You are on page 1of 21

SLAR/QS/FSPU/UITMKS

MEASUREMENTS OF
CONSTRUCTION WORK IV
DQS281

PILING WORK :
PRECAST CONCRETE PILE
PRECAST CONCRETE PILE
• Commonly used and suitable for almost any soil
condition
• Not suitable for limestone area, soft soil and sand soil
• Nominal size: 150x150mm – 400x400mm
• Maximum load bearing capacity: 1450kN(145 tonne)
• Grade of concrete: 25 – 40
TAKING OFF LIST
DESCRIPTION (if there is TRIAL PILE)
1. Preambles
UNIT

2. Provision Of Piling Equipment Item


3. Maintaining Piling Equipment Item
Preliminary Pile / Trial Pile
4. Precast Concrete Square Initial Pile No
5. Precast Concrete SquareExtension Pile M
6. Driving – Vertical M
7. Driving – Raking (Ratio) M
8. Pile Extension No
9. Cut-off Head No
10. Preparing concrete pile head No
11. Preliminary Load Test Item
Working Pile
12. Precast Concrete Square Initial Pile No
13. Precast Concrete Square Extension Pile M
14. Driving – Vertical M
15. Driving – Raking (Ratio) M
16. Pile Extension No
17. Cut-off Head No
18. Preparing concrete pile head No
19. subsequent Load Test Item
TAKING OFF LIST
DESCRIPTION (if there is NO TRIAL PILE) UNIT
1. Preambles
2. Provision Of Piling Equipment Item
3. Maintaining Piling Equipment Item

WORKING PILE
4. Precast Concrete Square Initial Pile No
5. Precast Concrete Square Extension Pile M
6. Driving – Vertical M
7. Driving – Raking (Ratio) M
8. Pile Extension No
9. Cut-off Head No
10. preparing concrete pile head No
11. Preliminary Load Test Item
12. Subsequent Load Test Item
PILING SCHEDULE
PILE CAP NO. OF NO. OF TOTAL INITIAL DRIVING EXTENSION PILE PILE CUT PREPARING REMARK
REF. PILE PILE PER NO. OF PILE (M) (M) EXTENSI- OF PILE HEAD S
CAP PILE CAP PILE (NOS) VERTICAL RAKING N.e 3.00m Exc. 3.00m ON (NO) HEAD (NO)
(NO)
PREAMBLES
CLAUSE DESCRIPTION

E.2.1 Ground Water Level


Ground water level was established at 3.00m below existing ground level on
9/12/2016 which shall be designated at the precontract water level.
E.2.1 Trial pit / Bore holes
3 Nos bore holes were sunk in positions shown on the location drawing.
E.1.1c Existing Services
Telephone cables cross over the site of a height of 10.00m on the North Side
of the site as shown on the location drawing.
E.2.2 Work Near Water
The work is to be carried out at a minimum distance of 40.00m from
riverbank, the normal level of which is 1.00m below ground level.
E.3.1 Starting Level
The piling work is expected starts at and measurement have been taken from
existing ground level
PROVISION OF PILING EQUIPMENT (E4.1a)
Heading: Element/Trade/Work
PRESSURE TREATED TIMBER PILE (ALL
PROVISIONAL) category:
Sub Heading: PILING WORK
Provision of Piling Equipment

Description: Unit Qty


Allow for bringing to site and removing from site
all plant required for this type of piling. ITEM
MAINTAINING OF PILING EQUIPMENT (E4.1b)
Heading: Element/Trade/Work
PRESSURE TREATED TIMBER PILE (ALL
PROVISIONAL) category:
Sub Heading: PILING WORK
Maintaining of Piling Equipment

Description: Unit Qty


Allow for maintaining on site all plant required
for this type of piling. ITEM
PRECAST CONCRETE INITIAL PILE (E5.3a)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Total number of piles length 12.00 m long with
380mm x 200mm 18 kg chilled hardened iron No
shoe and 200mm x 200mm mild steel plate
head
DRIVING (E5.3b)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Total driven length
M
DRIVING (E5.3b)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Working Pile)

Description: Unit Qty


Total driven length at raking ratio of 1 in
1.7320 M
PRECAST CONCRETE EXTENSION PILE (E5.7b)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Total length of extension pile not exceeding
3.00m. M

Total length of extension pile exceeding 3.00m.


PILE EXTENSION (E5.7a)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Total number of pile extensions
No
CUT-OFF HEAD (E5.9a)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Cutting off top of pile to required level
No
PREPARING CONCRETE PILE HEAD (E5.9b)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Preparing concrete pile heads and reinforcement
for caping No
PRELIMINARY LOAD TEST (E7)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Allow for __ nos of preliminary load testing on a
group of numbers 200mm x 200mm precast Item
concrete piles to a total combined load of ____KN.
SUBSEQUENT LOAD TEST (E7)
Heading: Element/Trade/Work
Precast Concrete Pile (ALL PROVISIONAL)
category:
Sub-Heading: PILING WORK
200mm x 200mm precast concrete Grade 45 piles
with chamfered edges of a minimum compression
stress of 48 N/mm at 28 days including all
accessories shoe, joint, and plate. (Trial Pile)

Description: Unit Qty


Allow for ___ nos of subsequent load testing on a
single ____mm x _____mm timber piles to a of Item
____KN.
END..