You are on page 1of 64

PROJEK PENYELENGGARAAN CERUN DI

JALAN PERSEKUTUAN DAN JALAN NEGERI


SEMENANJUNG MALAYSIA MELALUI
KONTRAK JANGKAMASA PANJANG

Semua Kerja-Kerja Pembaikan Cerun Yang Merangkumi Kerja Awalan,


Reka Bentuk Dan Pembaikan Fizikal (Reka & Bina) Di Jalan
Persekutuan Semenanjung Dan Jalan Negeri Malaysia Dan Kerja-Kerja
Pengumpulan Data.

PROJECT QUALITY PLAN


Project Title:

KERJA PEMBAIKAN CERUN MENGGUNAKAN


KAEDAH “SOIL NAIL & HYDROSEEDING” DI
LALUAN FT136 SEK 35.5 JALAN KULIM-BANDAR
BAHARU, KULIM, KEDAH.

KEMENTERIAN KERJA RAYA MALAYSIA JABATAN KERJA RAYA MALAYSIA


Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

TABLE OF CONTENTS
1. PROJECT POLICY ...................................................................................... 7
2. PROJECT DESCRIPTION ............................................................................... 8
2.1. PROJECT NAME ................................................................................... 8
2.3. PROJECT ORGANISATION ....................................................................... 8
2.4. PROJECT SCOPE OF WORKS .................................................................... 9
2.5. PROJECT AND CONTRACT PARTICULARS ...................................................... 9
3. PROJECT ORGANISATION, AUTHORITIES AND RESPONSIBILITIES ............................... 10
3.1. ORGANISATION CHART ......................................................................... 10
3.2. RESPONSIBILITIES ............................................................................... 10
3.2.3. Safety Officer .............................................................................. 11
3.2.4. Site Safety Supervisor .................................................................... 11
3.2.5. Land Surveyors............................................................................. 11
3.2.6. Supervisors ................................................................................. 12
3.2.7. Document Controller / Clerk ............................................................ 12
4. SYSTEM IMPLEMENTATION POLICIES ............................................................... 13
5. QUALITY OBJECTIVES ................................................................................ 13
6. PROCEDURE LIST ..................................................................................... 14
7. EQUIPMENT PLAN..................................................................................... 15
7.1. LIST OF EQUIPMENT ............................................................................ 15
7.2. METHOD STATEMENTS LIST .................................................................... 15
7.3. SUBCONTRACTORS’ METHOD STATEMENTS LIST ............................................ 16
7.4. MACHINERIES AND EQUIPMENT MAINTENANCE PLAN ....................................... 16
7.5. SCHEDULED INSPECTIONS AND MAINTENANCE .............................................. 17
8. WORK PROGRAM ...................................................................................... 18
9. METHOD STATEMENTS ............................................................................... 19
9.1. SURVEY WORKS.................................................................................. 20
9.1.1. Surveying Teams........................................................................... 20
9.1.2. Traverse Works ............................................................................ 20
9.1.3. Levelling Works ............................................................................ 20
9.2. SITE CLEARANCE ................................................................................ 20
9.2.1. Site Clearing Method ...................................................................... 20
9.2.2. Dumping Grounds.......................................................................... 21
9.2.3. Remove, Storage and Reinstating of Existing Guard Rail. ........................... 21

2|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.2.4. Demolition Works.......................................................................... 21
9.3. EARTHWORKS.................................................................................... 21
9.3.1. Excavate, Load, Haul and Deposit. ..................................................... 21
9.3.2. Removal of Unsuitable Material (Slipped Material)................................... 22
9.4. TURFING ......................................................................................... 24
9.4.1. Close Turfs ................................................................................. 24
9.4.2. Turf Reinforcement Matrix (TRM) ....................................................... 24
9.4.3. Laying of Close Turf....................................................................... 24
9.4.4. After Turf Care ............................................................................ 24
9.5. LOWER BASE ..................................................................................... 25
9.5.1. General ..................................................................................... 25
9.5.2. Materials .................................................................................... 25
9.5.3. Laying Equipment ......................................................................... 25
9.5.4. Laying Procedures ......................................................................... 25
9.6. UPPER SUB-BASE ................................................................................ 26
9.6.1. General Descriptions ...................................................................... 26
9.6.2. Materials .................................................................................... 26
9.6.3. Plants/ Machineries Required ........................................................... 26
9.6.4. Procedures ................................................................................. 26
9.6.5. Site Records ................................................................................ 27
9.7. ASPHALTIC CONCRETE BINDER COURSE ...................................................... 27
9.7.1. General ..................................................................................... 27
9.7.2. Material ..................................................................................... 27
9.7.3. Equipment .................................................................................. 27
9.7.4. Procedure .................................................................................. 28
9.8. ASPHALTIC CONCRETE WEARING COURSE ................................................... 29
9.8.1. General Description ....................................................................... 29
9.8.2. Materials .................................................................................... 29
9.8.3. Equipment .................................................................................. 29
9.8.4. Procedure .................................................................................. 29
9.9. ASPHALTIC CONCRETE WEARING COURSE ................................................... 30
9.9.1. Pull Out Test ............................................................................... 30
9.10. SOIL NAIL WORKS............................................................................. 34
9.10.1. Soil Nailing............................................................................... 34

3|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.11. GUNITING WORKS ............................................................................ 37
9.11.1. Guniting .................................................................................. 37
9.11.2. Procedure ................................................................................ 37
9.12. CONCRETE WORKS ........................................................................... 39
9.12.1. Special Requirements .................................................................. 39
9.12.2. Uniformity of Color ..................................................................... 39
9.12.3. Steel Reinforcement ................................................................... 39
9.12.4. Mix Design And Proportioning ......................................................... 40
9.12.5. Workability .............................................................................. 41
9.12.6. Sampling And Testing .................................................................. 42
9.12.7. Formwork and Surface Finish ......................................................... 44
9.13. DRAINAGE WORKS ............................................................................ 45
9.13.1. General .................................................................................. 45
9.13.2. Excavation ............................................................................... 45
9.13.3. Concrete Beds ........................................................................... 45
9.13.4. Laying of Drain and Culverts .......................................................... 45
9.14. GRID BEAM .................................................................................... 45
9.14.1. Setting Out .............................................................................. 45
9.14.2. Site Clearing ............................................................................. 45
9.14.3. Installation of Soil Nail................................................................. 46
9.14.4. Installation of Pre-Cast Grid Beam ................................................... 46
9.14.5. Inspection and Test Plan .............................................................. 46
9.15. CASCADE DRAIN .............................................................................. 47
9.15.1. Setting out ............................................................................... 47
9.15.2. Slope Preparation ...................................................................... 47
9.15.3. Cascade Drain ........................................................................... 47
10. RISK MANAGEMENT PLAN ......................................................................... 48
10.1. INTRODUCTION ............................................................................... 49
10.2. RISK MANAGEMENT PROCEDURE............................................................ 49
10.2.1. Process ................................................................................... 49
10.2.2. Risk Identification ...................................................................... 49
10.2.3. Risk Analysis ............................................................................. 49
10.2.4. Qualitative Risk Analysis ............................................................... 49
10.2.5. Quantitative Risk Analysis ............................................................. 50

4|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


10.3. RISK RESPONSE PLANNING .................................................................. 50
10.4. TOOLS AND PRACTICES ...................................................................... 51
10.5. GENERAL SAFETY REQUIREMENT ........................................................... 51
10.5.1. Head Protection ........................................................................ 51
10.5.2. Foot Protection ......................................................................... 51
10.5.3. Eye Protection .......................................................................... 51
10.5.4. Hands and Arm Protection ............................................................ 51
10.5.5. Safety Belts and Lifelines ............................................................. 51
10.5.6. Protection against Moving Object .................................................... 51
10.5.7. Respiratory Protection Equipment ................................................... 51
10.5.8. Ear Protection ........................................................................... 51
10.5.9. Warning Sign ............................................................................ 52
10.5.10. Fire Protection .......................................................................... 52
10.5.11. Miscellaneous ........................................................................... 52
10.5.12. Safety Organization and Responsibilities ............................................ 53
10.6. SAFETY AND HEALTH INSTRUCTION........................................................ 53
10.6.1. Safe Excavation and Trenching Works ............................................... 53
10.6.2. Objectives ............................................................................... 53
10.6.3. Procedures............................................................................... 53
10.7. STACKING PILING OF MATERIALS ........................................................... 55
10.7.1. General Safety Practices .............................................................. 55
10.7.2. Earth, Sand, Gravel and Crushed Stone ............................................. 56
10.8. HITTING TOOLS ............................................................................... 56
10.8.1. Hammer. ................................................................................. 56
10.9. LEVERAGE TOOLS AND ADJUSTABLE STEEL PROPS ...................................... 56
10.9.1. Hydraulic Jack. ......................................................................... 56
10.9.2. Picks and Shovels ....................................................................... 56
10.9.3. Spanner, wrenches and pliers. ....................................................... 56
10.9.4. Screwdriver .............................................................................. 57
10.10. CUTTING TOOLS .............................................................................. 57
10.10.1. Chisels .................................................................................... 57
10.10.2. Saw ....................................................................................... 57
10.11. GENERAL SAFETY PRACTICE ................................................................ 57
10.12. FIRE FIGHTING AND PROTECTION .......................................................... 58

5|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


10.12.1. Flammable liquid ....................................................................... 58
10.12.2. Electrical appliances ................................................................... 58
10.12.3. Fire Fighting Practice .................................................................. 58
11. INSPECTION AND TESTING PLAN ................................................................. 59
12. APPENDIX ........................................................................................... 60
12.1. APPENDIX A ................................................................................... 61
12.1.1. Project Meetings ........................................................................ 61
12.2. APPENDIX B ................................................................................... 61
12.2.1. Work Schedule .......................................................................... 61
12.2.2. Materials List ............................................................................ 61
12.2.3. PME List .................................................................................. 61
12.2.4. Validation of Works .................................................................... 61
12.2.5. Traffic Management Plan .............................................................. 61
12.3. APPENDIX C ................................................................................... 62
12.3.1. Internal Forms, Checklists and Reference Documents List ....................... 62
12.4. APPENDIX D ................................................................................... 63
12.4.1. EXTERNAL FORM, CHECKLIST AND REFERENCE DOCUMENT LIST ................. 63
12.5. APPENDIX F.................................................................................... 64
12.5.1. ORGANISATION CHART ................................................................. 64

6|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

1. PROJECT POLICY
The following designations shall be issued full “controlled” copies of the Project Quality Plan.
The Project Manager may issue partial “controlled” copies of the manual as deemed required.
The issue and distribution of full or partial copies of the Project Quality Plan are controlled as
per PQP Distribution List maintained by the Project Manager. All recipients are provided with
future amendments and revisions to the manual.
Re-production of the Project Quality Plan in any form is not permitted unless so authorized by
the Project Manager. Document control procedures shall be affected for all such re-production.

NAME DESIGNATION COPY NO.


MUHAMMAD ASYRAF BIN IZMI Regional Coordinator Master
SYAHMI FIKRI BIN ZAINOORLIZA Regional Coordinator

7|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


2. PROJECT DESCRIPTION
2.1. PROJECT NAME
KERJA PEMBAIKAN CERUN MENGGUNAKAN KAEDAH “SOIL NAIL & HYDROSEEDING” DI LALUAN
FT136 SEK 35.5 JALAN KULIM-BANDAR BAHARU, KULIM, KEDAH.
2.2. SCOPE OF WORKS
The works covered by this Section is as follows: -
 Preliminaries, Data & Information Management, Slope Early Warning System &
Provisional Sum
 Preventive, Emergency & Repairing (Corrective) Works. (‘Arahan Kerja’ (AK) will be
issued by the Project Director (PPP) from time to time)

Commencement date : 31 October 2019


Completion date : 02 March 2020

2.3. PROJECT ORGANISATION


Client : Jabatan Kerja Raya Malaysia
Cawangan Kejuruteraan Cerun ,
Tingkat 12,
Ibu Pejabat Jabatan Kerja Raya Malaysia,
Jalan Sultan Salahuddin,
50582 Kuala Lumpur

Superintendent Officer : PENGARAH CAWANGAN KEJURUTERAAN CERUN JKR

Main Contractor : PINTAS UTAMA SDN BHD


No. 21 Jalan Sungai Burung W32/W Bukit Rimau, 40460
Shah Alam Selangor Darul Ehsan
Tel: 03- 51247020 Fax: 03- 51248020
Person-in-Charge: En. Lamyudi bin Harun
Designation: Project Manager

Site Representative : GPC INTEGRATED SDN. BHD.


No. 14, Jalan Sungai Burung W32/W Bukit Rimau, 40460,
Shah Alam, Selangor Darul Ehsan.

8|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


2.4. PROJECT SCOPE OF WORKS
The preliminary works as listed below:
 Site clearance
 Earthworks
 Pavement works
 Road furniture
 Geotechnical works
 Structural works
 Traffic management works

2.5. PROJECT AND CONTRACT PARTICULARS


Project Title : KERJA PEMBAIKAN CERUN MENGGUNAKAN
KAEDAH “SOIL NAIL & HYDROSEEDING” DI
LALUAN FT136 SEK 35.5 JALAN KULIM-
BANDAR BAHARU, KULIM, KEDAH.
Client : Jabatan Kerja Raya Malaysia
Main Contractor : Pintas Utama Sdn Bhd
Contract No : JKR/CKC/S27/2019/270
Contract Sum : RM 529,200.00
Date Site Possession : 31 October 2019
Date of Completion : 02 March 2020
Defect & Liability Period : 2 Years
Liquidated Ascertain Damages : Rm 99.00/Day
Performance Bond : Maybank Islamic Berhad (787435-M)
Shah Alam Trade Finance Centre, No. 10,
Level 2, Persiaran Perbandaran, Seksyen 14,
4000 Shah Alam, Selangor Darul Ehsan.

Insurance Policies : MSIG Insurance (Malaysia) Bhd.


Contractors All Risks
Policy No :
Period :
Workmen’s Compensation
Policy No :
Period :

9|Page
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


3. PROJECT ORGANISATION, AUTHORITIES AND RESPONSIBILITIES
3.1. ORGANISATION CHART
The project organization chart is as in APPENDIX F. It shall be updated when necessary.

3.2. RESPONSIBILITIES
The authority and responsibilities for each member of the project are as listed below:

3.2.1. Project Manager


Project Manager shall have the overall authority and responsibility for the execution of
the work including anticipated job quality, effective cost control and for the entire
project management towards the successful completion of the project. He shall: -

 Be the prime person who shall contact and maintain liaison with the client and
his representative on all project matters.
 Organize project team and assign responsibilities to his supporting
managers/personnel for the performance of work and verification activities.
 Establish and control the overall project budget.
 Utilize and mobilize the required services of engineering, procurement,
construction, computer services, etc.
 Conduct technical and contractual reviews to ensure that the work is being
executed in accordance with contract documents.
 Monitor and co-ordinate the engineering and procurement activities.
 Direct purchasing to ensure proper selection of materials and on timely
receipt of materials at the job site.
 Review periodically the performance of the works and subcontractors.
 Initiate necessary remedial action to maintain the project on schedule.
 Negotiate and settle all contract changes.
 Authorize and approve all works being performed by his staff in connection
with the project.
 Preparation and confirmation of Project Final Account.
 Finalizing of Contract and Variation Orders.

3.2.2. Site Engineer


Site Engineer shall have the authority and responsibilities for the execution of field
construction, job supervision and loss prevention including the site operation directly
connected with the subcontractor at the construction site. He shall: -
 Establish site organization through consultation with the Project Manager
 Take the lead of the entire site activities.
 Review the overall construction plan at initial stage.
 Report on the construction progress and any factors adversely affecting the
project to the Project Manager.

10 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 Ensure verification and inspections of site work are planned and implemented
to maintain control.
 Review and decide on actions necessary upon the identification of non-
conformance. This may include reference to other interested parties.

3.2.3. Safety Officer


The Safety Officer shall have the authority and responsibility for the Safety, Health and
Welfare of all team members at site. He shall be directly responsibilities to the Project
Manager for ensuring compliance with statutory and company requirement for Safety,
Health and Welfare at site. His responsibilities shall include: -
 Monitor, evaluate and ensure that all work is being carried out safely.
 Implement technical and safety requirements for the project.
 Review and comment on project contractor’s method statement and risk
assessment.
 Ensure that the main contractor’s Project Safety and Health Plan is being
implemented and report all non-conformance to the Project Manager.
 Regulate safety checks of all areas at the project site. The Site Safety Officer
shall immediately report to the Project Manager any activity that in his opinion
 constitutes a safety hazard and advise on adequate measures to be
implemented.
 Co-ordinate the activities of sub-contractor’s safety officers. All sub-
contractors will be required to have a named individual in their site
organization that is responsible for safety.
 Complete accident reports for all incidents requiring Hospital treatment. A
register of incidents will be maintained on site.

3.2.4. Site Safety Supervisor


The Site Safety Supervisor is responsible to the Safety Officer for ensuring compliance
with statutory and company requirement for Safety, Health and Welfare at site. His
responsibilities shall include: -
 Initiation, co-ordination and supervision of the job safety program.
 Completion of documentation and application required by statutory
requirements at work site.
 Daily safety inspection of the job site and submission of a monthly summary
report to the project manager.
 Participation at the client’s safety meeting.
 Preparation of periodic accident summaries to project managers.
 Preparation of the lost time report.
3.2.5. Land Surveyors
The Land Surveyors shall be responsible to the Senior Supervisor for all land surveying
activities relating to the project including: -

11 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 Establishing centerline or reference point of structure, offset references
points or structure and TBM (temporary bench mark) for level reference.
 Setting out and taking existing ground level prior to commencement of
earthwork.
 Plotting of as built earthwork cross-sections.
 Setting out of reference point which will define the structure, drainage line,
toe of embankment or top of cut and profiles for earthworks during the
construction stage.

3.2.6. Supervisors
The Supervisors shall be responsible for the following: -
 Supervising and controlling the direct labors and subcontractor’s work and for
completion of the respective facilities in his discipline within the planned
schedule.
 Undertaking inspection of works at appropriate stages to ensure conformance
to specification.
 Identifying and reporting any accidence of non-conformance to either
specification or system.
 Controlling any further work until the deficiency or problem has been
satisfactorily resolved.

3.2.7. Document Controller / Clerk


The Document Controller / Clerk is responsible as follows: -
 Typing reports and tender documents
 Collating project documentation
 Accurate document control for all documentation and drawings internally and
externally
 Provide general support to other teams as necessary

12 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


4. SYSTEM IMPLEMENTATION POLICIES
 Following TOR as per agreed upon discussion between PUSB and CKC, JKR
 Following Sistem Pengurusan Bersepadu (SPBI, JKR)
 Development and establish field proforma / Field Data Collection
 Conceptual Design at selected slope proposed strategy/ remedial work
 Recommendation on early slope warning system (to detect any trigger of slope
movement.)

5. QUALITY OBJECTIVES
The purpose and scope of this PQP is to address the QA procedures and monitoring
requirements throughout the construction work. The PQP intended to:
• Define the responsibilities of personnel involved in the project.
• Provide proper guidelines for the construction of major components involved in the
project.
• Establish Testing Procedures or Protocols.
• Establish guidelines for Construction Documentations.
• Provide means of assuring the project is constructed in conformance to the
Technical Specifications, Construction Drawings and Applicable Regulatory
Requirements.

13 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


6. PROCEDURE LIST
The following procedures with a tick (  ) are applicable to this project. The project team shall
refer to the Operating Procedures Manual to implement these procedures.

PROCEDURE DOC. REF. APPLICABLE


PRE-CONSTRUCTION
Project Planning and Mobilization PUSB/OPM/PRE/01 
Project Quality Plan PUSB/OPM/PRE/02 
PROJECT IMPLEMENTATION & MAINTENANCE
Site Administration PUSB/OPM/PIM/01 
Inspection and Test PUSB/OPM/PIM/03 
Calibration PUSB/OPM/PIM/04 
Maintenance and Repair of PME PUSB/OPM/PIM/04 
POST-CONSTRUCTION
Final Inspection and Project Handing Over PUSB/OPM/PIM/01 
Defects Liability PUSB/OPM/PIM/02 
Customer Satisfaction Survey PU-F12
PURCHASING
Appointment of Suppliers PUSB/OPM/PUR/01 
subcontractor PU-F01 
Performance Evaluation of Suppliers PU-F04 NA
DOCUMENTS & RECORDS CONTROL
Control of Documents and Records PUSB/PU/PO/01 

QMS DEVELOPEMNT & CONTROL


Control of QMS Documents PUSB/OPM/QDC/01 
MEASUREMENT, ANALYSIS & IMPROVEMENT
Control of Non - Conformance PU-11 
Corrective Action PUSB/OPM/MAI/02 

14 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


7. EQUIPMENT PLAN
7.1. LIST OF EQUIPMENT
No Type of Equipment Quantity
1 Generator Set 1
2 Backhoe 1
3 Concrete Mixer 1
4 Lorry 1
5 Plate Compactor – 1T 1
6 Generator Set 1
7 Welding Machine 1
8 Soil Nailing Machine 1
9 Air Compressor 1
10 Grouting Mixer 1
11 Grout Pump 1
12 Power Pack 1
13 Control Panel 1
14 Water Pump 1
15 Dumpy Level 1
16 Concrete Mixer 1

7.2. METHOD STATEMENTS LIST


The following method statements with a tick (  ) are applicable to this project. The project
team shall refer to the Method Statements Manual to implement these documents.

METHOD STATEMENT LIST


Doc. Connected to
No. Document
Ref. Procedure
1. Sistem Pengurusan Bersepadu JKR N/A
2. Term of Reference By JKR N/A

15 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


7.3. SUBCONTRACTORS’ METHOD STATEMENTS LIST
The following are approved method statements submitted by the subcontractors on this
project. The project team shall monitor the subcontractor’s works as per the approved method
statement. The method statements are maintained in the Method Statements File.

Method Statement Subcontractor Issued / Approved Date

Soil Nailing +
Hydroseeding

7.4. MACHINERIES AND EQUIPMENT MAINTENANCE PLAN

NO MACHINERY UNIT QUANTITY


1 Hydraulic Power Pack SET 1

2 Grouting Machine NO. 1

3 Air Compressor NO. 1

4 Micropile/Soil Nail Portable Drill Machine NO. 1

5 Generator Set-20 kVA NO. 1

6 Excavator NO. 1

All tools, equipment and vehicles must be properly maintained so that workers are not
endangered. Construction regulations require inspections of vehicles, tools, machines and
equipment before use.

Preventive maintenance is the systematic care and protection of tools, equipment, machines
and vehicles in order to keep them in a safe, usable condition, limit downtime and extend
productivity. We must always be aware that maintenance tasks themselves are potentially
hazardous and can result in injury. The successful maintenance program is:

 well organized and scheduled,


 controls hazards,
 defines operational procedures, and
 trains key personnel.

16 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


7.5. SCHEDULED INSPECTIONS AND MAINTENANCE
All mobile equipment is to be inspected and maintained according to the following Equipment
Inspection Schedule as a minimum. Records of all inspections and maintenance are completed
and maintained for review and approval.
Maintenance of equipment, release of lubrication fluids, etc., is performed only in approved
areas. Spills and leaks from equipment are cleaned up promptly.

Type of Equipment Type of Inspection Schedule


Complete inspection and Before put to work and
certification annually
Critical items, controls, overall
Daily
functioning

Cranes – Crawler, Safety device, hooks, cables,


Monthly
Truck, Hydraulic, etc. electrical
Complete inspection Every 3 months
Repair When failure occurs
Manufacturer’s
Preventative maintenance
recommendation
Heavy Equipment Complete inspection Before put to work
Dozers, Backhoes Complete inspection Every 3 months
Repair When failure occurs
Manufacturer’s
Compactors, Trucks Preventative maintenance
recommendation
Operator’s checklist Daily
Miscellaneous Complete inspection Before put to work
Complete inspection Every 3 months
Compressors, Welding Repair When failure occurs
Machines, Generators
Manufacturer’s
Preventative maintenance
recommendation

Slings, Shackles, Deformation, cracks, corrosion,


Daily or before each use
Chokers, Lifting etc.
Devices Regular inspections of all devices Every 3 months

17 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

8. WORK PROGRAM

18 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

9. METHOD STATEMENTS

19 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.1. SURVEY WORKS
9.1.1. Surveying Teams
One survey team with one (1) surveyor and two (2) chainman for setting out and Original
Ground Level survey. The teams will carry out offset, maintain all build out T.B.M’s by
licensed surveyor, setting out for works to progress and carrying out all joint survey
works with the Employer’s Representative.
9.1.2. Traverse Works
Licensed surveyor will use reference points given in the Drawings to carry out setting
out work. All the coordinates provided has to be checked by using nearby established
makers (T.B.M’s) on the ground that tie with other closely within error of acceptable
value.
Surveyor will plant T.B.M. and reference marker along working area and jointly
confirmed with Employer’s Representative for other setting out.
Once these T.B.M. stations and other stations that have been jointly checked and
established are correct, barricading pegs shall be installed to ensure their safekeeping.
If such stations are found to be disturbed or missing at a later date, information shall
be relayed to the Employer’s Representative.
All traverse survey shall be closed. Any closing errors shall be corrected by distribution
or otherwise. The centrelines shall then be pegged out.
After first stage clearing has been carried out, the centreline survey shall be established
to obtain a better result due to good visibility and the decrease in the number of change
points. All re-established stations shall be protected as before and set-up of cross
section will proceed as per method statement on levelling works.

9.1.3. Levelling Works


Reference shall be made to approve benchmark for transferring to the site and the
installation of permanent points at structure location for use later. Cross section of
earthworks shall be set at 20-meter interval. Works shall preferably be carried out after
general site clearance and all levelling works shall be closed after each survey day so as
to eliminate undue errors. If errors obtained from survey are acceptable, corrections
shall be made by distribution or otherwise.

9.2. SITE CLEARANCE


9.2.1. Site Clearing Method
Before site clearing commences, limit of work shall be obtained and other reference
points shown on the Drawing. All established survey markers to be protected by
barricading in red pegs and the surrounding area at established stations to be cleared
manually.

20 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


All bushes, trees, tree roots and stumps shall be disposed to approve dumping area.
Open burning shall not be permitted.
Procedures of clearing are as follows;
 The limit of works shall be pegged
 Site clearing shall then proceed
 All vegetation to be pushed down by Excavator
 All bushes and trees pushed and pile-up shall be transported to approved dumping
area using Dump Trucks
 Exposed stumps and tree roots or buried logs, bushes and undergrowth shall be
grubbed up and transported to dumping area.

9.2.2. Dumping Grounds


The location of dumping ground for unsuitable materials have been confirmed by the
Contractor and possibly encroaching into third party land on which approval will be
sought as per illustrated sketch.
9.2.3. Remove, Storage and Reinstating of Existing Guard Rail.
The works to be carried out to remove store and reinstate existing guardrail is specified
as below: -
 Remove the existing guardrails with suitable method as the clearance for access
to working platform.
 The removed guardrails shall be kept in a store.
 Reinstate the removed guardrail back to its original condition and alignment
inclusive of make good or replace all damaged guardrail components.
9.2.4. Demolition Works
Demolition and/or excavation and removal from all structures features/obstruction
within the R.O.W that cannot be cleared by bulldozer and required pneumatic tools or
other specialised equipment from site shall not limited.

9.3. EARTHWORKS
9.3.1. Excavate, Load, Haul and Deposit.
The spot level setting out shall be carried out for Original Ground Level (OGL)
A. A joint survey on the OGL shall then be carried out. The excavation level of the
embankment can be obtained with reference to the Drawings for the typical
section embankment.
B. The Employer’s Representative at site shall verify all the survey data before
actual excavation commences.
C. Bulk excavation will be carried out using Hydraulic excavators. In transverse
direction, trimming will be carried out using Back-pusher. Dump trucks will be
used to haul the cut materials to the filling area or disposed off site.

21 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


D. Hauling of material from cuttings or the importation of fill materials to the
embankments or other areas of fill shall proceed only when sufficient compaction
plant is operating at the place of deposition.
E. Generally, for cutting the operations are as follow;
 General cutting shall be from top to bottom slope
 To check the setting out for cutting prior to commencement
 Cutting of earth then commences. Excavation will be carried out in such
a way that, in case it rains, no water will be trapped. At all times the
excavated surface shall have sufficient cross fall to shed the water and
prevent pounding.
 Cutting slopes, berm heights and width shall be as per Drawing.
 Trimming of slopes using Excavator shall be carried out progressively
 All times, grades and levels of each berm shall be check and approved
before proceeding to the next

9.3.2. Removal of Unsuitable Material (Slipped Material)


Excavation of Soft / loose materials (slipped materials) shall be carried out by an
Excavator and disposed away by Licensed Trucks. This shall be carried out in
compartments at site on the actual limits of excavation. Excavation works shall precede
in stages towards the limits area as agreed upon.

22 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

Process Flowchart Description Action By

Clearing Failed Area to


Clearing Ascertain the Extent of The Contractor
Failure

Excavation Excavate loose material Contractor

Reconstruct Slope with


Reconstruct Approved Method Contractor

Carries Out Testing According Consultants/site


Testing (If Any)
to Work representative

No

Pass?

Yes

Work to Continue

23 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.4. TURFING
Areas to be turfed are all embankments fill slopes and cut slopes. The completed slopes
shall be close turfed within seven (7) days.

9.4.1. Close Turfs


Turfs shall be square in shape, 300 x 300mm and 25mm thick minimum. It shall be free
from wild grasses. Turfs will be of cow grass species that is widely used and a fast-
growing type.

9.4.2. Turf Reinforcement Matrix (TRM)


Turf shall be on soil embankment and hydro-seed. The other shall be on hydro seeded
slope surface.

9.4.3. Laying of Close Turf


The turfs will be laid in a well-bonded pattern with no gaps between the turfs. For slopes
exceeding 1 on 4, each turf will be secured with a wooden peg of at least 230mm long
driven into soil and flush with the top of the turf.

9.4.4. After Turf Care


Turf will be moved with cutting blades set at 40mm above ground. The first and
subsequent moving will be carried out when the grass reached 75 – 100mm. The grass
area will be cleared of all grass cuttings.

24 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.5. LOWER BASE
9.5.1. General
Lower Sub-base is generally the lowest of the pavement layers consisting of sand or
quarry dust, laid on the sub-grade of a pavement.
9.5.2. Materials
Prior to the laying of lower sub-base, the material shall be approved by the Engineer
and comply to standard properties of sub-base material: -
 Soaked CBR > 20
 Plasticity Index (P1) > 10
 10% Fines Value (KN) > 30kn
 Grading shall be as followed

Percentage by Weight
Sieve Size (mm)
75 37.5 10 5 600um 75um
Lower Sub Base 100 85-100 45-100 25-85 8-45 0-10

9.5.3. Laying Equipment


The following plants shall be required for the laying of lower sub-base: -
 Motor grade MG 350
 Backpusher Ford 5000
 Vibratory Roller Dynapac
 Water Tanker

9.5.4. Laying Procedures


 Works shall commence upon the approval and acceptance of the sub-grade
formation layer i.e. Approval on the levels and density of sub-grade by the
Engineer.
 LSB material shall be delivered to site by tipper trucks and spreader by motor
grader or backpusher.
 Density test shall be carried out by sand replacement method (BS 1377, Test 15B)
or other methods approved by the Engineer.

25 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.6. UPPER SUB-BASE
9.6.1. General Descriptions
Upper sub-base is commonly known as crusher run and is used in all pavement sub-base
to support surface courses.

9.6.2. Materials
Upper sub-base consists of granded crusher rock (granite or limestone). The upper sub-
base material shall conform to the standard Properties of sub-base material as follows:
 Soaked CBR > 30
 Plasticity Index > 10
 10% Fines Value > 30kn
 Grading shall be as followed

Percentage by weight
Sieve Size (mm)
75 37.5 10 5 600um 75um
Upper Sub Base 100 85-100 40-70 25-45 8-22 0-10

9.6.3. Plants/ Machineries Required


The following plants shall be required for the laying of upper sub-base: -
 Motor grade MG 350 or equivalent
 Backpusher Ford 5000 or equivalent
 Vibratory Roller Dynapac CA 25 or equivalent
 Water Tanker - Isuzu or equivalent
 Tipper Trucks – Isuzu or equivalent

9.6.4. Procedures
A. Works shall commence on site upon approval and acceptance or lower sub-base
layer.
B. Approved upper sub-base materials shall be delivered to site by tipper trucks.
C. Laying and spreading in full width of the upper sub-base material shall be carried
out by using backpusher and motor grader.
D. The moisture content of the upper sub-base materials shall be monitored and
water shall be applied using water tanker on the laid materials.
E. Compaction using vibratory roller shall commence when the moisture content is
+ 3.0% of the optimum moisture value.
F. The surface of the upper sub-base shall be finished to the grade and line as
required by the Drawings.
G. On completion of laying and compacting, joint survey and in-situ density
measurement shall be conducted to check for compliance with the specified
requirement.
H. Trial compaction shall be carried out to assess the suitability of the compaction
plant and to establish the rolling pattern required to achieve the specified
compaction requirement.

26 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


I. Compaction shall be carried out using Vibratory Roller Dynapac CA 25 or
equivalent. In order to achieve the specified compacted density, compaction
using the vibratory roller as specified / equivalent shall commence only when
the moisture content of the upper sub-base materials lies within + 3.0% of the
optimum moisture value as determined in accordance with BS 1377 test 13.
J. The rolling pattern applied shall be vibratory passes for compacted thickness of
15mm of as per specification.

9.6.5. Site Records


The contractor shall provide competent personnel to supervise the overall work and
furnish the following records to the Engineer each week: -
 Date of laying
 Weather

9.7. ASPHALTIC CONCRETE BINDER COURSE


9.7.1. General
The asphaltic concrete binder course is the premix layer supporting the asphaltic
wearing course.
9.7.2. Material
ACBC consists of aggregate, quary dust, bitumen and filter or Portland cement.
8.7.2.1. Material Quality Requirements
 Gradation : As per Job Standard Mixture
 Binder Content : As per Job Standard Mixture
 Stability : > 550 kg
 Void in total mixture : As per Job Standard Mixture
 Void filled with binder : As per Job Standard Mixture
 Stiffness : > 270 kg
 Flow : 2.0 mm – 1.0 mm
The aggregate shall be surface dry and mixed at an approximate
temperature. The mix material as delivered to the laying site shall be
between 120 C to 160 C.

9.7.3. Equipment
Plant required to produce ACBC shall be:
 Premix Plant - Linhoff or equivalent (250t/hr)
 Wheel loader - Caterpillar 950 F
 Weigh bridge
Machineries required for laying ACBC:

 Tipper Trucks - Isuzu 10 wheeler or equivalent


 Asphalt Paver - Titan 411 or equivalent

27 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 Pneumatic Tyred Roller - Dynapac WP 20 or equivalent
 Tanden Roller - Dynapac CC21 or equivalent
 Bitumen Distributor - Technics or equivalent
9.7.4. Procedure
A. Trial mix and trial lay shall be carried out to determine the job mix standard
and the compaction pattern.
B. Works shall commence on site upon approval and acceptance of the dense
bituminous macadam layer.
C. The surface to receive the asphaltic concrete base course shall be freed of all
dirt, loose materials and standing water by sweeping.
D. Tack coat of approved bitumen emulsion shall be applied as per Specifications
on the prepared surface prior to laying of the asphaltic concrete base course.
E. The asphaltic concrete base course shall be plant-mixed (Paving Plant &
Processes Continuous Drum Mixer) with bitumen content as established in the
Job Standard Mixture.
F. The approved asphaltic concrete base course shall be delivered to site by tipper
trucks. To prevent the loss of beat, the mixture shall be covered by tarpaulin.
G. The asphaltic concrete base course shall be laid by ABC Tital 411 paver or
equivalent in single layer and in 2 runs.
H. If the laid surface is open-textured, backcasting shall be carried out and the
bigger size aggregates removed before rolling.
I. At the end of the paving operation, the transverse joint shall be feathered
down. Vertical joint shall be provided for the next operation of paving.
J. Compaction shall be carried out using the specified/equivalent type of
compactors and the rolling pattern shall be as per established during the trial
lay.
K. Rolling shall always commence from the lower to the higher side of the
carriageway. The minimum rolling temperature shall be 120 C.
L. The surface of the asphaltic concrete base course shall be finished to the grade
and line as required by the Drawings.
M. On completion of laying and compaction, joint survey shall be carried out to
check for compliance with the specified requirement.

28 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.8. ASPHALTIC CONCRETE WEARING COURSE
9.8.1. General Description
The wearing course is the final layer of the pavement.
9.8.2. Materials
The material quality shall meet the following requirements:

 Gradation : As per Job standard mixture


 Binder Content : As per Job standard mixture
 Stability : > 550 kg
 Void in total mixture : As per Job standard mixture
 Void fill with binder : As per Job standard mixture
 Stiffness : > 270 kg
 Flow : 2.0 mm – 4.0 mm
The aggregate shall be surface dry and shall be mixed at an appropriate temperature.
The mix material as delivered to the laying site shall be between 120C to 160C.

9.8.3. Equipment
Plant required to produce ACWC shall be:

 Premix Plant - Linhoff or equivalent (250t/hr)


 Wheel loader - Caterpillar 950 F
 Weigh bridge
Machineries required for laying ACWC:

 Tipper Trucks - Isuzu 10-wheeler or equivalent


 Asphalt Paver - Titan 411 or equivalent
 Pneumatic Tyred Roller - Dynapac WP 20 or equivalent
 Tandem Roller - Dynapac CC21 or equivalent
 Bitumen Distributor - Technics or equivalent

9.8.4. Procedure
A. Trial mix and Trial lay shall be carried out to assess the suitability of the
mixing, laying and compacting plant and to establish the sequence of the laying
operation.
B. Works shall commence on site upon approval and acceptance of the asphaltic
concrete wearing course.
C. The sampling of the mixture shall be carried out twice a day at the plant to
determine the gradation, binder content and the Marshall Properties.
D. The surface to receive the asphaltic concrete wearing course shall be freed of
all dirt, loose materials and standing water by sweeping.
E. Tack coat of approved bitumen emulsion shall be applied as per Specifications
on the prepared surface prior to laying of the asphaltic concrete wearing
course.

29 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


F. The asphaltic concrete wearing course shall be plant-mixed (Paving Plant &
Process Continuous Drum Mixer) with bitumen content as established in the Job
Standard Mixture.
G. The approved asphaltic concrete wearing course shall be delivered to site by
tipper trucks. To prevent the loss of heat, the mixture shall be covered by
tarpaulin.
H. The asphaltic concrete wearing course shall be laid by ABG. Titan 411 paver or
equivalent in single layer and in 2 runs.
I. If the laid surface is open-textures, backcasting shall be carried out and the
bigger size aggregates removed before rolling.
J. At the end of the paving operation, the transverse joint shall be feathered
down. Vertical joint shall be provided for the next operation of paving.
K. Compaction shall be carried out using the specified/equivalent type of
compactors and the rolling pattern shall be as per established during the trial
lay.
L. Rolling shall always commence from the lower to the higher side of the
carriageway. The minimum rolling temperature shall be 120 0C.
M. The surface of the asphaltic concrete wearing course shall be finished to the
grade and line as required by the Drawings.
N. On completion of laying and compaction, joint survey shall be carried out to
check for compliance with the specified requirement.

9.9. ASPHALTIC CONCRETE WEARING COURSE


9.9.1. Pull Out Test
9.9.1.1. Introduction
The pull-out test is intended to investigate the geotechnical capacity of the soil
nail or rock bolt design to demonstrate their behaviour and performance and also
to confirm the quality and adequacy of the design.
Basically, this write-up description the proposed method statement for the pull-
out test on soil nail or rock bolt is method based on BS8081 1981.
9.9.1.2. Setting Up of Pull-Out Test
 Proposed setting-up of the pull-out test assembly.
9.9.1.3. Loading Sequence
 The proposed loading sequence shall be applied incrementally as
specified by the Engineers.
9.9.1.4. Test Cycle
 Three cycles for preliminary pull-out test and two cycles for working pull-
out test.
9.9.1.5. Preparation
 Before the testing, the non-shrink grout of the test nail must be at least
achieved the compressive strength of 30MPa.
 The grout compressive cube test results shall be submitted to the
Engineer for review prior to the test.

30 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.9.1.6. Measurement of Displacement
 The actual displacement of the soil nail or rock bolt shall be measured by
minimum 4 nos. of dial gauge, reading to the nearest 0.01mm.
 Two (2) dial gauges to measure the soil nail head displacement and the
other two (2) dial gauges to be placed at the independent reference
beam.
 Independent reference beam legs shall be firmly installed with minimum
distance 1m away from the soil nail position and/or outside the seating
base.
9.9.1.7. Measurement of Applied Load
 The applied load to the soil nail or rock bolt shall be by a centre hole
single cylinder or centre hole double cylinder and applied by hydraulic.
 The load indicator shall be calibrated.
 Displacement indicator shall calibrate Dial Gauge with criterion with
read-able to 0.01mm.
 The test load shall be monitored with a load cell as the primary device
and a pressure gauge as the secondary device.
 The loading apparatus shall be set up in such a way that no loading, other
than the pull-out load, acts on the steel bar at the nail head.
 The steel plate (bearing plate) provided shall be placed against an even
temporary cut bearing surface which shall be normal to the alignment of
the steel bar to ensure adequate load distribution and avoid eccentric
loading during pull-out testing.
 The applied load must be perpendicular to the soil nail.
 A minimum free length/ungrouted zone of 1m in length to the face shall
be provided, or as directed by the Engineer.
 Throughout the test, the soil nail movement versus the applied load shall
be measured, plotted on a graph and recorded along with all other
relevant information. All the results shall be submitted to the Engineer
within 3 days of completion of the test.
9.9.1.8. Terminate Test
 The loading shall be terminated at failure or at least 3 times the design
unit bond stress for the preliminary pull-out test and at least 1.5 times
the designed nail load for the working pull-out test.
 For safety reasons, all nails shall not be stressed beyond 0.8 times the
characteristic strength of the nail reinforcement (180kN).
9.9.1.9. Test Procedure
A. Prepare the surface of the test area to be carried out.
B. Applied extension coupling to the Test-Bar if it is too short.
C. Setting the Load Plate and Angle Plate properly.
D. Setting up the reference beam and fitting 4 nos. of measurement dial
gauge on the plate.
E. Fitting the hollow cylinder (Hydraulic Jack Cylinder).
F. Put the hollow Load Cell which throughout the Test-Bar.

31 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


G. At the end of Test-Bar placed in hollow plate setting properly and lock
the nut tight.
H. Setting up the reference beam and fitting 3 nos. of measurement Dial
Gauge on the plate of item 6.
I. Applied some force to make sure whole setting is firm, then release the
force. The alignment load (AL) should be the minimum load required to
align the testing apparatus and should not exceed 5% of the design test
load.
J. Commencing the test based on sequence below.
K. Termination of test shall refer item (9) above.

32 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

PROCESS FLOW CHART DESCRIPTION ACTION BY

Completion of activity before


Slope rectification work Contractor
testing

Testing carried out in presence


Testing Contractor
of Consultant

SO Representative and review of Consultants/Site


Result
the test result Representative

No

Approve

Yes

Contractor to proceed to next


Work to continue
activities

33 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.10. SOIL NAIL WORKS
9.10.1. Soil Nailing
9.10.1.1. Preparation and Setting Out
 The Earthwork Contractor shall only carry out trimming/excavation works
prior to the soil nail drilling work. Furthermore, the Earthwork Contractor
shall not trim/excavate the slope and allow the slope to deteriorate/fail
without installing the soil nail works.
 Setting out the positioning of Soil Nail and marked on site at the specified
location as per Consulting Engineer’s Drawings.
 The installation of Soil Nail including drilling, installation and stressing
shall be carried out in accordance with the Consulting Engineer’s
Specification.
 An exposed slope shall be covered with plastic sheet or canvas for
temporary protection from weather or unexpected event.
9.10.1.2. Fabrication of soil nail bar
 A galvanised high yield deformed steel bar (according to specification)
shall be used. The length of the steel bar shall be single length as
specified.
 Approved UPVC pipe centralizers shall be installed 1.5m spacing
throughout the length of the soil nail bar.
9.10.1.3. Drilling of borehole
 Portable Drill Rig with temporary staging or firm working platform and
drag bit shall be used.
 The grid position of Soil Nail shall be marked on the existing slope once
the working platform has been prepared.
 Position drilling machine on the setting out point marked on site with
specified inclination and drill 125mm diameter borehole to the depth
required.
 Down the hole hammer shall be used if rock / hard material is
encountered.
 Once the predetermined depth is reached the drill hole shall be flushed
clean using compressed air and drill rods retrieved & drilling rig shall be
shifted to the next location.
 Upon completion the hole, a 12mm galvanized high yield deformed steel
bar with threaded at the exposed end and for a sufficient length to
facilitate fixing of nuts and shall be inserted with the pre-drill hole.
 Upon completion of drilling and installation of reinforcement, grouting
has to commence as soon as possible.
 Before lowering of the steel bar and grouting, the hole shall be flushed
clean by means of compressed air to remove any standing water.

34 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.10.1.4. Grouting of Borehole
 Grouting operation shall be in accordance with Section 10.4 BS 8081
(1989).
 The cube test result for trial mix shall be submitted before start work.
No grouting works is allowed prior to approval on the cube test results of
trial mix by the Engineer.
 The proportions of grout and the minimum strength of work cubes shall
comply with following requirements: -
 Range of water/ cement ratio 0.45 cube strength
 7 days (N/mm²) – 20
 28 days (N/mm²) – 30
 The quantities of cement in the mix shall be measured by weight in an
approve weight batching or as per bag.
 The drill hole shall be grouted on the same day as drilling except where
otherwise agreed by Engineer. Grouting shall be placed by tremie under
gravity or very low excess pressure shall continue until injected grout of
the same composition and consistency as that mixed emerges from the
outlet for at least one minute.
 The frequency of the cube test shall be minimum 1 set for every mixing
batch (minimum six (6) nos. cubes per set with minimum two (2) nos.
tested at age of seven (7) days and minimum two (2) nos. at age of 28
days). The nos. of tests shall be carried out according to nos. of mixing
batch.

35 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

PROCESS FLOW CHART DESCRIPTION ACTION BY

Consultant Rep. Indentified Consultant


Setting out for Soil Nail Point
specific location/Point

Standby galvanized end


Fabrication of Soil Nail Bar Contractor
treated/bend high tensile bar

Drill 100mm diameter hole


Drilling of Borehole Contractor
using soil nail machine

Quality test –
 Trial mix for cement
grout Consultants/Site
Grouting of Borehole
 Prepare cement grout Representative
cube for Compressive
test

Lock steel plate with nut / tie


Consultants/Site
Inspection/Testing inside RC wall reinforcement
Representative
bar & inspection by Consultant

36 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.11. GUNITING WORKS
9.11.1. Guniting
9.11.1.1. Description
 This guniting process is a dry mix process.
 Minimum cement content shall be 350kg/m3. A trial mix shall be carried
out on the test panel and the result of core samples from test panel shall
be submitted for Consultant’s review and approval before the
commencement works. Minimum six (6) core samples (minimum 76mm
diameter) from each panel shall be collected for testing as per approved
specification.
9.11.1.2. Strength of Gunite Concrete
 Gunite concrete grade 30
 1 : 1.5 (cement / sand mixed proportion base in volume)
9.11.2. Procedure
A. All surface roots, vegetation and loose materials shall be trimmed, cut
and removed.
B. Use high water pressure jet to clean surface follow by compressed air to
dry the surface.
C. An exposed slope shall be covered with plastic sheet or canvas for
temporary protection from weather or unexpected event.
D. Install a single layer of BRC A6 mesh reinforcement on the designation
slope location.
E. Prior to guniting, 80mm diameter UPVC weep holes shall be installed at
predetermined location and secured to the wire mesh using tie wires, the
embedded end of the UPVC pipe shall be wrapped around with geotextile
Polyfelt TS20 sheet (or equivalent) and the exposed end which will
eventually be protruding out of the finished gunite face shall be wrapped
with plastic to prevent ingression of gunite mix during guniting.
F. The plastic wrapping shall later be removed upon completion of guniting.
G. By using 1: 1.5 mixed proportion base on volume to mix the cement and
sand to either the Gunite Machine and conveyed by compressed air with
delivery hose.
H. Water supply shall be discharged through the nozzle from a water pump
to form a wet mix at the nozzle. The nozzleman shall control the water
for the mix supply at the nozzle.
I. Gunite mix shall be sprayed onto the cleaned surface in circular motion
until 100mm minimum thickness guniting is achieved.
J. The nozzle shall be always directed perpendicular to the surface from
about 1-2m away.
K. The sequence of guniting shall be from the top to the bottom of the slope
(bottom up direction) for every stage, not to spray from top to the
bottom. This is to prevent accumulation from bound of shotcrete at the
bottom and also stacking up of fresh shotcrete over the early sprayed
shotcrete.

37 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

PROCESS FLOW CHART DESCRIPTION ACTION BY

Prepare clear slope surface


Consultants/Site
from roots, vegetation and Consultant Rep. inspect
Representative
loose

Install BRC mesh As per drawings 2 layers A6


Contractor
reinforcement with dowel bar

As per drawings 75mm dia.


Install UPVC weep holes UPVC/PVC pipe wrapped with Contractor
Geotextile

1:1.5 mixed proportion base Measurement for the proportion


Contractor
(cement & Sand) ratio (cement & Sand)

Random check for the thickness Consultants/Site


Sprayed 100mm Thk. Guniting
of guniting Representative

Coring and panel test if Consultants/Site


Inspection/Test
required Representative

38 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.12. CONCRETE WORKS
9.12.1. Special Requirements
 Standard
 Unless otherwise stipulated all concrete works and material shall comply
with the recommendations contained in the BS 8110: Part 1 – 3, 1985
“Structure Use of Concrete”. However, CP114 shall be referred to when
required by the Superintending Officer.
9.12.2. Uniformity of Color
 In order to ensure uniformity of color, it is important that all constituent
material of the concrete, i.e. cement, fine and coarse aggregates,
originate from one approved source throughout the Contract. Preliminary
trial and batch mixes shall be made ascertain the best grading in
uniformity of color and surface finish.
9.12.3. Steel Reinforcement

9.12.3.1. Mild Steel


 All reinforcing bars, unless otherwise specified shall be plain round mild
steel bars complying with BS 4449.
9.12.3.2. High Yield Steel
 High yield steel reinforcing bars shall comply with BS 4449.
9.12.3.3. Reinforcement Fabric
 Steel reinforcement fabric shall comply with BS 4483. Fabric shall be
delivered to site in flat sheets and shall at no time be rolled.
9.12.3.4. Tests Certificates
 Manufacturer’s test certificates for the Contractor as shall produce the
steel and when required by the Engineer or his Representative.
9.12.3.5. Further Tests
 Notwithstanding the production of manufacturer’s test certificate, the
Engineer or his Representative shall have the right to require such further
tests, as he may necessary, to be carried out by an approved laboratory
and at the Contractor’s expense.
9.12.3.6. Storage
 All steel reinforcement shall be kept clean and under cover until it is
required to be used in the works.
9.12.3.7. Binding Wire
 The binding wire for steel reinforcement shall be 16 SWG soft pliable
annealed steel wire.

39 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.12.3.8. Bar Bending Schedules
 The Contractor shall prepare bar bending schedules with calculated
weights for the reinforcement shown on the drawings and shall submit
these schedules in triplicate for the approval of the Engineer before bar
cutting and bending commences. Any approval so given shall not relive
the Contractor of his responsibility for the correct fixing of all
reinforcement in accordance with the drawings and specifications.
9.12.3.9. Fixing
 The reinforcement shall be fixed in the formwork and held form against
displacement by approved cover blocks and binding wires to ensures that
the meshwork or reinforcing bars will retain their designed from and
exact position in the formwork during the process of depositing and
consolidating the concrete. Bars intending to be in contact when passing
each other shall be securely held together intersections with binding
wires. Binders and stirrups shall tightly embrace the longitudinal
reinforcement to which that shall be securely wired.
 Any reinforcement, which is out of level line or placed by more than 6mm
of that specified shall be taken up and refixed at the Contractor’s
expense to the satisfaction of the Engineer. The ends of all tying wires
shall be turned into the body of the concrete and not allowed to project
towards the surface of the concrete. Precast concrete cover blocks, mild
steel distance or spacer pieces and stools or other permanent supports
shall be provided by the Contractor at mo additional charge.
 During concreting a competent steel fixer shall be in attendance on the
works to adjust the correct position of the reinforcement immediately
prior to the placing of the concrete and throughout the duration of the
concreting.
9.12.3.10. Laps
 Laps length of the reinforcing bars shall be calculated on the permissible
stresses given in BS 8110:1985 for the full tensile stresses in the bars but
no increase for wind be permitted. Laps in the reinforcement shall be
suitably staggered.
9.12.4. Mix Design And Proportioning
9.12.4.1. Grades of Concrete
The various of concrete to be used in the Works shall be as specified or shown
on the Drawings and shall have properties as set out in table below.

40 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


Concrete Characteristic Strength of Cement/cu.m of Concrete Maximum
Grade Works Cubes placed kg Aggregate
(N/mm2) 7 Days 28 Days Max Min Size (mm)
(20)
30 (40) 27 40 420 360 20
30 (20) 20 40 390 340 40
25(40) 20 30 390 340 20
25(20) 17 25 360 320 40
20 (20) 17 25 360 320 20
15 (40) 13.5 20 330 270 20
15 (20) 10 15 - 180 40
10 15 - 200 20

Notes:
 Cement content is weight of cement on Kg. to produces approximately
one cubic meter of fully compacted concrete.
 Cube strength at 7 days is provided for assisting production control and
not to be used for compliance test.

9.12.5. Workability
 The concrete shall be of such consistency that it can be readily worked
into the corners and angles of the formwork and around reinforcement
without segregation of the materials or bleeding of free water at the
surface. Striking the formwork, it shall present a face, which is uniform
free from honey-combing, surface crazing, or excessive dusting and which
neither shall nor, in the opinion of the Engineer, be interior to the
standard referred to below.
 In order to satisfy the Engineer that the workability of the proposed mixes
is adequate for the requirements of the specifications, the Contractor
shall carry out a series or workability tests on the preliminary trial mixes,
as stated earlier in this specification. These tests shall be carried out in
accordance with BS 1881, or the Engineer may approve such other
procedure as. The samples to be tested shall be obtained from the
batches used for the preliminary test cubes.
 In addition, the Contractor shall supply for the various grades of concrete
and each of the finished defined in this specification, a section or
formwork complete with reinforcement fixed in position and generally
representative of the sections commonly to be employed on the works.

41 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


The capacity of this trial section of formwork shall be at least half a batch
of concrete, but in any case, less than 0.25 cu.m. (8cu.ft) the formwork
shall comply with the requirements as defined in this specification. The
mould shall be filled in the presence of the Engineer or his Representative
with concrete of the same mix and batch from which the preliminary test
cubes are made and shall be compacted in the same manner and with the
same equipment as proposed for the works. This procedure shall, be
repeated with modified mixes until the appearance of concrete after
removing the mould is acceptable to the Engineer or his Representative
after which it shall be used as the standard for that class and finish.

9.12.6. Sampling And Testing


9.12.6.1. Works Cube Test Procedure
A. Samples of concrete for tests shall be taken a cube made, as and when
directed by the Engineer.
B. Normally for each class on concrete, 8 cubes shall be made for each 15
cu.m of concrete, or part thereof in each day’s work. This number of
cubes may be reduced if consistently satisfactory results are obtained or
increased up to a maximum of 16 when in the opinion of the Engineer or
his Representative; additional tests are required as for example in the
early stages of the works.
C. Test cubes shall be made, cured and stored under the same conditions as
the works to which they relate and shall be transported and tested in
compression in accordance with BS 1881. The tests shall be carried out in
a laboratory approved by the Engineer. Reports of all tests shall be
supplied to the Engineer or his Representative within 24 hours of the
cubes being tested.
D. Every test cube shall be clearly and permanently marked with its code
number and date of casting together with an indication of the part of the
works to which it relates. The Engineer or his Representative shall decide
the system of identifying and marking the cubes.
E. A record of such tests identifying the test cubes with the part of the work
executed shall be kept on the site and made available to the Engineer or
his Representative on request.
F. Concreting may not proceed until satisfactory arrangements have been
made to comply with the requirement of the Clause.
9.12.6.2. Test for Consistency
 The workability of the concrete shall be measured by tests, carried out
in a standard ‘Compacting Factor’ apparatus, describe in Part 3 BS 1881,
The results of the tests shall not exceed 0.92. Initial tests shall be made
using samples obtained from the batches used in casting of the test cubes
for the trial mixes. Tests shall also be carried at the discretion of the
Engineer on concrete used in the works to check that the mixes
determined during the initial tests are continuing to satisfy the
requirements of the specification.

42 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 The slump test on concrete shall be in accordance with BS 1881 and shall
be subject to the Engineer’s approval according to the results for the trial
mixes with reference to the grade of concrete and the purpose for which
it may be used.
 The tests shall be carried out in pairs and the average values computed.
9.12.6.3. Standard of Acceptance of Works Cubes
 Compression test shall be carried out on 150mm cubes all as stated earlier
in this specification. Each cube shall be made from a single sample taken
from a randomly selected batch at the point discharge from the mixer,
or, in the case of ready mixed concrete, at the point of discharge from
the delivery vehicles.
 Compliance with the specified strength of each class of concrete may be
assumed if the Engineer is satisfied that:

A. The average strength determined from any group of four consecutive


test cubes exceeds the specified cube strength by not less than 7.5
N/mm2 if it can be established that the standard deviation of cube
test on at least 40 separate batches of concrete of nominally similar
proportions of similar materials and produced by the same plant under
similar supervision is not greater than 3 N/mm2; and
B. Each individual test result is greater than 85% of the specified cube
strength.

 If only one cube results fail to meet the second requirement then that
result may be considered to represent only the particular batch of
concrete from which that cube was taken provided the average strength
of the group satisfies the first requirement. If the average strength of any
group of four consecutive test cubes fails to meet the first requirement
then all the concrete in all the batches represented in all such cubes,
including those not actually tested and those for which test results
exceed the specified cube strength, shall be deemed not to comply with
the strength requirements.
9.12.6.4. Testing Laboratory
 The Contractor may with the Engineer’s approval arrange to have testing
of concrete test cubes and other material carried out by a properly
qualified independent testing organization which the Contractor proposes
to employ shall be submitted for the Engineer’s approval prior to the
performances of any tests and good time to allow the Engineer to consider
the Contractor’s proposal.
9.12.6.5. Record
 Record shall be kept by the Contractor of the positions on the works of
all batches of concrete of their classes, and of all test cubes, cores or
other specimen to be taken from them. Copies of these records shall be
supplied to the Engineer.

43 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.12.6.6. Placing
 The concrete shall be placed in position and sequence indicated on the
Drawings, in the Specifications or as directed by the Engineer. It shall be
deposited as nearly as possible in its final position, working from the stop
end, if any. It shall be placed in such manner as to avoid segregation of
the concrete or displacement of the reinforcement other embedded
items, or formwork.
 The concrete shall not be placed against in-situ concrete, which has been
in position for more than 30 minutes unless a construction joint has been
formed.
9.12.6.7. Use of Chutes
 Where chutes are used to convey the concrete, their slopes shall not be
such to cause segregation, and suitable spouts or baffles shall be provided
to obviate segregation during discharge. Concrete shall not be allowed to
fall freely more than 1.5m unless through an approved chute. The use of
aluminium for chutes is prohibited.

9.12.7. Formwork and Surface Finish


9.12.7.1. General
 The Contractor shall be entirely responsible for the sufficiency of the
formwork and also for the safe removal of the same. Before commencing
the works, he shall submit for the approval of the Engineer details of the
formwork he proposes to use, but such approval shall in no way relieve
him of any of his responsibility for the sufficiency and efficiency of the
formwork and that it will be restraint to the strains imposed on it when
the concrete is vibrated and that is lined as may be necessary to provide
the desired concrete surface finished.
9.12.7.2. Treatment
 To prevent concrete from adhering to the formwork the surface against
which the concrete is to the deposited shall, before the placing of
concrete receive a thin coat approved mould oil or other approved
material. Care shall be taken to keep any steel reinforcement or any item
to be built into the concrete free from any such coating material. The
rates for shuttering shall be inclusive of this coating.

44 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.13. DRAINAGE WORKS
9.13.1. General
 Storm water drainage works shall comprise all surface drains for building,
roadside drain, main drainage system, culverts, sumps and subsoil drains.
9.13.2. Excavation
 The contractor shall erect sign sight rails and provide boring rods checking
of excavation depths and gradient and shall give assistances to the
Architect for the checking.
9.13.3. Concrete Beds
 All precast concrete units shall be laid on compacted concrete beds
constructed with (1:3:6) concrete with grader aggregates of maximum
size of 25mm.
 Unless otherwise stated in the Contract Drawings all concrete beds shall
be not less than 150mm thick and laid to the full widths as shown in the
drawings.
 The beds shall be reinforced where shown in the drawing or as directed
by the Architect.

9.13.4. Laying of Drain and Culverts


 Precast concrete drains and culverts shall be laid true to line, depths and
even gradients.
 The sides of precast concrete drains up to the top of for culverts to the
level passing through the center of the pipe shall be filled with (1:3:6)
concrete and well compacted.
 Branches to pipes or concrete surround shall be formed as shown in the
drawing.
 All joints shall be fully filled with freshly mixed (1:3) cement and sand
mortar and neatly pointed.
9.14. GRID BEAM
9.14.1. Setting Out
 Carry out setting out of the site by qualified surveyor based on the
engineering drawing made available inclusive of ROW pegging (if
necessary)
9.14.2. Site Clearing
 Clearing, grubbing, trees cutting, stripping of topsoil etc.
 Removal of loose failed material.
 Removal material shall be transported using dump truck to the agreed
disposal areas.

45 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.14.3. Installation of Soil Nail
A. Mark soil nail points on the slope surface.
B. The spacing between soil nails are specified in the drawings.
C. Install temporary staging on the slope.
D. Fix portable drill machine onto the temporary platform.
E. Start drilling on the first hole. The hole is tilted about 10° downwards.
F. Start drilling using soil nail drilling machine. Down-the-hole hammer
(DTH) with Ø100mm drill bit is used for drilling. Air compressor is used to
provide high pressure air for the purpose of running the DTH and for the
flushing out debris from the hole.
G. Prefabricate galvanised T25, 6m bar by inserting into Ø50mm corrugated
HDPE pipe.
H. Insert the prefabricated reinforcement into the drill hole.
I. Mix cement and water in the grout mixer for about 5 minutes. The
water/cement ratio is between 0.45 – 0.5 to create grade 25 grout.
J. The grout is pumped into the hole until it is filled with grout. The grouting
is stopped when fresh grout is observed coming out from the hole.
K. The process is repeated until all soil nails are completely installed.
9.14.4. Installation of Pre-Cast Grid Beam
A. The position of soil nails is designed in such a way that the distance
between each of them is 1.75m in any direction.
B. The precast grid beams are placed between the soil nails. The exposed
reinforcements of the grid beams are attached together surrounding the
protruding end of T25 bar of soil nail.
C. Using site mix, concrete grade 20 is then poured into the nail head to
encase and bind the reinforcements and T25 of soil nail.
D. 125mm x 125mm x 10mm thick galvanised mild steel plate is then tied to
the T25 end (which is threaded) using galvanized nut.
E. Some wet concrete is filled into the precast concrete cap and then fixed
to the nail head as cover and to look tidy and nice.
F. When all the grid beams are fixed and capped to the soil nails, some soil
is placed between the grid beams and then covered with close turfing.
9.14.5. Inspection and Test Plan
 The relevant inspection and tests to be carried out on the project are
outlined in the inspection and test plan. The project team shall
implement the inspection and test plan. The inspection and test plan shall
be used in concurrence with the project specifications, standards,
drawings and instructions with JKR regulation.

46 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


9.15. CASCADE DRAIN
9.15.1. Setting out
 Setting out location for cascade drain will be carrying out as shown on
the Drawing.
 Cascade drain position will be marked with suitable identifiable pegs or
markers on the slope for necessary inspection by Client.
 The position and length of cascade drain will be according to the drawing.
9.15.2. Slope Preparation
 This slope surface shall be trimmed locally if necessary when there is
vegetation or lose material at the cascade drain position.
9.15.3. Cascade Drain
 Drain shall be excavated besides the shoulder drain at interval specified
by the Engineer. The width and depth shall be as specified in the drawing.
 Gradient of excavation is checked against the requirement. Upon
approval from the Engineer, lean concrete at thickness of 50mm is laid
along the drain.
 Followed with the installation BRC A8 (or as otherwise specified) on the
lean concrete. Spacer block are used to ensure required thickness of
50mm is achieved concrete grade 25/20 is used. Construct 450mm x
600mm reinforced concrete cascade drain.
 Formwork is set-up for drain walls and concrete is poured into the
formwork.
 The concrete is let to cure for at least 2 days prior to dismantling of the
formwork.
 The construction shall be based on requirement imposed as per drawing.

47 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

10. RISK MANAGEMENT PLAN

48 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


10.1. INTRODUCTION
A risk is an event or condition that, if it occurs, could have a positive or negative effect
on a project’s objectives. Risk Management is the process of identifying, assessing,
responding to, monitoring, and reporting risks. This Risk Management Plan defines how
risks associated with the project KERJA PEMBAIKAN CERUN MENGGUNAKAN KAEDAH
‘TIE BACK WALL’ DI LALUAN FT004 SEKSYEN 81.80, JALAN KULIM-BALIK-GRIK,
BALING, KEDAH will be identified, analyzed, and managed.
It outlines how risk management activities will be performed, recorded, and monitored
throughout the lifecycle of the project and provides templates and practices for
recording and prioritizing risks. The Risk Management Plan is created by the project
manager in the Planning Phase. The intended audience of this document is the project
team, project sponsor and management.
10.2. RISK MANAGEMENT PROCEDURE
10.2.1. Process
 The project manager working with the project team and project sponsors
will ensure that risks are actively identified, analyzed, and managed
throughout the life of the project. Risks will be identified as early as
possible in the project so as to minimize their impact. The steps for
accomplishing this are outlined in the following sections. The project
manager will serve as the Risk Manager for this project.
10.2.2. Risk Identification
 Risk identification will involve the project team, appropriate
stakeholders, and will include an evaluation of environmental factors,
organizational culture and the project management plan including the
project scope. Careful attention will be given to the project deliverables,
assumptions, constraints, WBS, cost/effort estimates, resource plan, and
other key project documents. A Risk Management Log will be generated
and updated as needed and will be updated as required.
10.2.3. Risk Analysis
 All risks identified will be assessed to identify the range of possible
project outcomes. Qualification will be used to determine which risks
are the top risks to pursue and respond to and which risks can be ignored.
10.2.4. Qualitative Risk Analysis
 The probability and impact of occurrence for each identified risk will be
assessed by the project manager, with input from the project team using
the following approach:
a) Probability
 High – Greater than <70%> probability of occurrence
 Medium – Between <30%> and <70%> probability of
occurrence
 Low – Below <30%> probability of occurrence

49 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


b) Impact
H  High – Risk that has the potential to greatly impact project
cost, project schedule or performance
M  Medium – Risk that has the potential to slightly impact
L project cost, project schedule or performance
Impact

 Low – Risk that has relatively little impact on cost,


L M H schedule or performance
 Risks that fall within the RED and YELLOW zones will have
Probability risk response planning which may include both risk
mitigation and a risk contingency plan.
10.2.5. Quantitative Risk Analysis
 Analysis of risk events that have been prioritized using the qualitative risk
analysis process and their affect on project activities will be estimated,
a numerical rating applied to each risk based on this analysis, and then
documented in this section of the risk management plan.
10.3. RISK RESPONSE PLANNING
 Each major risk (those falling in the Red & Yellow zones) will be assigned to a
project team member for monitoring purposes to ensure that the risk will not
“fall through the cracks”.
 For each major risk, one of the following approaches will be selected to address
it:
o Avoid – eliminate the threat by eliminating the cause
o Mitigate – Identify ways to reduce the probability or the impact of the
risk
o Accept – Nothing will be done
o Transfer – Make another party responsible for the risk (buy insurance,
outsourcing, etc.)
 For each risk that will be mitigated, the project team will identify ways to
prevent the risk from occurring or reduce its impact or probability of occurring.
This may include prototyping, adding tasks to the project schedule, adding
resources, etc.
 For each major risk that is to be mitigated or that is accepted, a course of action
will be outlined for the event that the risk does materialize in order to minimize
its impact.
 The level of risk on a project will be tracked, monitored and reported throughout
the project lifecycle.
 A “Top 10 Risk List” will be maintained by the project team and will be reported
as a component of the project status reporting process for this project.
 All project change requests will be analyzed for their possible impact to the
project risks.
 Management will be notified of important changes to risk status as a component
to the Executive Project Status Report.

50 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


10.4. TOOLS AND PRACTICES
 A Risk Log will be maintained by the project manager and will be reviewed as a
standing agenda item for project team meetings.
10.5. GENERAL SAFETY REQUIREMENT
10.5.1. Head Protection
 All employee and workers employed on site should wear safety helmets
(approved by SIRIM) where they might be exposed to head injuries from
falling or flying object or striking against objects.
10.5.2. Foot Protection
 All employees and workers employed on site should wear appropriate
footwear where they might be exposed to injury from falling, crushing
object, hot or corrosives, poisonous substance, sharp edge tools, nails
and protruding sharp object from the ground.
10.5.3. Eye Protection
 All Employee and workers employed on site should wear appropriate
protection goggles where they might be exposed to eye injuries from
flying particles, harmful light or others dangerous substances.
10.5.4. Hands and Arm Protection
 All employee and workers employed on site should wear appropriate
gloves where they might be exposed to hand or arm injuries such as hot
or corrosive, poisonous substances, sharp, rough or pointed edges.
10.5.5. Safety Belts and Lifelines
 All employees and workers employed are working above 10 feet high
should wear appropriate safety belts (according to the manufacturing
specifications and instruction) where they might be exposed to accidental
falls.
10.5.6. Protection against Moving Object
 All employees and workers who are frequently exposed to moving vehicle
should wear bright yellow or orange coloured vest preferably of the type
of fabric that is visible especially at night.
10.5.7. Respiratory Protection Equipment
 All employee and workers should be provided with respiratory protection
equipment in places where lack of oxygen, toxic gas, dust particles or
other hostile environment that will endanger life of workers on site. The
type of respiratory protection equipment should be recommended by
Project Engineer and when required on site.
10.5.8. Ear Protection
 All employee and workers should be provided with ear protection
equipment in place where excessive noise level is detected more than

51 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


90db and in area where workers are exposed to long hour of excessive
noise.
10.5.9. Warning Sign
 All construction site should be provided with simple effective warning
sign in the three official language shall be place in a conspicuous position
at all entrances to the site for whole period of the work in hand to warn
employee and public of trespassing and danger on site and to dismantle
and remove them on completion
10.5.10. Fire Protection
 Maintaining an effective fire protection and prevention program at jobs
site during all construction stages
 Availability of the required fire extinguishing equipment.
 A location plan indicating all fire extinguishing equipment shall be place
in noticeable places.
 All fire extinguishing equipment shall be maintained, inspected and kept
in good operating conditions.
 Smoking is forbidden in operation that has potential fire hazard and sign
that reads “Do Not Smoke” shall be placed in a noticeable place.
 A portable fire extinguishing approved by the SIRIM shall be placed at not
more than 20 m from the diesel storage tank or other combustible liquid
storage area.
10.5.11. Miscellaneous
 The engines of all equipment that is being loaded must be cut off during
the fuel loading operation.
 All employee and workers shall be kept his work area in order and clean
 Holes, well, pits, M&E opening and hoppers etc. shall be permanently
covered unless such opening was being used.
 No repair, cleaning or greasing work shall be done on equipment under
operation.
 All employee and workers should consult Safety Officer if there is any
doubt arises as to safety standards required to perform certain task on
site.
 All employee and workers are absolutely forbidden to attend work being
drunk or under the influence of any other intoxicating drug.
 Malicious behaviour, joking and running around site are absolutely
forbidden during the working hours.
 No neckties are allowed when working near machinery under operation.
 No temporary electrical connection without proper socket or other
temporary electrical operation is allowed for safety reasons.
 The use of equipment, tools or machinery in unsafe condition shall not be
allowed.

52 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


10.5.12. Safety Organization and Responsibilities
 The Safety Officer sole responsibilities should be as following:
 As an advisor to the senior management.
 Recommend improvement to the existing safety system. Anticipate
potential risk and hazard at site and recommend relevant safety
procedures.
 Recommend the appropriate apparatus, protective clothing and safety
equipment.
 Established safety working procedures and policies.
 Report and record all accidents on site.
 To enforce all safety aspect on site complies with the rule and regulation
of the local authorities.
 To organize meeting once a fortnight for the purpose of educating
workers and employee the awareness of safety procedures on site.
 To make sure all workers on site observe the regulation concerning
health, welfare and first aid facilities.
10.6. SAFETY AND HEALTH INSTRUCTION
10.6.1. Safe Excavation and Trenching Works
 This instruction applies to any contractors to carry out excavation and
trenching works on the construction site. Excavation involves removal of
soil and rock, in lesser or greater quantities.
10.6.2. Objectives
 The objectives of this instruction are to outline the action, which must
be taken to ensure safe excavation and trenching works in construction
site.
10.6.3. Procedures
10.6.3.1. Excavation and Trenches Works in Construction Site
 Excavation and trenching works are considered dangerous works. Almost
all construction work involves some form of excavation for foundation,
drain, sewer, etc. Unless stringent safety control being conducted mishap
should not happen. Contractors performing excavation and trenches work
shall as a minimum but no limited to follow strictly to the safe procedures
as follow:
10.6.3.2. Prior to Work Commence:
A. Acquire clearance or approval from Project Engineer.
B. Ensure workers are trained in excavation work.
C. For purpose of excavation, no ground should be considered good or safe
until it has been investigated.
D. Prevent unauthorized person entering to the excavation area especially
children.
E. Check of soil type and decide on which type of support work is required
in consultation with a competent engineer or supervisor.
F. Check whether the excavation will affect adjoining roads or building.

53 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


G. Determine the position of all public services and ensure that are
adequately marked and disconnected as necessary.
H. Always seek advices before excavating below existing foundations of
adjacent or adjoining building. It may be necessary to provide shoring,
raking or flying or both.
I. Provide an adequate supply of material for support work, along with
barriers and correct traffic notices.
J. Make provision poling boards to stand proud of the existing ground levels.
This prevents any loose material from falling into the excavation.
K. Check for the provision of adequate lighting.
L. Check that adequate and sufficient ladders have been provided for safe
access to the excavation and that enough ropes for securing these items
are to hand.
M. Determine the positions of bridges, temporary roads and spoil heaps.
N. Determine the methods of excavating before commencing works, and the
method by which it is intended to install and remove any support work.
O. Plan for an emergency situation.
10.6.3.3. Whilst work in progress
A. A competent person shall inspect excavation and trenches daily and
after bad weather before works begin.
B. Always treat buried cable as alive.
C. Ensure that only sound material is being used.
D. Ensure that approved and safe methods are adopted for the installation
of support work in excavation. A competent person should be in
attendance at all times.
E. Ensure that all working surface are safe.
F. Install timbering as soon as the excavation sides are trimmed. This
should be done from a work cage, from ground level, or from insides
existing timbering.
G. Ensure that all support work is secure and that props and wedges are
tight and properly maintained.
H. Check for signs of overstress in support work, any damages that may
have been caused by plant and, when timber is used, make long term
checks for disease and defects, i.e. dry rot, shakes, etc.
I. Check for any water or soil, which may be seeping through support work.
J. Check for signs of the earth peeling or cracking at unsupported faces.
K. Check that there are adequate ladders that are maintained, secured and
used correctly.
L. When pumping, ensure that there are adequate sumps and that soil is
not being drawn from behind support work.
M. Check for unhealthy atmospheres.
N. Ensure that spoil heaps and material, etc. Are kept back from the edges
of the excavation.
O. Ensure that there are adequate barriers, notices and warning lights.
P. Check that the edges of excavation are provided with top and mid
guardrails at all places where there is a danger of person falling 2 meters
or move or falling and injuring themselves.

54 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


Q. Bridges and gangways should be provided and handrails and toe-boards.
R. Ensure that stops for dumpers, tipping lorries, etc. are well anchored.
S. Ensure that all passing traffic is kept well back from edge of excavation.
T. Ensure that the correct method of withdrawing support work is used; if
for any reason it is considered unsafe to remove it, leave it in.
U. Ensure that persons are not working too close to machines or each other.
V. Ensure that the correct protective clothing and protective equipment is
being used.
W. Ensure that persons are wearing suitable ear defenders when piling is
taking place.
X. Ensure that machine operators have the best possible vision of the
works, which is in progress.
Y. Ensure that services are marked and protected and adequately
supported when exposed in excavations.
Z. Ensure that any backfilling is carried out correctly and in planned
sequence and maintained.
AA. Carry out inspections daily, prior to each shift, after use of explosives
or after inclement weather, particularly frost and rain.
BB. Ensure that a proper record of all inspections is made and signed by a
competent person.
CC. The written report, or a copy, should be provided to the personnel on
whose behalf the inspection was made within 24 hours.
DD. Always treat buried cable as live.
10.6.3.4. Responsibilities
 The Contractor’s Project Engineer:
 To nominate competent person in an excavation work.
 To ensure safety, a qualified person should conduct training to workers
involved in the excavation work conducts training.
 To conduct risk analysis/assessment prior to work.
 To set safe working procedure in writing.
 To establish and enforce safe Work Permit System.
 To provide First Aid Kit at site whilst work in progress.

10.7. STACKING PILING OF MATERIALS


10.7.1. General Safety Practices
 Materials should be so stacked and unstacked that materials falling,
rolling, overturning, falling apart or breaking can injure no workers.
 Worker’s not directly involved with the operations should stay away from
the areas where stacking and unstacking operations are in progress.
 Ladders should be provided to workers for climbing stacks.
 No workers should be employed out of sight of other works in stacking
and unstacking operations.
 Before starting to take down stacks, workers should clear the ground
around them of any obstacles.

55 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 Stacks should only be taken down from the top, and no object should be
pulled out from under another.
 Stacks that lean heavily, become unstable or threaten to collapse should
only be taken down under close supervision.
10.7.2. Earth, Sand, Gravel and Crushed Stone
 Slope at the natural angle of repose of the material.
 Be enclosed by stout fencing.
10.8. HITTING TOOLS
10.8.1. Hammer.
 Strike squarely and avoid glancing blows.
 Do not strike with the side hammer.
 Never strike two hammer faces together.
 Always wear eyes protection where the works is dangerous.
 Select the correct hammer for the work is done.
 Never use loose or damaged handles. Maintain any hammer regularly
 Never strike metal harder than those hammer head at the hammerhead
may shatter dangerously.
 Do not use excessive force in hitting

10.9. LEVERAGE TOOLS AND ADJUSTABLE STEEL PROPS


10.9.1. Hydraulic Jack.
 Always support the load centrally on the jack, to avoid eccentric loading.
 In the case of props, always secure the head and footplate to timber
support.
 Never support from unstable ground.
 Keep jacks or props well maintained at all times.
 Keep within the specified loading capacity of any jack or prop.
 Never improvise, particularly with adjustable steel prop when it’s
dangerous to use mild steel bars or nails as pins. The manufacturing pins
of high yield steel must always be used.
10.9.2. Picks and Shovels
 Use the correct stance with leg astride for firm footing.
 Make sure overhead area is clear of obstruction.
 Keep pick sharp.
 Make sure their handle free from splinters, crack or other defects.
 Do not leave any tools lying on the ground. They might be a tripping
hazard.
10.9.3. Spanner, wrenches and pliers.
 Always use the correct size of jaws to avoid slipping and hand injuries.

56 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 Never attempt to increase the leverage by adding sleeved addition to the
spanner length. This will strip off thread or snap bolts and stud.
 Do not hit any spanner or wrenches with hammer.
 Take extra care when cutting tensioned wire, as the end tends to fly off.
 Pliers for electrical use must have insulted handles.
10.9.4. Screwdriver
 Always use the correct size of shrank for the screw head.
 Never carry screwdrivers in pockets, as skin punctures will occur.
 Do not hammer screwdrivers.
 Never user screwdriver for leverage or as chisel to remove obstruction.
 Screwdrivers for the electrical works must be insulated.
 Keep screwdriver with accurately ground tip. Do not exert excessive
pressure upon the work, especially where overbalancing may occur.
10.10. CUTTING TOOLS
10.10.1. Chisels
 Keep chisels sharpened to the correct angle, grinding angle between
twenty to twenty-five degrees, sharpening angle thirty to thirty-five
degrees.
 Use the right type of chisels for the job.
 Always keep hand and body behind the cutting edge.
 When not using the chisels, place it safely or use protection plastics cap
to cover the cutting edge.
 Always use mallets for all chisel; never hit them with a hammer.
10.10.2. Saw
 Use the correct type of saw for the job.
 Make sure the teeth are properly set and adjust to avoid bindings.
 When not use, keep the teeth of saw protected with full sheath covering
the whole blade.
 Always protect the saw from rust after contact with moisture by smearing
with oil.
 Avoid excessive force where the saw may buckle and cause injuries.
 Do not work where off cuts might fall on others without giving warning.

10.11. GENERAL SAFETY PRACTICE


 Always assess the job before lifting and make sure it within your
capabilities.
 Ensure good grip and correct posture.
 Make sure the back is straight and not overburdened.
 Always keep clear vision while lifting.
 Use lifting hook and aids where capable.
 Do not over-reach stack the materials.
 Prepare and check the route to avoid any slippery surface or obstacles.

57 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 Always wear protection clothing, e.g. boots with steel toecaps.
 Stop and relief, in preference to maintaining a lift if delay occurs.
10.12. FIRE FIGHTING AND PROTECTION
10.12.1. Flammable liquid
 All containers must be clearly marked, showing the contents.
 All containers must have secure capping device.
 Flammable liquid must be stored in a securable locked compound at least
twenty feet away from any temporary building. Lit cigarettes must be
prohibited within twenty feet of any combustible store.
 Spillages must be cleaned up or covered with sand.
 Transportation must be only taking place when containers are sealed.
10.12.2. Electrical appliances
 Isolation by main switch and sufficient protection against excess current
must be included.
 All overhead wiring must be strong enough for the span and marker flag
use for protection.
 All ground wiring must be underground or protected from vehicular
damage by the use of ramps.
 All portable electrical powered hand tools must be connected with
flexible.
 Power supplies must be reducing to safe voltage.
 The telephone numbers to contact the nearest firefighting, hospital,
police station and the person on charged in case emergency should be
provided.
10.12.3. Fire Fighting Practice
 Keep a clear fire escape route and free access for firefighting and a free
access for firefighting.
 All hazard materials and substances must be stored separately in clearly
specified areas.
 Ensures all site personnel are aware of fire escape and emergency
procedures.
 Provide firefighting appliances in easily seen, accessible areas and
arranged regular checks of these.
 Provide a clearly marked layout plan site indicating the location of all
firefighting appliances.
 Ensure all flammable liquids and gasses and their appliances are stored
in proper place.
 Check all electrical appliances are not overloaded and protected from
incorrect voltage.
 Arrange regular clearing of combustible waste materials on site at least
once weeks.
 Ensures all site personnel are aware of any danger areas and marked with
clear notices.

58 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


 Provide sellable containers for oily rags, paint rags and other fire inducing
waste.
 Establish, maintain a good liaison with local emergency services such as
police, hospital and site security.
 Arrange a regular fire prevention check once a week.
 Install; make know to all site personnel a good alarm system.

11. INSPECTION AND TESTING PLAN


 The relevant inspection and tests to be carried out on the project are outlined
in the inspection and test plan.
 The project team shall implement the inspection and test plan. The inspection
and test plan shall be used in concurrence with the project specifications,
standards, drawings and instructions with JKR regulation.

59 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)

12. APPENDIX

60 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


12.1. APPENDIX A
12.1.1. Project Meetings

NO. MEETING AGENDA CHAIR PERSON ATTENDEES FREQUENCY


1. Site Project SO Client Monthly
Meeting progress Consultants
Current issues Project Manager
Quality issues Project Engineer

12.2. APPENDIX B
12.2.1. Work Schedule
 Refer to enclosed Project Programme. The latest Project Programme is
maintained by Project Manager.
12.2.2. Materials List
 Refer to enclosed Materials List. The latest Materials List is maintained
by Project Manager.
12.2.3. PME List
 Refer to enclosed PME List. The latest PME List is maintained by Project
Manager.
12.2.4. Validation of Works
 N/A
12.2.5. Traffic Management Plan
 Refer to construction drawings.

61 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


12.3. APPENDIX C
12.3.1. Internal Forms, Checklists and Reference Documents List
 The following forms, checklists, reference documents with a tick (  ) are
applicable to this project. The project team shall refer to the Operating
Procedures Manual to implement these documents.

FORM AND CHECKLIST


No. Document Doc. Ref. Connected to
Procedure
1. Sistem Pengurusan Bersepadu JKR N/A
2. Term of Reference By JKR N/A
3. Transmittal Note
4. Client Satisfaction Survey Form PU-F12
5. Non-Conformance Report Log PU-F11
6. Client Satisfaction Survey Form
7. Client Complaint Table
8. Performance Evaluation Form
9. Notice of Defect Form PU-F21
10. Request of Inspection PU – F08
11. Site Diary PU – F10

REFERENCE DOCUMENT
No. Document Doc. Ref. Connected to
Procedure
1. Inspection & Test Plan
2. Company Filing Index

62 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


12.4. APPENDIX D
12.4.1. EXTERNAL FORM, CHECKLIST AND REFERENCE DOCUMENT LIST
(From Client or Customized Documents)
 The following forms, checklist and reference document are provided by
client or customized to meet project specification requirement. These
form, checklist and reference documents are attached in this appendix
for implementation by the project team.

FORM AND CHECKLIST

No. Document Connected to Procedure

1. Term of Reference JKR N/A

2. Sistem Pengurusan Bersepadu (JKR_ N/A

63 | P a g e
Pintas Utama Sdn Bhd (PUSB) No. Ref : Rev.00

PROJECT QUALITY PLAN (PQP)


12.5. APPENDIX F
12.5.1. ORGANISATION CHART

64 | P a g e

You might also like