UTMN-2094 FLOW LINE WEEKLY UPDATE

P.O ISSUE DATE : MCC DATE : CUT OF DATE : 03-JULY-2020


TOTAL
TOTAL PREVIOUS WEEK THIS WEEK COMPLETED
SL.NO ACTIVITY QUANTITY UNIT QTY QUANTITY QUANTITY

1 RIGHT OF WAY 3398 LM 3200

2 FLOW LINE EXCAVATION 3398 LM 100%

3 FLOW LINE WELDING 267 JOINTS 15 100%

4 EXTERNAL GIRTH WELD COATING 267 JOINTS 20 10 257

5 MARL ROAD CROSSINGS 5 EACH 100%

6 ASPHALT ROAD CROSSING 1 EACH 100% 100%

7 UNDER GROUND P/L CROSSINGS 4 EACH 10% 100%

8 POD CROSSINGS 3 EACH 100%

9 PIPE LOWERING 3398 LM 100%

10 CP SINGLE PIN TERMINALS 3 EACH 100% 100%

11 CP BONDING BOX INSTALLATION 5 EACH 50% 80%

12 KM MARKER INSTALLATION 3 EACH

13 PIPE MOVEMENT MARKER 4 EACH

14 WARNING BOARD 10 EACH

15 BACK FILLING 3398 LM 200 3300

16 BERMING 3398 LM 500 600 2500

REQUIREMENT NOTIFICATION

QTY CONFIRM QTY APPROVED


BY SITE BY ENGINEERING
SL.NO ITEMS REQUIRED DATE SIZE QUANTITY ENGINEER HEAD

SUB CONTRACTOR INCHARGE