Professional Documents
Culture Documents
Gav Hurford
System Operator
Overview
Final thoughts
What is the System Operator?
Customer Services
sells the electricity
National Control
• 765 kV – 132 kV
• Frequency control
• Voltage control
• System security
Regional Control
• 132 kV – 66 kV
• Voltage control
• System security
Regional Control
• 66 kV – 11 kV
• Customer supply
National Control is responsible for the real-
time operation of the power system
6
Generation responsibilities (August 2021)
2 500
0
500
1 000
1 500
2 500
2 000
01-Sep-21 01-Sep-21
01-Sep-21 01-Sep-21
02-Sep-21 02-Sep-21
02-Sep-21 02-Sep-21
03-Sep-21 03-Sep-21
04-Sep-21 04-Sep-21
04-Sep-21 04-Sep-21
05-Sep-21 05-Sep-21
06-Sep-21 06-Sep-21
06-Sep-21 06-Sep-21
07-Sep-21 07-Sep-21
07-Sep-21 07-Sep-21
08-Sep-21 08-Sep-21
09-Sep-21 09-Sep-21
09-Sep-21 09-Sep-21
10-Sep-21 10-Sep-21
11-Sep-21 11-Sep-21
11-Sep-21 11-Sep-21
12-Sep-21 12-Sep-21
12-Sep-21 12-Sep-21
13-Sep-21 13-Sep-21
14-Sep-21 14-Sep-21
14-Sep-21 14-Sep-21
15-Sep-21 15-Sep-21
16-Sep-21 16-Sep-21
16-Sep-21 16-Sep-21
17-Sep-21 17-Sep-21
17-Sep-21 17-Sep-21
18-Sep-21 18-Sep-21
19-Sep-21 19-Sep-21
Impact of renewable generation
19-Sep-21 19-Sep-21
20-Sep-21 20-Sep-21
Technology totals
21-Sep-21 21-Sep-21
21-Sep-21 21-Sep-21
22-Sep-21 22-Sep-21
22-Sep-21 22-Sep-21
23-Sep-21 23-Sep-21
24-Sep-21 24-Sep-21
24-Sep-21 24-Sep-21
Technology contribution to renewable total
25-Sep-21 25-Sep-21
26-Sep-21 26-Sep-21
26-Sep-21 26-Sep-21
27-Sep-21 27-Sep-21
27-Sep-21
PV and to a lesser extent CSP continue to support the system during the day
27-Sep-21
28-Sep-21 28-Sep-21
29-Sep-21 29-Sep-21
29-Sep-21 29-Sep-21
30-Sep-21 30-Sep-21
Some evenings wind has supplied over 2000 MW during peak, while others much less so.
CSP
CSP
Hydro
Hydro
Solar PV
Solar PV
Landfill gas
Landfill gas
Onshore Wind
Onshore Wind
Renewable statistics
Current Installed Capacity (MW)
Maximum Contribution (MW) - based on System Operator data (subject to metering verification)
CSP 500.0
PV 2,212.1 Cal Year Indicator CSP PV Wind (Eskom+IPP) Total (Incl other REs)
Maximum 504.5 2,062.8 2,284.0 4,433.0
Wind (Eskom+IPP) 2,921.4 All Time
Max Date 25-Nov-2020 12:00 10-Oct-2021 12:00 21-Jun-2021 13:00 02-Oct-2021 14:00
Total (Incl other REs) 5,659.0
Maximum 200.9 1,350.5 1,229.8 2,576.3
2016
Witkop Solar Plant (30 MW), Limpopo
Max Date 11-Aug-2016 14:00 16-Dec-2016 12:00 23-Dec-2016 13:00 23-Dec-2016 13:00
Maximum 302.0 1,432.5 1,708.2 3,142.7
2017
Max Date 07-Nov-2017 10:00 27-Oct-2017 12:00 25-Dec-2017 18:00 13-Dec-2017 13:00
Maximum 399.7 1,392.1 1,902.3 3,298.9
2018
Max Date 04-Dec-2018 16:00 03-Oct-2018 12:00 02-Oct-2018 16:00 28-Sep-2018 11:00
Maximum 502.1 1,375.6 1,872.0 3,530.6
2019
Max Date 24-Sep-2019 11:00 19-Jan-2019 12:00 14-Dec-2019 15:00 27-Oct-2019 13:00
Maximum 504.5 1,929.2 2,113.9 4,050.0
2020
Max Date 25-Nov-2020 12:00 25-Nov-2020 12:00 01-Dec-2020 19:00 24-Nov-2020 13:00
Maximum 503.9 2,062.8 2,284.0 4,433.0
2021
Max Date 10-Oct-2021 11:00 10-Oct-2021 12:00 21-Jun-2021 13:00 02-Oct-2021 14:00
Maximum Difference between Consecutive Evening Peaks (MW) -
based on System Operator data (subject to metering verification)
Cal Year Indicator Total (Incl other REs)
Maximum 1,744
All Time
Max Date 07-Aug-2021 to 08-Aug-2021
Maximum 828
2016
Sere Wind Farm
11
Generator Unit Requirements [Grid Code]
Time vs. System Frequency
• No automatic tripping.
Time (Minutes)
Emergency
Load
Reduction
Preventing Total Power System Collapse
(Blackout)
50.2Hz
Controlled manual
load shedding
Automatic load
shedding
(<1sec)
14
What is a national blackout?
15
Major blackout events
The impact is devastating on almost every single part of daily life. Sellers were only taking cash, either in
dollars or bolivars
Shopkeepers and residents were battling to keep their produce fresh, with restaurants either preparing what
they have or preparing to throw everything out
https://www.thesouthafrican.com/venezuela-blackout-eskom-grid-collapse-glimpse/
A few key impacts of a national blackout
Telecommunications • Mobile sites will be sustained 2-4hrs (what about traffic & priority access)
• Backbone failure within 8hrs
• Recharging batteries
• Other South African Telco’s will not be available after a while
Water • Local reserve 48hr guideline for munics (not universally in place)
• Water treatment essential (cannot distribute raw water)
• Water required for data centres
• Power stations may have min 3 days (for 6 units) // downstream flooding
No MS TEAMS?
Liquid fuel
• Storage available “3-5 days” subject to requirements (no backup gens)
• Ports and refineries need electricity (No contingency plans)
• Industry will be required to ration and prioritise supply
● Equipment damage*
● Uncertainty of event
Speed of restoration
● General Grid Code compliance (e.g. ● Response procedures (incl. Load ● Coal automatic unit islanding (new units > Increase exponential
generator specs, two facilities) shedding protocols, manual island) 200MW) at identified Power Station based on islanded units
● System Operations best practice ● Control room skills/intuition ● Islanding procedures (tested)
(reserves, skills) (knowledge and experience) ● Power station operator skill/intuition to
● Network flexibility beyond design ● Third party (Munic control rooms) manage the unit
criteria (e.g. reactors) ● Resources (e.g. fuel oil as required)
● Operational planning (reserves, DMP) ● Special protection schemes ● Three black start facilities capable of
● Outage scheduling (Tx, Gx risk (automatic under-frequency, low restarting the country
assessments and decisions) voltage, reverse-power, transient ● Blackstart facilities Procedures (tested)
stability, out-of-step, inter-lock, power ● Power station operator skill/intuition to
● Real-time operations/response
system stabilizers, sub-synchronous manage the restart
● Protection implementation resonance, etc)
● Situational awareness (visibility) ● Resources
• Our grid topology makes black starting the Eskom system technically
difficult because of the centralised generation pool and the very long
transmission lines
• This power must be supplied in a stable manner for the duration of the
start-up (minimum four hours)
20
Restoring a blackout
• Following a complete blackout of the grid, at least one black start facility
is required to restart the power system.
• The longer a coal fired generator has been shut down, the longer it
takes to restart the unit.
22
MW
21000
22000
23000
24000
25000
26000
27000
28000
29000
30000
31000
32000
33000
34000
35000
00:00 to 01:00
01:00 to 02:00
02:00 to 03:00
03:00 to 04:00
04:00 to 05:00
05:00 to 06:00
06:00 to 07:00
07:00 to 08:00
08:00 to 09:00
09:00 to 10:00
10:00 to 11:00
Summer and Winter Profiles
23
11:00 to 12:00
Hours
12:00 to 13:00
13:00 to 14:00
14:00 to 15:00
15:00 to 16:00
16:00 to 17:00
17:00 to 18:00
18:00 to 19:00
19:00 to 20:00
20:00 to 21:00
21:00 to 22:00
Actual 2018 Winter Profile for Residual Demand
22:00 to 23:00
23:00 to 00:00
Summer and Winter Profiles
01:00 to 02:00
02:00 to 03:00
03:00 to 04:00
04:00 to 05:00
05:00 to 06:00
06:00 to 07:00
07:00 to 08:00
08:00 to 09:00
09:00 to 10:00
10:00 to 11:00
11:00 to 12:00
12:00 to 13:00
13:00 to 14:00
14:00 to 15:00
15:00 to 16:00
16:00 to 17:00
17:00 to 18:00
18:00 to 19:00
19:00 to 20:00
20:00 to 21:00
21:00 to 22:00
22:00 to 23:00
23:00 to 00:00
MW
Hours
24
Pumped storage schemes
• The scheme is about 75% efficient but offers the only viable means of storing large amounts of energy.
• Pumped Storage Schemes complement traditional base load technologies such as large coal fired power and nuclear
power stations because they can store surplus power during off-peak times and generate during peak times.
• Pumped storage schemes will be required to maintain power supply and grid stability when there is a large
penetration of wind and solar power. (Particularly in SA because our neighbours cannot support us like in Europe or
America)
• Pumped storage schemes are often combined with water transfer schemes.
Open cycle gas turbine
OCGTs, GTs and pumped storage make up 6 000 MW of dispatchable generation. If the
fuel for these generators is depleted it will add 6 stages of load shedding.
Managing a constrained power system
29
Planning process
18 month
UCLF +
residual
OCLF
demand
forecast
forecast
• Four critical components make up the Plan and determine the need for
OCGT generation usage and load shedding:
31
System Operator Capacity Outlook for the next 18
Months (Base Case)
System Operator Capacity Outlook (Base Case)
MW Available Capacity (Excl Gas) Gas Reserve Requirement Planned Outages
51000 Unplanned Provision Peak Residual Forecast Installed Capacity
49000
47000
Winter UCLF
45000 11 000 MW
Summer UCLF Summer UCLF
43000
12 000 MW 12 000 MW
41000
39000
37000
35000
PCLF Operating Reserve
33000
31000
29000
27000 Gas
25000
23000 Available Capacity (Excl Gas)
21000
19000
Sep 2021
Oct 2021
Jun 2022
Oct 2022
Jan 2022
Apr 2022
Jan 2023
Apr 2023
Feb 2022
Mar 2022
Sep 2022
Feb 2023
Mar 2023
Jul 2022
Aug 2022
Nov 2021
Dec 2021
May 2022
Nov 2022
Dec 2022
Month
Cumulative Monthly Unplanned Outage Levels
Cumulative Monthly Unplanned Outage Levels
Monthly UCLF % Monthly OCLF % Monthly UCLF MW Monthly OCLF MW
35.0% 22 500
20 000
30.0%
17 500
20.0% 12 500
15.0% 10 000
7 500
10.0%
5 000
5.0%
2 500
0.0% 0
May-2017
May-2018
May-2019
May-2020
May-2021
Nov-2017
Sep-2017
Sep-2018
Sep-2019
Sep-2020
Sep-2021
Jan-2017
Jul-2017
Jan-2018
Jul-2018
Jan-2019
Jul-2019
Jan-2020
Jul-2020
Jan-2021
Jul-2021
Mar-2017
Mar-2018
Nov-2018
Mar-2019
Nov-2019
Mar-2020
Nov-2020
Mar-2021
Months
Source: Gx Technical Indicators Reports 33
Unplanned Outage Performance
Winter 2021
Winter UCLF+OCLF Frequency (01-Apr-2021 to 31-Aug-2021)
Thu 01-Apr-2021 to Tue 31-Aug-2021 Base Plan Assumption Base Plan + 1000MW Risk Base Plan + 2000MW Risk
30.0% 100
90
24.1%
25.0% 80
20.9%
Frequency in %
70
20.0% 17.8%
60
14.4%
15.0% 50
9.7% 40
10.0% 8.2% 30
20
5.0% 2.7%
1.7%
0.0% 0.2% 0.2% 10
0.0% 0
6,000 to
7,000 to
8,000 to
9,000 to
10,000 to
11,000 to
12,000 to
13,000 to
14,000 to
15,000 to
16,000 to
10,000
7,000
8,000
9,000
16,000
11,000
12,000
13,000
14,000
15,000
17,000
Outage Level (MW)
70
14.6% 13.7%
15.0% 13.0% 60
9.8% 50
10.0% 40
6.3% 30
5.0% 3.7% 20
0.7% 1.2% 10
0.0%
0.0% 0
6,000 to
7,000 to
8,000 to
9,000 to
10,000 to
11,000 to
12,000 to
13,000 to
14,000 to
15,000 to
16,000 to
10,000
7,000
8,000
9,000
11,000
12,000
13,000
14,000
15,000
16,000
17,000
Outage Level (MW)
12-month outlook to 31 August 2022
Winter 2022
Number of LS days 0 days 3 days 65 days
Highest stage of LS N/A Stage 1 Stage 2
OCGT costs R 0.8bn R 1.8bn R 3.5bn
History has shown that it is not possible to use more than about R 1.2bn of diesel in a month due to the physical limitations of moving
the diesel to the OCGT stations. Where the Plan shows a diesel usage greater than this, additional stages of load shedding should be
expected
36
Grid Code & NRS048-9
• NRS048-9 Ed. 2
• This is not an Eskom document, it is an industry document adopted and
approved by NERSA
• The 3rd edition is currently being developed
• Defines load shedding, load curtailment and load reduction
• Defines criteria for critical and essential loads
• Specifies guidelines for load shedding schedules including Stages 5-8
• System Operator must declare a power system emergency. This is no
longer done publically because it causes widespread panic among the
public
37
NRS048-9
38
Implementing load shedding
Instruct
Communicate
redistributors to
System Operator National Control No advanced with internal
shed or shed at
(National Control) determines the warning stakeholders and
Generation transmission
monitors the stage of load brief shareholder
constraint level
power system shedding and the Sufficient
24/7/365 duration warning
Consult with
internal
stakeholders and
Load shedding brief shareholder
according to
schedules. Load
• Early Warning
curtailment as
(internal)
instructed
• Alert
(external)
• Instruction
Distribution
instruct Instruct Eskom
municipalities or Distribution to
shed on their shed load.
behalf
39
Final thoughts
40
Why do we load shed?
42
43