Professional Documents
Culture Documents
Financial Standings
a) Liquidity
b) Profitability
c) Net Worth
d) Annual Turnover
Next Image shows the Soil Strata available at various sections of the project.
Based on the samples obtained from the bore holes following tests were conducted
on the samples-
9 RETAINING WALL
BLOCK WORK INFRONT OF RETAINING WALL Dimension of Block– 400*200*200
Mortar-Cement sand mortar with ratio 1:4
Block Strength- 7.5 N/mm2
MIX –M15
ROOF SLAB
Thickness of the bond-10mm
Joint Type-Basic English Bond(1 block thick)
RETAINING WALL
BLOCK WORK IN FRONT
OF RETAINING WALL
CONCOURSE SLAB
BLOCK WORK FOR ROOMS
EXAMPLE
U23-SAFETY ROOM
U64-ELECTRICAL APPLIANCE REPAIR
U26-WAITING ROOM ARCHITECTURAL ROOM PLAN(CONCOURSE SLAB)
COOLING MECHANISM OF OTE
OTE LIFTING
FRESH AIR DUCTS
Ventilation systems provided below the roof slab for a constant supply
of fresh air.
ROOF SLAB
SCUPPER DRAIN(BEHIND BLOCK WORK) Water proofing material (Brush Bond Rfx)
EXCAVATORS
Hydraulic 220 Excavator
Hydraulic 210 Excavator
Hydraulic 215 Excavator
BREAKERS
Hydraulic 340 Breaker
Hydraulic 210 Breaker
Shot creting
Concrtete-M40
5.25 m below roof level
Formwork & scaffolding for Concourse slab
Thickness- 550mm
Reinforcement For concourse slab
BOOM PLACER
Surface preparation: The bulged area on concrete surface shall be hacked with chisel to
required line, level. All dirt, dust shall be cleaned with brush and water.
Repairing: Hacked area will be patched up with cement: sand mortar of proportion 1:4.
On the completion of patch up work, the exposed area shall be thoroughly cured.
Grout Loss Exposed aggregate surface created by exit of cement slurry/grout mortar from
the gaps of formwork due to excessive vibration, unsealed joint of formwork
during pouring of concrete.
Repair
-The concrete surface is cleaned and free from dust/oil/grease etc by using
broom or wire mesh by scrubbing vigorously.
-After removal of loose particles surface is washed with water.
-Patch-up is done at cleaned surface with non-shrink Grout conbextra GP2
Minor Honey Combing
It is due segregation of aggregates and mortar into the concrete.
Honeycomb creates in structures due to mainly improper
compaction in terms of excessive/insufficient vibration at the
time of placing.
Major Honeycombing
Repairing Involves-
The loose aggregate that are exposed shall be removed by
gently tapping on it. After removal of all loose aggregate,
dust, dirt etc. by wire/Soft brush then surface will be
cleaned with Water. Patchup is done by using conbextra
GP2/Rendroc which is mixed with cement and then the
paste is applied.
Waterproofing of Structure
Chemicals used for Waterproofing
-For Priming Purpose
Master Seal M501&502(Provided In two component A & B)
-Waterproofing Layer
Master Seal M800(Provided In two component A & B)
Master Seal M501&502-Master Emaco 2525 is a solvent free, high-performance, versatile epoxy binder that can be used
to produce a range of epoxy resin based mortars.
Used For-
Structural bonding of new to old concrete
Production of epoxy resin mortars to grout bolt holes
Steel bonding
-MIXING
• Application of Primer Involves mixing of component A and B and application on
the surface as shown MIXING OF A & B