GASAN BY PASS

PIPE CULVERT

DENNIS RAMOS
CONS./FAB OF RCCP, 36"Ø FOR PIPE CULVERT
JO UNIT U.PRICE NOV13-19 NOV20-26 NOV27-DEC3
DEC4-10 DEC11-17 DEC11-31 JAN2-8 JAN8-14 TOTAL
CONCRETE WORKS 104 LM 600 13 11 12 15 CA 29 14 10 104
62400
AMOUNT 7800 6600 7200 9000 10000 7400 8400 6000 62400
RETENTION 780 660 720 900 1740 840 600 6240
RELEASE 7020 5940 6480 8100 10000 5660 7560 5400 56160
100%

GILBERT LANO
CONS./FAB OF RCCP, 36"Ø for Crane Way and Septic tank
JO UNIT U.PRICE FEB26-MARCH10
CONCRETE WORKS 22 LM 600 22
13200
AMOUNT 13200
RETENTION
RELEASE 13200

GILBERT LANO
CONS./FAB OF RCCP, 24"Ø FOR LGU MOTORPOOL
JO UNIT U.PRICE JULY2-15
CONCRETE WORKS 9 LM 500 9
4500
AMOUNT 4500
RETENTION
RELEASE 4500

GILBERT LANO
CONS./FAB OF RCCP, 36"Ø FOR CRANE WAY
JO UNIT U.PRICE JULY30-AUG12
CONCRETE WORKS 10 LM 600 10
6000
AMOUNT 6000
RETENTION
RELEASE 6000
GARY CANTURA
*2 PIPE WILL BE REFLECTED IN ASBUILT
INST. OF PIPE CULVERT JO UNIT U.PRICE FEB26-MARCH10
38 LM 250 38

AMOUNT 9500
RELEASE 9500

RODRIGO LONTOC

INST. OF PIPE CULVERT JO UNIT U.PRICE JULY2-15


36 LM 250 36

AMOUNT 9000
RETENTION 900
RELEASE 8100

NOTE: EXCESS PIPE WAS USED IN RECONSTRUCTION OF DAMAGED CRANEWAY (TWICE)