Check list For piping

No Item Description ACC REJ NOTE

1. Piping

1.1 Material of Each Piping /Fitting/Valve

1.1.1 Die Stamp Or Stencil Of Piping Fitting /Valve

1.1.2 Color Code Marks On Piping

1.1.3 Material Certificates Of piping , Fitting and Valve

1.2 Thread Joints

Visual

Alignment

1.3 Flange Joint

Visual

Alignment

Condition Of Flange Alignment Between Equipment And Pipe

1.4 Erection And Installation OF


Pipes/Fitting/Valve.(AG)

Location And Position

Arrangement Order

Alignment

Dimension

Visual (Spool ID, Cleaning, Damage And Flow Direction and…)

1.5 Erection And Installation OF


Pipes/Fitting/Valve.(UG)

1.5.1 Location And Position

1.5.2 Arrangement Order

1.5.3 Alignment
Check list For piping
1.5.4 Dimension

1.5.5 Visual

All Pipe Laying

Coating And Wrapping

Calibration Of Pressure Gauge

Drawing

Flushing And Drying

Physical Damage

Flow Direction

1.5.6 Holiday Test

1.5.7 Cathodic Protection Test

1.6 Piping Support

1.6.1 Location

1.6.2 Arrangement

1.6.3 Condition Of Fixing

1.6.4 Tightness And Fixed End

1.6.5 Movement Of Sliding End

1.6.6 Clearance Between other Licensor Structure After Thermal


Movement

Rigidity During Valve Operation.

Removal Of Temporary Stopper On Sliding End.

Tightness Of Connection And Fastening .

Pre-Installation Check.

1.7 Pressure Test

1.7.1 Insulation Of Equipment and Instruments

Rotating Machinery
Check list For piping

Pressure Relieving Devices

Equipment Blind

Instruments

Normally Opened To Atmosphere

Any Other Specified Equipment

1.7.2 Hydrostatic Test

1.7.3 Pneumatic Test

1.7.4 NFPA Test of Fire Water Piping System

1.8 Cleaning

1.8.1 Visual Inspection Of Chemical Cleaning(If Require)

1.8.2 Visual Inspection Of Chemical Cleaning(If Require)

1.9 Fire Hydrant

1.9.1 Material

1.9.2 Pre- Installation Check

1.9.3 Identification Marking

1.9.4 Installation Of Equipment

1.9.5 Functional Test

1.10 Tracing

1.11 Insulation Of Piping

1.12 Painting