You are on page 1of 4

CONSTRUCTION TOLERANCE

CONFLICTS IN
CRSI
REINFORCED CONCRETE ENGINEERING
DATA REPORT
A SERVICE OF THE CONCRETE REINFORCING STEEL INSTITUTE
NUMBER 40

933 N. Plum Grove Rd., Schaumburg, Illinois 60173-4758

CONFLICTS BETWEEN ELEMENTS OF


INTRODUCTION REINFORCED CONCRETE FRAMES

The construction tolerances for cast-in-place Reinforcing Steel And Member Profile
reinforced concrete buildings have evolved with - The depth of a beam between 12 and 36 in.,
in the American Concrete Institute over the past Figure 1, has a tolerance of +1/2 in. and -3/8 in.
50 years into what is generally considered to be The height of the stirrup and the position of the
a reasonable set of criteria that can be achieved horizontal bar positioned by the stirrup has a tol-
using normal construction practices. erance of +/- ½ in. Since the bars are supported
One of the early attempts to publish building by the 1-1/2 in. bar supports on the soffit, all of the
tolerances appeared in the ACl literature in tolerances affect the top cover. If the stirrup is ½
1940. The first presentation of forming toler - in. taller and the beam is 3/8 in. shallower than
ances in an ACI standard appears to be in 1963 theoretical, the top cover could be reduced by ½
in “Recommended Practice for Concrete plus 3/8 or 7/8 in. An actual cover of 5/8 in. would
Formwork”. Subsequently, construction toler - be the result. According to ACI 117, the tolerance
ances have been included in many ACl commit- for the 1-1/2 in. cover over the stirrup is ½ in., pro-
tee reports and specifications. ACI tolerances for viding for a minimum cover of 1 in. Therefore, the
fabricated reinforcing bars have been developed cover will be reduced below the allowable toler-
by CRSI. All ACl tolerances are now being con - ance though all components of the assembly, the
solidated under the auspices of ACl Committee formwork, the rebar fabrication, the rebar place-
117, Tolerances. The committee has developed ment, and the concrete finishing, usually per-
“Standard Tolerances for Concrete Construction formed by separate subcontractors, were within
Materials”. The current document is designated acceptable tolerances. Careful coordination of the
as ACl 117-90. trades and field measurement before placing con-
Reinforced concrete is the result of the work of crete is recommended to resolve this conflict.
several separate trades or subcontractors who Specifying additional cover where cover is critical
utilize various ACl tolerances applicable to their may also be appropriate.
trade. Tolerance conflicts in reinforced concrete For a beam perpendicular to a sloping surface
construction are multiplied by having potentially such as in a parking garage, Figure 2, the deci-
inconsistent tolerances within ACl with which to sion on where the beam depth is to be measured
build and the requirement to accommodate the also affects the depth of the beam stirrup. Since
tolerances of other building elements. Conflicts the top slopes and the beam soffit is usually hor-
within the set of ACI tolerances still exist, but izontal, if the depth is measured on the downhill
most construction disputes arise from conflicts side, the stirrups will be the same as for non-
with adjoining elements. ramp beams. If, however, the decision is made to
This report presents some common areas of measure the beam depth at the centerline, the
conflict due to tolerances. Recommendations of stirrup will have to be roughly 3/4 in. less in
actions that may lessen or eliminate the conflicts height than for the non-ramp beams. Making this
are presented. decision also reduces the effective depth of the
beam reinforcement and therefore its capacity.
The Architect/Engineer should specify the point
at which the depth is to be measured and con -
sider the effects on the reinforcing steel.

© Copyright 1995 by the Concrete Reinforcing Steel Institute


Fig. 1 Beam Stirrup Cover Fig. 2 Measuring Beam Depth

Formwork And Member Profile Deciding where the beam depth is to be meas-
Widely used concrete joist construction is ured presents a third problem on sloping or
formed with thin gage inverted “U” shaped metal ramped surfaces. If the beam depth is measured
forms which lap at joints and have flanges which on the downhill side, the soffit of the beam is low-
are nailed to framing material forming the joist ered by 3/8 in. which reduces the clearance by
soffit. The lap joints and soffit connection typi- 3/8 in.
cally have offsets of up to ½ in. with occasional The simultaneous occurrence of these three
1 in. offsets (Figure 3). While not meeting the conditions is quite normal. What was intended to
ACl cross-section tolerance of -1/4 in., +3/8 in. be 7-ft clear becomes 6 ft 9-3/4 in. This is 2-1/4
for members up to 12 in. in width, the offsets do in. less than planned. The story height should be
meet ACl 117 Class C (½ in.) and Class D (1 in.) increased by 2-1/4 in. to allow for the construc-
tolerances for offsets between adjacent pieces tion tolerances.
of formwork. Fortunately, the offsets usually The use of post-tensioning sometimes com-
either make the member thicker or do not occur pounds the problems of trying to keep the edge
at locations which would affect the structural of the building within acceptable tolerance
integrity of the concrete joist. The end 3 to 6 ft of (Figure 5). The usual procedure would be to cast
the joist rib is structurally most vulnerable to the first lift columns, then cast the floor slab.
thickness deficiency. Before tensioning the floor beams and slabs, it is
This conflict can best be resolved by recogniz- likely that the 2nd lift of columns has been cast.
ing that the tolerance range required with this The tensioning operation compresses the con-
method of construction is greater than with more crete and tends to pull the edges of the building
costly alternatives. Class “C” or “D” tolerances toward the center or other stable location. The
should be specified and, except in areas affect- result may be the movement of the slab by as
ing structural integrity, the cross-sectional toler- much as 3/4 in., pulling the first floor columns out
ances should not be strictly applied to this type of plumb and moving the 2nd lift of columns lat-
of construction. erally by this amount. The casting of the 2nd slab
and the 3rd lift of columns followed by the ten-
Conflicts Between Members sioning of the 2nd floor system moves the top of
In a long span beam and slab parking struc- the 2nd lift of columns an additional 3/4 in.
ture, the floor-to-floor height is often 10 ft 0 in. inward for a total movement of 1-1/2 in. As the
with a 3-ft deep beam. The minimum clearance building progresses, the offsets progress. A 10-
specified is 7 ft 0 in. which leaves zero tolerance. story building could be off by as much as 7-1/2
The ACI tolerances on the forming would allow in. unless corrective measures were taken.
+/-3/4 in. for the soffit and top elevation. This The common remedy is to anticipate the
could reduce the clearance by 1-1/2 in. movement and lean the columns outward and
The problem worsens in the ramp areas, build the slab edge beyond its desired location.
Figure 4, where the slope of the ramp at 5 or 6 Unfortunately, the movement does not always
percent grade makes the clearance on the uphill occur due to the level of the post-tensioning
side of the beam 3/8 in. less than at the center- force or constraints in the building geometry.
line. This occurs because the beam soffits are This is a condition where the Architect/Engineer
placed level rather than parallel to the slope of should advise the Contractor of the anticipated
the ramp. movement so the Contractor can act accordingly.
Conflicts Between The Frame And Other Trades Interior Conditions
Other trades, particularly the finish trades, The installation of floor-to-ceiling partitions
must build their product to meet or surround the presents conflicts similar to the exterior opening.
concrete elements. Their products also have a Attachment of partitions or other elements
set of industry established tolerances. These against the underside of concrete joist construc-
products are often plant manufactured with sig -
tion must be designed to accommodate the like-
nificantly less variation in dimensions and are
also often exposed to public view and have erec- ly ½ in. to 1 in. vertical offsets that may occur
tion tolerances that are much more restrictive along the joist soffits.
than the hidden concrete elements. It becomes
the responsibility of the Architect/Engineer to
consider the differences in tolerances between
the various elements of the finished structure
and to develop connection details and clear-
ances to accommodate these differences.

Fig. 3 Joist Construction With Lapped Forms

Exterior Conditions
The ACI tolerance for the edge of a concrete
slab is +/- 1 in. The typical 5-in, brick ledge angle Fig. 4 Clearance to Slab Below Sloping Surface
leaves about ½ in. clear between the bolt and
the brick, Figure 6. Any movement of the build -
ing edge outward encroaches on the insulation
and air gap and may require chipping of the brick
or removal of concrete. Chipping the brick weak-
ens the brick and removal of concrete may
destroy the anchorage for the brick angle and
reduce the cover on the reinforcing bars at the
beam edge. The Architect/Engineer must devel-
op connection details that would accommodate
the potential 2 in. movement of the slab edge.
The installation of window units to the under-
side of concrete beams or slabs, Figure 7, is fre-
quently a cause of tolerance conflict. The toler-
ance for the location of the soffit is +/- 3/4 in. The
same tolerance applies to the top surface of the
beam which allows for an opening size variance
of +/- 1-1/2 in. The window unit manufacturer
anticipating a 1/4 in. sealant joint top and bottom
builds the unit to a tolerance of +/- 1/16 in. The
result is 1 in. wide sealant joints or perhaps a
unit that is 1 in. taller than the opening. The solu -
tion to this problem may be easier than some. An
expansion channel allowing for +/- 3/4 in. move-
ment was a solution employed 20 years ago that Fig 5. Post-Tensioning Movement
is still valid today.
Fig. 6 Attachment of Brick, Precast or Curtainwall Fig. 7 Window Frame in Concrete Opening

CONCLUSIONS

These examples are only a few of the many Pre-design conferences with Contractors,
areas of conflict relating to the construction of a Subcontractors and Suppliers will frequently
structure to acceptable tolerances that could be point out areas of possible conflict. Most of the
made easier by the closer cooperation of the discussed conflicts can be avoided by recogniz-
parties involved. ing that variations, as allowed in ACI 117, will
The ACI tolerances for the reinforced frame occur and by acting accordingly.
are generally reasonable but increased pressure The Architect/Engineer and Contractor
to build faster with less cost makes them harder should be aware of the potential discrepancies
to maintain. Building the frame to more exacting between the exact dimensions and locations
tolerances is possible but should only be called shown on design drawings, and the variance of
for when absolutely necessary as the additional practical dimensions which make tolerances
cost can be significant. The other trades are necessary in order for the various trades and
faced with similar problems. suppliers to construct a reinforced concrete
The Architect/Engineer must be continuous- structure. A concerted effort should be made to
ly aware of tolerances and design accordingly. coordinate the work of the various trades, antici-
Where it is necessary to be more restrictive at pate problems of fit, and resolve a potential con -
specific locations, these locations and their flict prior to its occurrence. Last minute disputes
requirements should be shown on the design at the jobsite are an expensive alternative.
drawings or in the project specifications.

REFERENCES
Nichols, JR., “Tolerances in Building Beall, C., “Specifying Construction Tolerances”,
Construction”, ACI Journal, April 1940. The Construction Specifier, August 1990.
Standard Tolerances for Concrete Construction
and Materials, ACl 117-90, 1990. Birkeland, P.W., and Westhoff, L.J., “Dimensional
“Reasonable Tolerances for Cast-in-Place Tolerances in a Tall Building”, ACI Journal,
Concrete”, Concrete Construction Magazine, August 1971.
May 1974.

CONCRETE REINFORCING STEEL INSTITUTE


933 N. Plum Grove Road, Schaumburg, Illinois 60173-4758 • 847/517-1200
WESTERN REGION OFFICE
259 S. Randolph Ave., Suite 220, Brea, California 92821 • 714/257-7302

This publication is intended for the use of professionals competent to evaluate the significance and limitations of its contents and who
will accept responsibility for the application of the material it contains. The Concrete Reinforcing Steel Institute reports the foregoing
material as a matter of information and, therefore, disclaims any and all responsibility for application of the stated principles or for the
accuracy of the sources other than material developed by the Institute.

H N H 0995/25M Printed in U.S.A.

You might also like