ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 1 JULY 2021

LEBUHRAYA MAHAMERU A140


NO. HULS OTHERS
ITEM LSC FHRII STORE
SITE SUBANG SITE
STAGE 1A STAGE 1B STAGE 1C STAGE 2A STAGE 2B STAGE 3A
OFFICE
1 TEMPORARY TRAFFIC WARNING SIGNS 32 18 15 7 9

2 TEMPORARY DIRECTIONAL SIGNS 10 5

3 TEMPORARY APOLOGETIC SIGN 1 1

4 PLASTIC BARRIER 343 355 194 88 28 12 14

5 PLASTIC HOARDING 139 281 43 354

8 CONCRETE BARRIER 1.5m 31 19

9 CONCRETE BARRIER 1.0m

10 DELINEATOR BARRIER 77 187 22 16

11 DELINEATOR STRING 41 31 26 16

12 BLINKERS

13 SUPER/GIANT CONE (1000 mm) 0

14 SAFETY CONE (70 mm) 5 11 4

15 FLASHING ARROW 1

16 ROBOTIC FLAGMAN

17 PORTABLE VARIABLE MESSAGING SYSTEM


(PVMS)
18 TRAFFIC CONTROL PADDLE

19 TRAFFIC CONTROL FLAG 4

20 TRAFFIC BATON LIGHT

21

22
ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 27 July 2021

NO. SITE HULS OTHERS


ITEM STAGE 1A STAGE 1B STAGE 1C STAGE 2A STAGE 2B STAGE 3A LSC FHRII
STORE SUBANG SITE

1 TEMPORARY TRAFFIC WARNING SIGNS 32 16 15 6 9 2

2 TEMPORARY DIRECTIONAL SIGNS 11 5

3 TEMPORARY APOLOGETIC SIGN 1 1

4 SIGN A-FRAME (LLM)

5 SIGN POLE (LLM) 13

6 SIGN A-FRAME (JKR)

7 SIGN POLE (JKR) 1

4 PLASTIC BARRIER 345 364 201 86 28 18 21 60

6 PLASTIC HOARDING 139 267 43 301 60

8 CONCRETE BARRIER 1.5m 31 19

9 CONCRETE BARRIER 1.0m

10 DELINEATOR BARRIER 74 170 26 20

11 DELINEATOR STRING (ROLL) 1

12 BLINKERS 41 31 24 15 4

13 SUPER/GIANT CONE (1000 mm)

14 SAFETY CONE (70 mm) 5 3 10

15 PORTABLE FLASHING ARROW 1

16 ROBOTIC FLAGMAN

17 PORTABLE VARIABLE MESSAGING SYSTEM


(PVMS)
18 TRAFFIC CONTROL PADDLE

19 TRAFFIC CONTROL FLAG 3

20 TRAFFIC BATON LIGHT 2

22 IBC TANK

23 HOST IBC TANK


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 22 August 2021

NO. SITE SITE HULS OTHERS


ITEM STAGE 1B STAGE 1C STAGE 2A STAGE 2B STAGE 3A STAGE 4A STAGE 4B LSC FHRII TOTAL
STORE OFFICE SUBANG SITE

1 TEMPORARY TRAFFIC WARNING SIGNS 25 1 6 8 9 1 5 55

2 TEMPORARY DIRECTIONAL SIGNS 11 14 25

3 TEMPORARY APOLOGETIC SIGN 1 1 2

4 SIGN A-FRAME (LLM) 3 3

5 SIGN POLE (LLM) 0

6 SIGN A-FRAME (JKR) 0

7 SIGN POLE (JKR) 0

4 PLASTIC BARRIER 390 39 88 194 18 141 96 36 60 1062

6 PLASTIC HOARDING 391 42 19 117 36 60 665

8 CONCRETE BARRIER 1.5m 31 19 50

9 CONCRETE BARRIER 1.0m 0

10 DELINEATOR BARRIER 152 4 25 16 3 27 227

11 DELINEATOR STRING (ROLL) 1 1

12 BLINKERS 34 4 11 23 6 5 32 115

13 SUPER/GIANT CONE (1000 mm) 0

14 SAFETY CONE (70 mm) 3 3 4 10

15 PORTABLE FLASHING ARROW 1 1

16 ROBOTIC FLAGMAN 0

17 PORTABLE VARIABLE MESSAGING SYSTEM (PVMS) 0

18 TRAFFIC CONTROL PADDLE 0

19 TRAFFIC CONTROL FLAG 3 3

20 TRAFFIC BATON LIGHT 2 11 13

22 IBC TANK 0

23 IBC TANK HOSE 0


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 1 Oct 2021

NO. STAGE 2B + SITE HULS OTHERS


ITEM STAGE 1B STAGE 2A STAGE 3A STAGE 3B STAGE 4A STAGE 4B SITE STORE LSC FHRII TOTAL
BRIDGE OFFICE SUBANG SITE

1 TEMPORARY TRAFFIC WARNING SIGNS 20 7 19 5 4 1 7 63

2 TEMPORARY DIRECTIONAL SIGNS 8 11 17 6 42

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 0

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 0

9 PLASTIC BARRIER 329 61 174 20 69 226 128 12 39 60 1118

10 PLASTIC HOARDING 278 45 111 26 159 27 51 36 60 793

11 CONCRETE BARRIER 1.5m 31 19 50

12 CONCRETE BARRIER 1.0m 12 9 50 40 39 150

13 DELINEATOR BARRIER 115 13 38 166

14 DELINEATOR STRING (ROLL) 1 2 1 4

15 BLINKERS 29 9 26 11 5 8 2 90

16 SUPER/GIANT CONE (1000 mm) 1 3 4

17 SAFETY CONE (70 mm) 4 8 1 12 5 30

18 PORTABLE FLASHING ARROW 1 1

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE MESSAGING SYSTEM


0
(PVMS)
21 TRAFFIC CONTROL PADDLE 0

22 TRAFFIC CONTROL FLAG 0

23 TRAFFIC BATON LIGHT 0

24 IBC TANK 2 2

25 HOST IBC TANK 0

26 WATER PUMP 0
ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: as at 21 Oct 2021 (not completed until end of month)

NO. STAGE 2B + STAGE 4A + SITE SITE HULS OTHERS


ITEM STAGE 1B STAGE 2A STAGE 3A STAGE 3B STAGE 3C STAGE 4B PMC2 TOTAL
BRIDGE BRIDGE STORE OFFICE SUBANG SITE

1 TEMPORARY TRAFFIC WARNING SIGNS 20 10 19 5 4 10 6 7 5 86

2 TEMPORARY DIRECTIONAL SIGNS 6 12 13 5 11 47

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 0

7 SIGN A-FRAME (JKR) 2 2

8 SIGN POLE (JKR) 3 3

9 PLASTIC BARRIER 284 59 174 18 57 60 213 125 14 39 60 1103

10 PLASTIC HOARDING 237 56 112 26 39 159 23 68 36 60 816

11 CONCRETE BARRIER 1.5m 31 19 50

12 CONCRETE BARRIER 1.0m 40 12 9 50 60 40 39 50 300

13 DELINEATOR BARRIER 132 28 28 10 11 209

14 DELINEATOR STRING (ROLL) 1 2 1 4

15 BLINKERS 29 9 26 10 12 15 8 10 119

16 SUPER/GIANT CONE (1000 mm) 1 3 4

17 SAFETY CONE (70 mm) 6 11 4 10 31

18 PORTABLE FLASHING ARROW 1 1

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE MESSAGING SYSTEM


0
(PVMS)
21 TRAFFIC CONTROL PADDLE 0

22 TRAFFIC CONTROL FLAG 0

23 TRAFFIC BATON LIGHT 0

24 IBC TANK 2 2

25 HOST IBC TANK 0

26 WATER PUMP 0
ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 28/12/2021

NO. SITE SITE


ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3C PMC2 STORE TOTAL
OFFICE STORE

1 TEMPORARY TRAFFIC WARNING SIGNS 11 9 10 5 8 2 4 10 59

2 TEMPORARY DIRECTIONAL SIGNS 3 4 9 18 11 45

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 52 52

6 SIGN POLE (LLM) 25 25

7 SIGN A-FRAME (JKR) 6 6

8 SIGN POLE (JKR) 11 12 14 14 26 2 4 10 0 0 5 23 121

9 PLASTIC BARRIER 181 177 350 95 47 60 37 28 77 1052

10 PLASTIC HOARDING 145 109 322 58 35 40 36 8 53 806

11 CONCRETE BARRIER 1.5m 31 19 50

12 CONCRETE BARRIER 1.0m 140 51 49 50 60 50 400

13 BARRIER DELINEATOR 140 13 11 10 36 28 238

14 DELINEATOR STRING (ROLL) 1 1 1 3

15 BLINKERS 21 9 9 9 5 10 25 88

16 SUPER/GIANT CONE (1000 mm) 10 10

17 SAFETY CONE (70 mm) 201 201

18 PORTABLE FLASHING ARROW 1 2 3

19 ROBOTIC FLAGMAN 1 1

20 PORTABLE VARIABLE MESSAGING SYSTEM


0
(PVMS)

21 TRAFFIC CONTROL PADDLE 0

22 TRAFFIC CONTROL FLAG 0

23 TRAFFIC BATON LIGHT 7 7

24 IBC TANK 3 3

25 IBC TANK HOSE 1 1


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 27/1/2022

NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3C SITE OFFICE SITE STORE KESAS PMC2 STORE TOTAL

1 TEMPORARY TRAFFIC WARNING SIGNS 11 9 10 5 8 2 4 10 59

2 TEMPORARY DIRECTIONAL SIGNS 3 4 9 18 11 45

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 2 25 27

6 SIGN POLE (LLM) 10 17 27

7 SIGN A-FRAME (JKR) 10 10

8 SIGN POLE (JKR) 11 12 14 14 26 2 4 10 5 26 124

9 PLASTIC BARRIER 209 209 444 130 141 103 37 28 77 1378

10 PLASTIC HOARDING 161 121 379 116 26 42 36 8 53 942

11 CONCRETE BARRIER 1.5m 31 19 50

12 CONCRETE BARRIER 1.0m 140 51 49 50 60 50 400

13 BARRIER DELINEATOR 140 13 11 10 36 28 238

14 DELINEATOR STRING (ROLL) 1 1 1 3

15 BLINKERS 21 9 9 9 5 5 8 5 71

16 SUPER/GIANT CONE (1000 mm) 9 2 11

17 SAFETY CONE (70 mm) 16 90 106

18 PORTABLE FLASHING ARROW 1 1 2

19 ROBOTIC FLAGMAN 1 1

20 PORTABLE VARIABLE MESSAGING SYSTEM


0
(PVMS)

21 TRAFFIC CONTROL PADDLE 0

22 TRAFFIC CONTROL FLAG 2 2

23 TRAFFIC BATON LIGHT 2 7 9

24 IBC TANK 3 3

25 IBC TANK HOSE 1 1


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 28 FEBRUARY 2022 (FEBRUARY)

SITE STORE LDP


NO. STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE
ITEM MEDIAN (PERUNDING PMC2 TOTAL
1B 2A 4B 2B 4A 3A 3B 3C 3D 1B 3B JAS)
1 TEMPORARY TRAFFIC WARNING 19 9 10 8 9 1 4 10 70
SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 2 4 9 18 11 44

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 21 21

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 19 11 14 17 27 1 4 10 5 108

9 PLASTIC BARRIER 220 205 348 130 99 60 88 34 175 96 1455

10 PLASTIC HOARDING 164 125 294 116 26 42 41 253 96 1157

12 CONCRETE BARRIER 171 70 134 50 60 15 50 550

13 BARRIER DELINEATOR 140 24 10 36 28 238

14 DELINEATOR STRING (ROLL) *40 metres


1 1 1 3
(0.8)
15 BLINKERS 21 12 8 5 13 6 9 8 7 8 97

16 SUPER/GIANT CONE (1000 mm) 1 1

17 SAFETY CONE (70 mm) 2 4 6

18 PORTABLE FLASHING ARROW 1 1

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0

22 TRAFFIC CONTROL FLAG 2 2

23 TRAFFIC BATON LIGHT 2 2

24 IBC TANK 0

25 IBC TANK HOSE 0


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 1 APRIL 2022 (MARCH 2022)

SITE STORE LDP


NO. STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE
ITEM STAGE 3B (PERUNDING PMC2 TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E 1B 3B JAS)
1 TEMPORARY TRAFFIC WARNING 19 9 10 8 9 1 4 10 70
SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 2 4 9 18 11 44

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 1 2 3

6 SIGN POLE (LLM) 21 21

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 19 11 14 17 27 1 4 10 5 108

9 PLASTIC BARRIER 159 214 388 134 114 94 147 144 197 96 1687

10 PLASTIC HOARDING 102 124 303 116 41 42 40 151 310 96 1325

12 CONCRETE BARRIER 221 70 134 50 110 15 50 50 700

13 BARRIER DELINEATOR 140 24 10 36 28 238

14 DELINEATOR STRING (ROLL) 1 1 1 40 m 3

15 BLINKERS 20 13 12 4 12 5 12 4 23 7 9 121

16 SUPER/GIANT CONE (1000 mm) 1 1

17 SAFETY CONE (70 mm) 2 4 6

18 PORTABLE FLASHING ARROW 1 1 2

19 ROBOTIC FLAGMAN 1 1

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0

22 TRAFFIC CONTROL FLAG 0

23 TRAFFIC BATON LIGHT 0

24 IBC TANK 0

25 IBC TANK HOSE 0


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 28/04/2022 (APRIL 2022)

SITE STORE LDP


NO. STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE BIENAZ MD SHAH
ITEM STAGE 3B (PERUNDING PMC2 TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E 1B 3B EMPIRE OTHMAN
JAS)
1 TEMPORARY TRAFFIC WARNING 11 15 10 8 9 1 4 10 68
SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 2 4 9 18 11 44

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 1 2 3

6 SIGN POLE (LLM) 19 19

7 SIGN A-FRAME (JKR) 3 3

8 SIGN POLE (JKR) 11 17 14 17 27 1 4 10 5 106

9 PLASTIC BARRIER 159 212 385 134 114 96 147 118 198 96 20 25 1704

10 PLASTIC HOARDING 102 125 307 116 41 42 40 159 308 96 1336

12 CONCRETE BARRIER 221 70 134 50 110 15 50 50 700

13 BARRIER DELINEATOR 140 24 10 30 28 16 55 303

14 DELINEATOR STRING (METRE) 50 50 50 40 190

15 BLINKERS 20 13 10 4 12 5 12 5 23 7 9 120

16 SUPER/GIANT CONE (1000 mm) 1 1 2

17 SAFETY CONE (70 mm) 5 5

18 PORTABLE FLASHING ARROW 1 1 2

19 ROBOTIC FLAGMAN 1 1

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0
ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 30/06/2022 (JUNE2022)

STAGE STAGE SITE STORE


NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3E PMC2 TOTAL
3C 3D 1B 3B

1 TEMPORARY TRAFFIC WARNING 11 15 10 8 9 1 4 10 7 75


SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 2 4 9 18 11 44

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 0

7 SIGN A-FRAME (JKR) 5 5

8 SIGN POLE (JKR) 11 17 14 17 27 1 4 10 7 108

9 PLASTIC BARRIER 427 205 364 130 131 155 86 50 44 79 1671

10 PLASTIC HOARDING 101 123 309 54 59 84 50 178 425 1383

12 CONCRETE BARRIER 221 70 134 50 110 15 50 50 700

13 BARRIER DELINEATOR 140 24 10 30 28 16 248

14 DELINEATOR STRING (METRE) 50 50 50 150

15 BLINKERS 20 19 10 4 12 5 12 13 14 10 7 126

16 SUPER/GIANT CONE (1000 mm) 0

17 SAFETY CONE (70 mm) 0

18 PORTABLE FLASHING ARROW 0

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0
ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: 29/7/2022 (JULY 2022)

STAGE STAGE SITE STORE MEDIAN CREST


NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3E TOTAL
3C 3D BRIDGE 4 BUILDER
1B 3B

1 TEMPORARY TRAFFIC WARNING 11 15 10 8 9 4 12 7 10 86


SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 2 4 9 18 33

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 10 10

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 11 17 14 17 27 4 12 7 109

9 PLASTIC BARRIER 194 225 381 41 119 31 213 50 346 120 45 50 1815

10 PLASTIC HOARDING 94 144 292 43 24 71 50 157 502 1377

12 CONCRETE BARRIER 190 70 120 53 54 50 15 101 47 700

13 BARRIER DELINEATOR 136 24 10 22 6 12 210

14 DELINEATOR STRING (ROLL) 1 1 2

15 BLINKERS 22 19 7 9 12 9 5 16 10 6 115

16 SUPER/GIANT CONE (1000 mm) 1 1

17 SAFETY CONE (70 mm) 0

18 PORTABLE FLASHING ARROW 1 1 2

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0
ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (AUGUST 2022)

STAGE STAGE SITE STORE MEDIAN CREST


NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3E ENSTEK TOTAL
3C 3D BRIDGE 4 BUILDER
1B 3B

1 TEMPORARY TRAFFIC WARNING 11 11 10 8 5 4 2 9 7 10 77


SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 2 4 9 16 31

3 INFORMATION SIGNBOARD 1 1 2

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 1 2 3

6 SIGN POLE (LLM) 10 10

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 11 13 14 17 21 4 9 7 96

9 PLASTIC BARRIER 190 230 363 126 185 85 50 217 87 45 150 50 1778

10 PLASTIC HOARDING 81 142 307 43 48 70 50 71 418 150 1380

12 CONCRETE BARRIER 190 70 120 53 104 15 101 47 700

13 BARRIER DELINEATOR 136 24 23 22 13 5 223

14 DELINEATOR STRING (ROLL) 1 1 2

15 BLINKERS 24 19 9 2 12 10 12 11 10 6 115

16 SUPER/GIANT CONE (1000 mm) 1 1

17 SAFETY CONE (70 mm) 0

18 PORTABLE FLASHING ARROW 1 1 2

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0
Prepared By:

Name: Mohamad Faizul Amri


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (SEPTEMBER 2022)

STAGE STAGE SITE STORE MEDIAN FOKUS CREST


NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3E ENSTEK TOTAL
3C 3D BRIDGE 4 AWANA BUILDER
1B 3B

1 TEMPORARY TRAFFIC WARNING 10 10


SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 0

3 INFORMATION SIGNBOARD 0

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 10 10

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 0

9 PLASTIC BARRIER 351 209 368 119 129 84 50 106 103 45 50 150 1764

10 PLASTIC HOARDING 99 125 316 43 40 70 50 59 363 150 1315

12 CONCRETE BARRIER 190 70 120 53 104 15 101 47 700

13 BARRIER DELINEATOR 0

14 DELINEATOR STRING (ROLL) 0

15 BLINKERS 6 6

16 SUPER/GIANT CONE (1000 mm) 1 1

17 SAFETY CONE (70 mm) 50 50

18 PORTABLE FLASHING ARROW 1 1 2

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0
Prepared By:

Name: Mohamad Faizul Amri


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (SEPTEMBER 2022)

STAGE STAGE SITE STORE MEDIAN FOKUS CREST


NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3E ENSTEK TOTAL
3C 3D BRIDGE 4 AWANA BUILDER
1B 3B

1 TEMPORARY TRAFFIC WARNING 10 10


SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 0

3 INFORMATION SIGNBOARD 0

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 10 10

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 0

9 PLASTIC BARRIER 50 150 50

10 PLASTIC HOARDING 150 0

12 CONCRETE BARRIER 0

13 BARRIER DELINEATOR 0

14 DELINEATOR STRING (ROLL) 0

15 BLINKERS 6 6

16 SUPER/GIANT CONE (1000 mm) 0

17 SAFETY CONE (70 mm) 50 50

18 PORTABLE FLASHING ARROW 0

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0
Prepared By:

Name: Mohamad Faizul Amri


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (AUGUST 2022)

STAGE STAGE SITE STORE MEDIAN FOKUS CREST


NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3E ENSTEK TOTAL
3C 3D BRIDGE 4 AWANA BUILDER
1B 3B

1 TEMPORARY TRAFFIC WARNING 10 10


SIGNS
2 TEMPORARY DIRECTIONAL SIGNS 0

3 INFORMATION SIGNBOARD 0

4 TEMPORARY APOLOGETIC SIGN 0

5 SIGN A-FRAME (LLM) 0

6 SIGN POLE (LLM) 10 10

7 SIGN A-FRAME (JKR) 0

8 SIGN POLE (JKR) 0

9 PLASTIC BARRIER 50 150 50

10 PLASTIC HOARDING 150 0

12 CONCRETE BARRIER 0

13 BARRIER DELINEATOR 0

14 DELINEATOR STRING (ROLL) 0

15 BLINKERS 6 6

16 SUPER/GIANT CONE (1000 mm) 0

17 SAFETY CONE (70 mm) 50 50

18 PORTABLE FLASHING ARROW 0

19 ROBOTIC FLAGMAN 0

20 PORTABLE VARIABLE 0
MESSAGING SYSTEM (PVMS)
21 TRAFFIC CONTROL PADDLE 0
Prepared By:

Name: Mohamad Faizul Amri


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (AUGUST 2022)

STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE SITE STORE MEDIAN CREST
NO. ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E 1B 3B BRIDGE 4 BUILDER

1 PLASTIC BARRIER 190 230 363 126 185 85 50 217 87 45 50 150 1778

2 PLASTIC HOARDING 81 142 307 43 48 70 50 71 418 150 1380

DATE/MONTH: (JULY 2022)

SITE STORE
STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE MEDIAN CREST
NO. ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E BRIDGE 4 BUILDER
1B 3B

1 PLASTIC BARRIER 194 225 381 41 119 31 213 50 346 120 45 50 1815

2 PLASTIC HOARDING 94 144 292 43 24 71 50 157 502 1377

PERBEZAAN KUANTITI "PLASTIC BARRIER"

SITE STORE
STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE MEDIAN CREST
MONTH ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E BRIDGE 4 BUILDER
1B 3B

JULY 194 225 381 41 119 31 213 50 346 120 45 50 1815


PLASTIC BARRIER
AUGUST 190 230 363 126 185 85 50 217 87 45 50 150 1778

KURANG (-) / TAMBAH (+) -4 5 -18 - 7 +154 -128 0 -129 -33 0 0 - -37

194 50 237 88 45 50 150


*STAGE 3A (90 BARRIER MRT DISIMPAN DI 1B) - 23/6/2022
*STAGE 1B-2 (233 BARRIER (MRT=184, SHERATON=49) TELAH DISIMPAN DI 1B) - 27/6/2022
*50 BARRIER MRT ACTIVATE DI CREST BUILDER (1/7/2022)
*50 BARRIER MRT SIMPAN DI 1B (JS) - 30/62022
*(9 BARRIER RASB) SIMPAN DI SITE STORE 3B (28 BARRIER RASB) SIMPAN DI SITE STORE 1B - 13/7/2022 (STOR)
*STAGE 3A (DEACTIVATE 41 BARRIER MRT 21 MERAH 20 PUTIH DISIMPAN SITE STORE 1B) - 1/8/2022
*STAGE 3C & 3D (DEACTIVATE 3D/ACTIVATE 3C, 50 BARRIER MRT (25 MERAH 25 PUTIH) DISIMPAN DI 3C)
*SEWA BARRIER & HOARDING (ENSTEK) NILAI, 150 BARRIER & 100 HOARDING (AMBIL DI SITE STORE 1B), 50 HOARDING (AMBIL DI SITE STORE 3B)
* TOTAL SEPATUTNYA BERDASARKAN BULAN AUGUST DI SITE STOR 1B SELEPAS STAGE 3A DAN 1B-2 DEACTIVATE DAN BAWA BARRIER DI STOR KE 1B ADALAH 437, DISEWA KE NILAI DAN CREST BUILDER SEBANYAK 200 BARRIER. (437-200 = 237)
PERBEZAAN KUANTITI "PLASTIC HOARDING"

SITE STORE
STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE MEDIAN CREST
MONTH ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E BRIDGE 4 BUILDER
1B 3B

JULY 94 144 292 43 24 71 50 157 502 1377


PLASTIC HOARDING
AUGUST 81 142 307 43 48 70 50 71 418 150 1380

KURANG (-) / TAMBAH (+) -13 -2 +15 0 +24 -1 0 -86 -84

57 450

*SEWA BARRIER & HOARDING (ENSTEK) NILAI, 150 BARRIER & 100 HOARDING (AMBIL DI SITE STORE 1B), 50 HOARDING (AMBIL DI SITE STORE 3B)

*52 HOARDING MRT SIMPAN DI SITE STORE 3B - 13/7/2022


ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (AUGUST 2022)

STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE SITE STORE MEDIAN CREST
NO. ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E 1B 3B BRIDGE 4 BUILDER

1 PLASTIC BARRIER 190 230 363 126 185 85 50 217 87 45 50 150 1778

2 PLASTIC HOARDING 81 142 307 43 48 70 50 71 418 150 1380

DATE/MONTH: (JUNE 2022)

SITE STORE
STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE MEDIAN CREST
NO. ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E BRIDGE 4 BUILDER
1B 3B

1 PLASTIC BARRIER 427 205 364 130 131 155 86 50 44 79 45 1716

2 PLASTIC HOARDING 101 123 309 54 59 84 50 178 425 1383

PERBEZAAN KUANTITI "PLASTIC BARRIER"

SITE STORE
STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE MEDIAN CREST
MONTH ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E BRIDGE 4 BUILDER
1B 3B

JUNE 427 205 364 130 131 155 86 50 44 79 45 1716


PLASTIC BARRIER
AUGUST 190 230 363 126 185 85 50 217 87 45 50 150 1778

KURANG (-) / TAMBAH (+) -237 +25 -1 - -5 +30 -1 0 +173 +8 0 0 - +62

194 50 237 88 45 50 150


*STAGE 3A (90 BARRIER MRT DISIMPAN DI 1B) - 23/6/2022
*STAGE 1B-2 (233 BARRIER (MRT=184, SHERATON=49) TELAH DISIMPAN DI 1B) - 27/6/2022
*50 BARRIER MRT ACTIVATE DI CREST BUILDER (1/7/2022)
*50 BARRIER MRT SIMPAN DI 1B (JS) - 30/62022
*(9 BARRIER RASB) SIMPAN DI SITE STORE 3B (28 BARRIER RASB) SIMPAN DI SITE STORE 1B - 13/7/2022
*STAGE 3A (DEACTIVATE 41 BARRIER MRT 21 MERAH 20 PUTIH DISIMPAN SITE STORE 1B) - 1/8/2022
*STAGE 3C & 3D (DEACTIVATE 3D/ACTIVATE 3C, 50 BARRIER MRT (25 MERAH 25 PUTIH) DISIMPAN DI 3C)
*SEWA BARRIER & HOARDING (ENSTEK) NILAI, 150 BARRIER & 100 HOARDING (AMBIL DI SITE STORE 1B), 50 HOARDING (AMBIL DI SITE STORE 3B)
*TOTAL SEPATUTNYA BERDASARKAN BULAN AUGUST DI SITE STOR 3B SELEPAS BAWA BARRIER DARI STOR ADALAH 88. (79+9 = 88)
* TOTAL SEPATUTNYA BERDASARKAN BULAN AUGUST DI SITE STOR 1B SELEPAS STAGE 3A DAN 1B-2 DEACTIVATE DAN BAWA BARRIER DI STOR KE 1B ADALAH 437, DISEWA KE NILAI DAN CREST BUILDER SEBANYAK 200 BARRIER. (437-200 = 237)
PERBEZAAN KUANTITI "PLASTIC HOARDING"

SITE STORE
STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE STAGE MEDIAN CREST
MONTH ITEM STAGE 3B ENSTEK TOTAL
1B 2A 4B 2B 4A 3A 3C 3D 3E BRIDGE 4 BUILDER
1B 3B

JUNE 101 123 309 54 59 84 50 178 425 1383


PLASTIC HOARDING
AUGUST 81 142 307 43 48 70 50 71 418 150 1380

KURANG (-) / TAMBAH (+) -20 +19 -2 -11 -11 -14 0 -107 -7 -3
*116 HOARDING DARI 3A SIMPAN (DI SITE STORE 3B) 12/6/2022 78 427
*SEWA BARRIER & HOARDING (ENSTEK) NILAI, 150 BARRIER & 100 HOARDING (AMBIL DI SITE STORE 1B), 50 HOARDING (AMBIL DI SITE STORE 3B)
*52 HOARDING MRT SIMPAN DI SITE STORE 3B - 13/7/2022
*TOTAL SEPATUT BERDASARKAN BULAN 8 DI SITE STORE 3B ADALAH (425+52-50 = 427)
*TOTAL SEPATUT BERDASARKAN BULAN 8 DI SITE STORE 1B ADALAH (178-100 = 78)
ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (AUGUST 2022)

SITE STORE
NO. MEDIAN CREST
ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3C STAGE 3D STAGE 3E BRIDGE 4 ENSTEK TOTAL
BUILDER
1B 3B

1 PLASTIC BARRIER 190 230 363 126 185 85 50 217 87 45 50 150 1778

2 PLASTIC HOARDING 81 142 307 43 48 70 50 71 418 150 1380

ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (SEPTEMBER 2022)

SITE STORE
MEDIAN CREST
NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3C STAGE 3D STAGE 3E ENSTEK TOTAL
BRIDGE 4 BUILDER
1B 3B

1 PLASTIC BARRIER 338 213 369 126 131 85 50 117 97 45 50 150 1771

2 PLASTIC HOARDING 81 127 313 43 42 70 50 71 433 150 1380

ROAD ARK SDN BHD

LIST OF TRAFFIC MANAGEMENT CONTROL & DEVICES

DATE/MONTH: (20 SEPTEMBER 2022)

SITE STORE
MEDIAN CREST
NO. ITEM STAGE 1B STAGE 2A STAGE 4B STAGE 2B STAGE 4A STAGE 3A STAGE 3B STAGE 3C STAGE 3D STAGE 3E ENSTEK TOTAL
BRIDGE 4 BUILDER
1B 3B

1 PLASTIC BARRIER 351 209 368 119 129 84 50 106 103 45 50 150 1764

2 PLASTIC HOARDING 99 125 316 43 40 70 50 59 363 150 1315

Tambah Barrier/Hoarding di Stage 2B (6 Nos Barrier, 6 Nos Hoarding) - 12/9/2022

Kumpul Barrier/Hoarding (2A/4B), simpan di site store 3B. (Barrier 17 Nos, Hoarding 15 Nos) - 13/9/2022

Prepare Barrier MRT (Activate 1B-1) 148 Nos - 15/9/2022