Professional Documents
Culture Documents
Bajaj
-
General Hanager, =. Hew Delhi
Chairmau. I 5 A d a Pacific - Education
86
and laying of 220 volts lines with Erection Works
consumer connections to more than 8000
households in these villages and 1. IAEC (Madras) Ltd., India
towns.
87
These initial documents helped each of the project weekly reports were
participant to understand the total generated after feeding weekly data.
project, his role and the unified co-
ordinated approach to project execu- Based on the master network level I1
tion. networks were prepared by each Divi-
sional Co-ordinators for their area of
The contract was executed by BHEL as work. These networks included:
main contractor who were responsible
for project management and control. 1. Network for project engineering
In order to have effective co-ordina- 2. Network for civil construction
tion with all constituent partners, a 3. Network for electrical and
special Project Group was constituted mechanical works
which was entrusted the overall re- 4. Network for transmission and
sponsbility of project co-ordination distribution works
and management. However, within BHEL, 5. Network for BHEL manufactured eq-
the Engineering Co-ordinator ensured uipment and bought out equipment
preparation of overall schemes, ap-
proval of vendor drawings and design, These networks were monitored by the
and overall engineering co-ordination. project co-ordination group with the
The Divisional Co-ordinators at manu- Divisional Co-ordinators, initially,
facturing plants were entrusted the on a two week interval and, subse-
responsibility of co-ordinating manu- quently, on a monthly basis.
facturing activities in their respec-
tive areas. However, each manufacturer/ subcon-
tractor of the project prepared his
Early in the project execution stage, own network deriving key dates from
the Project Co-ordination group with the level I1 network. These were
the help of the Engineering Co-ordina- called the level I11 networks and were
tor prepared a "Contract Handbook". reviewed regularly by the concerned
This detailed out the complete scope Divisional Co-ordinators on a regular
of the project and indicated which basis and it's review provided infor-
agency had the prime responsibility mation for feeding data for the review
for the defined area of work. It also of level 11 networks.
gave details of exact scope of works
and Elupply. The Contract Handbook Apart from review of progress of the
helped each player to understand his project regularly on network basis,
own role/responsibility and also learn regular review meeting were also held
about the roles and responsibilities with the Project Owners, Consulting
of other players. The responsibility Engineers and main project execution
of co-ordination between the various agencies. These meetings helped in
agencies rested with the project co- expediting decisions on project execu-
ordination group. tion matters which had direct bearing
on the time and cost of the project.
Proiect Manaaement and Control
The project was being executed simul-
The project was managed by network taneously in many parts of the world.
techniques. A Master network was In order to have fast communication
prepared with two different completion and to have acceptable level of turn-
times. A 36 month network was pre- around time on information many new
pared to review and monitor as per concepts were used:
project requirements including with
the Project Owner and the Technical 1. It was necessary that all commu-
Consultants. In order to achieve high nications either by letter or by
probability of success in completing telexes is received by the concerned
the project in time, another network agencies and in case of any missing
with completion time of 34 months was communication both sender and the
prepared. The second network was receiver agency should be alerted: A
mainly used for project monitoring and specific letter/telex numbering scheme
control by the project co-ordination for each agency was devised. A record
group. All review and time planning was kept by all agencies receiving or
was based on a 34 month network. The sending messages to check that these
network gave an overall picture of the are being received regularly and no
project and was monitored with the message is missed. The system of
help of a computer. At the beginning message numbering was as follows:
88
was one of the key factors for the
J/A/B - T 001 success of the project. In house
detailed review was also undertaken
where with BHEL top management every two
J = denotes the name of the project months and help sought wherever sup-
A = name of the issuing agency port from outside agencies including
B = name of the receiving agency Govt of India was required.
T = stands far telex but it can be
changed to F for fax or to L
for letter -~
Cost Control
001= it is the sequential numbering
of the message. The success of the project was also
dependent on its execution at the most
2. The communication between project optimum cost. A tight budgetary
site and project co-ordination in New control was enforced to ensure no cost
Delhi bas strengthened. A radio link over runs. In brief following mecha-
was established between Gizan and nism of budgeting was adopted.
Liasion office in Riyadh. Then a
telex link was established between 1. The cost of each component was
Riyadh and New Delhi. T h e was fixed estimated. It was compared with the
for a call between Gizan and Riyadh. overall cost and with minor adjust-
Telex messages from New Delhi were so ment, the cost of each package was
sent that there was proper co-ordina- frozen. (It is to be kept in mind
tion with Radio link timings. that overall project cost was already
fided).
3. In order to cut down the drawing
approval time, after the desighs were 2. A s i n c a s e of time planning,
ready a team of engineers would visit three percent was estimated as the
the Supervising Engineer for drawing probability factor.and it was deducted
approvals. Wherever changes were from the frozen cost of each element.
required by the supervising engineer, The new cost became the target cost of
these were carried out during the each element.
meeting itself. Drawings were resub-
mitted and approvals obtained, thus 3. Whenever a c d t m e n t to purchase .
reducing the time of drawing approvals was made it was compared with the
to the barest minimum. target-cost. If the purchase price
was more, engineering design require-
4. A n executive was earmarked pri- ment was closely evaluated to check if
marily for collection of reports on requirements could be ref rdmed to
LII 'networks for updating L1 networks. avert cost over run.
He was travelling every week to dif-
ferent centres of activity for collec- 4. Tendering system was adopted for
tion of such information. major components, but the price of the
competitors was' not advised to the
5 Due to postal limitations, the bidders. Negotiations were again
feedback from the project site was conducted with the lowest bidders to
time consuming. Similarly, it was elicit further concessions. Overall a
difficult to rush resources at short saving of 3.5% was achieved in the
notice if t h e project was behind target costs of purchased items.
schedule. A concept of rolling plan
was developed. The site activities 5. As the payment of various compo-
were planned in detail for the next nents was in different currencies like
four weeks. Review was taken at the US$, DM. Sw.Fr., etc., and the receipt
end of each week and a new week aded was in Saudi Rials, management of
to the planning process. This review exchange risks was extremely important
along with resource planning for the for cost control: Offshore bank A/c
fourth week was sent every week to the in Bahrain and London were opened and
Project co-ordination group in New surplus funds converted into these
Delhi for overall project review and currencies at the most appropriate
feed back. time to hedge against exchange risks.
Such funds were then invested in short
A strong and sound project planning term deposits.
was the backbone of the project. It
was rigidly adopted and followed. It 6. One of the major expense was that
89
of shipment and transportation of effective, fast and reliable means of
equipment to the site. In order to postal communication is necessary.
cut d o w n expenses, equipment w a s
directly shipped to Gizan port, by 5. Co-ordination of timely supplies
clubbing the shipments and chartering is important. Role of establishing
small ships having their own derrick an optimum shipment and transportation
cranes. This arrangement not only facility is very important, as materi-
reduced the cost but also reduced al will flow in from many countries.
transportation damages to the minimum. It is also important to ensure that
Survey of road from port to project transportation damages are minimum.
site was done by experts and the road
was either strengthened or diversions 6. Preparation of drawings, O&M
built. manuals, and consolidated spare part
lists is important for smooth opera-
7. I n short all areas of expenses tion after commissioning. Practices
were carefully monitored and it was in each country differ yet the final
ensured that only minimum possible project should show an unified ap-
costs are incurred. This resulted in proach.
a net saving of 8% from the budgeted
project costs. Goncluaiap