business
because they are passing up positive NPV projects which
fails the goal of maximizing shareholder wealth
84. hard rationing the situation that occurs when a business cannot raise
financing for a project under any circumstances; DCG
analysis breaks down because we don't have a fixed
required return, so best course of action is ambiguous -
probable that required return is so large that no positive
NPV project exists
9/9