MEASUREMENTS OF

CONSTRUCTION WORK IV
DQS281

PILING WORK :
INTERLOCKING STEEL SHEET PILE
INTERLOCKING STEEL SHEET PILE
• Continuous boards inserted into ground as earth
retaining structure, support earth pressure, and
to keep water out of an excavation.

• Sheet pile are normally formed of timber, steel or


reinforced concrete
INTERLOCKING STEEL SHEET PILE
FUNCTION
INTERLOCKING STEEL SHEET PILE
To protect riverbank FUNCTION

To enclose a site or part of to prevent the


escape of the loose subsoil
To form water tight enclosure

To construct retaining wall


TIMBER SHEET PILE
CONCRETE SHEET PILE
V-JOINT
GROUTED TOUNGE AND GROOVE
STEEL SHEET PILE
LARSEEN SHEET PILE

FRODINGHAM SHEET PILE


(Z-SHAPED)

STRAIGHT WEB SHEET PILE


INTERLOCKING JOINT FOR
LARSEEN SHEET PILES
HYDRAULIC HAMMER VIBRATOR

INTERLOCKING STEEL SHEET PILE


METHOD
ANCHORS
2400mm centre to centre
TAKING OFF LIST
NO DESCRIPTION UNIT

Preambles
1 Provision of piling equipment Item
2 Maintaining of piling equipment Item
3 Supply steel sheet pile
a) n.e 12m long M2
b) 12m – 24m long M2
c) Excdg. 24m long M2
4 Total driven area M2
5 Extra over corner pile M
6 Extra over junction pile M
7 Extra over closure pile M
8 Extra over taper pile M
9 Cut off head M
10 Forming Holes No
PILING SCHEDULE
PREAMBLES
CLAUSE DESCRIPTION

E.2.1 Ground Water Level


Ground water level was established at 3.00m below existing ground level on
9/12/2016 which shall be designated at the precontract water level.
E.2.1 Trial pit / Bore holes
3 Nos bore holes were sunk in positions shown on the location drawing.
E.1.1c Existing Services
Telephone cables cross over the site of a height of 10.00m on the North Side
of the site as shown on the location drawing.
E.2.2 Work Near Water
The work is to be carried out at a minimum distance of 40.00m from
riverbank, the normal level of which is 1.00m below ground level.
E.3.1 Starting Level
The piling work is expected starts at and measurement have been taken from
existing ground level
PROVISION OF PILING EQUIPMENT (E4.1a)
HEADING: INTERLOCKING STEEL SHEET PILE (ALL Element/Trade/Work
PROVISIONAL) category:
PILING WORK

SUB HEADING: Provision for piling equipment


Description: Unit Qty
Provision on piling equipment all plant required for this section of
the work. ITEM
MAINTAINING OF PILING EQUIPMENT (E4.1b)
HEADING: INTERLOCKING STEEL SHEET PILE (ALL Element/Trade/Work
PROVISIONAL) category:
PILING WORK

SUB HEADING: Maintaining piling equipment


Description: Unit Qty
Maintaining on site all plan required for this section of the work
ITEM
SUPLLY LENGTH (E5.5a)
HEADING: INTERLOCKING STEEL SHEET PILE (ALL Element/Trade/Work
PROVISIONAL) category:
PILING WORK
SUB HEADING: Supply, deliver to site, unload,
handle, transport and pitch FSP II A U-Section
interlocking steel sheet pile or other equal and
approved steel sheet pile including all necessary
strutting and walling (measured net, no allowance
made for laps)
Description: Unit Qty

Total area of interlocking steel sheet piles not exceeding 12.00m M2


lengths
DRIVING (E5.5b)
HEADING: INTERLOCKING STEEL SHEET PILE (ALL Element/Trade/Work
PROVISIONAL) category:
PILING WORK
SUB HEADING: Supply, deliver to site, unload,
handle, transport and pitch FSP II A U-Section
interlocking steel sheet pile or other equal and
approved steel sheet pile including all necessary
strutting and walling (measured net, no allowance
made for laps)
Description: Unit Qty

Total driven area M2


CORNER (E5.5c)
HEADING: INTERLOCKING STEEL SHEET PILE (ALL Element/Trade/Work
PROVISIONAL) category:
PILING WORK
SUB HEADING: Supply, deliver to site, unload,
handle, transport and pitch FSP II A U-Section
interlocking steel sheet pile or other equal and
approved steel sheet pile including all necessary
strutting and walling (measured net, no allowance
made for laps)
Description: Unit Qty

Extra over for Corner pile M


CUT OFF HEAD (E5.8e)
HEADING: INTERLOCKING STEEL SHEET PILE (ALL Element/Trade/Work
PROVISIONAL) category:
PILING WORK
SUB HEADING: Supply, deliver to site, unload,
handle, transport and pitch FSP II A U-Section
interlocking steel sheet pile or other equal and
approved steel sheet pile including all necessary
strutting and walling (measured net, no allowance
made for laps)
Description: Unit Qty

Horizontal cutting top of interlocking piles to remove tops to M


required level
FORMING HOLE (E5.9d)
HEADING: INTERLOCKING STEEL SHEET PILE (ALL Element/Trade/Work
PROVISIONAL) category:
PILING WORK
SUB HEADING: Supply, deliver to site, unload,
handle, transport and pitch FSP II A U-Section
interlocking steel sheet pile or other equal and
approved steel sheet pile including all necessary
strutting and walling (measured net, no allowance
made for laps)
Description: Unit Qty

Cutting interlocking steel piles to form holes No


END..