Time Schedule Finishing Rotor - Motor 5.

3MW
No Finishing Step Date 28-May 29-May 30-May 5/31/2023
Time 21:00 22:00 23:00 0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00
P
1 Pengambilan data megger jam 10 (electrical test)
A
P 1 1 1 1 1 1
2 Konek lead-Coil - 6 jam
A
P 0
3 Ambil data lead - coil (megger test)
A
P 0 1
4 Oven seblum varnish - 1 jam
A
P 0 1 1 1 1 1
5 Varnish & konek leadbar-slipring - 5 jam
A
Pengeringan (oven) setelah varnish - 11 jam P 0 1 1 1 1 1 1 1 1 1 1 1
6
(temp 130-140 degC) A
P 0 1 1 1 1
7 Bending & cleaning varnish di core rotor - 4 jam
A
P 1
8 Hipot Test
A
P 0 1 1 1 1 1
9 Pengeringan bending & cor 1 hole - 5 jam
A
Persiapan pengiriman rotor & pengambilan data P
10
MCA - TSD Citeureup A
P 0 1 1 1 1
11 Pegiriman ke Workshop Mesindo
A
P 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
12 Proses balancing (target 31 Mei finish)
A