UTMN-2294 FLOW LINE WEEKLY UPDATE

P.O ISSUE DATE : MCC DATE : CUT OF DATE : 13-SEP-2020


TOTAL
TOTAL PREVIOUS WEEK THIS WEEK COMPLETED
SL.NO ACTIVITY QUANTITY UNIT QTY QUANTITY QUANTITY

1 RIGHT OF WAY 6279 LM 6000

2 FLOW LINE EXCAVATION 6279 LM 80 6130

3 FLOW LINE WELDING 495 JOINTS 11 3 471

4 EXTERNAL GIRTH WELD COATING 495 JOINTS 133 399

5 MARL ROAD CROSSINGS 7 EACH 3 completed

6 ABOVE GROUND P/L CROSSINGS 4 EACH 90%

7 UNDER GROUND P/L CROSSINGS 8 EACH 60%

8 POD CROSSINGS 7 EACH 80%

9 UNDER GROUND CABLE CROSSINGS 7 EACH 2 completed 6 completed

10 PIPE LOWERING 6279 LM 1300 5900

11 CP SINGLE PIN TERMINALS 6 EACH

12 CP BONDING BOX INSTALLATION 8 EACH

13 KM MARKER INSTALLATION 6 EACH

14 PIPE MOVEMENT MARKER 16 EACH

15 WARNING BOARD 14 EACH

16 BACK FILLING 6279 LM 1100 250 5750

17 BERMING 6279 LM

REQUIREMENT NOTIFICATION
QTY CONFIRM QTY APPROVED
BY SITE BY ENGINEERING
SL.NO ITEMS REQUIRED DATE SIZE QUANTITY ENGINEER HEAD

SUB CONTRACTOR INCHARGE


RECEIVED NOTIFICATION
QUANTITY
SL.NO ITEMS RECEIVED DATE RECEIVED TOTAL RECEIVED
1 8" PIPE 25-Jul-20 60 450
2 8'' BEND PIPE 11-Aug-20 20 45
TOTAL 495

PERSONNEL INFORMATION
NO. OF DAYS
CAME IN THIS
SL.NO NAME DESIGNATION WEEK
1 Mr. BALAMURGAN WELDING QC 2
2 Mr. Kamlesh COATING QC 1
3 Coating Crew 4 persons 1