Professional Documents
Culture Documents
Chapter 1
Contract Basics
The first chapter presents the basic information a construction
contractor needs to know about contract law. It describes contract
"Start with what characteristics including:
is right rather
than with what is ■ The four elements
acceptable." ■ Terms and conditions
Peter Drucker ■ Classifications of contracts
■ Breach
■ Damages
Contract Characteristics
A contract is an agreement or promise between two or more parties
to do, or not to do, a specific act. A contract may be expressed in words
(oral or written) or implied (shown by acts).
A valid contract is one that has all of the four elements and is in the
proper form (written if mandated by law).
2
Note
Each state will have slightly different laws affecting
contracts. The basics described in this chapter will apply
to all contracts.
Negotiation
The formation of a valid construction contract is the end product of
Offer
An offer is a promise made by one party to do, or not to do, a specific
act. This promise is an offer when it defines the promised action
clearly enough to be easily understood.
Time Limitations
Most offers have a deadline for acceptance. In the proposal (and/or
bid) there is normally a specified time limit for the duration of an
offer (typically 30 days).
If the firm offer does not stipulate a specific time frame, the reasonable
time usually cannot exceed three months.
I
Warning
When submitting a bid, you as a contractor are entering
into a binding contractual relationship as described by
your bid documents.
Acceptance
Typically, the owner (offeree) shows acceptance of the offer by
signing the contractor’s (offeror’s) proposal.
Often the owner is interested in doing business, but not under the
terms expressed in the original offer. When this is the case, a If the assump-
counteroffer can be made. tions are wrong,
the conclusions
Counteroffer aren't likely to be
A counteroffer has the effect of switching the roles of offeror and very good.
offeree.
A counteroffer is not an acceptance and does not in any way bind the
original offeror to the initial offer made. In essence, a counteroffer
nullifies a previous offer.
2
Note
Do not interpret all continued bargaining as counterof-
fers. Fine tuning a contract is not the same as nullifying
a contract. As long as the terms being discussed are
consistent with the original intent of the agreement,
there is no reason to consider fine tuning as jeopardizing
previous negotiations.
Consideration
Consideration is defined as the promised activity of each party in
completing the contract. All parties entering into a contract provide
consideration.
2
Note
Consideration should be clearly stated in the contract and
easy to determine. It can be money, property, or a promise
to do or not to do something.
Payment
There are two standard methods used to describe the means of
payment in the contract:
Legally Sufficient
The consideration element of a contract has to be legally sufficient.
2
Note
A contract between two minors is void. In addition, a
contract between a person of legal age and a minor is
voidable. (see "Status of a Contract" later in this section)
P Tip
Be especially aware of this possibility when dealing with
the remodeling of rental units. If someone has a history of
representation for another, then legal capacity can be
established.
Legal Purpose
A contract has to have legal purpose and be possible to perform. For
instance, a contract to kill or steal is clearly invalid.
Example 1:
P Tip
We urge you to put your agreement(s) in writing. How-
ever, if you choose not to, keep an accurate and complete
record of expenses. If there is a dispute, you will need the
following types of evidence to support your claim:
■ Receipts
■ Invoices
■ Canceled checks
■ Journal of your daily business activities
Even though only certain contracts have to be in writing, you should make it a practice to put all of your
agreements in writing. There is simply no better way to prevent disputes. If an owner does not want a written
agreement, abandon the effort to bid the project. Let someone else get the problem.
Integration Clause
The integration clause is typically part of the general conditions of
a construction contract. It states that the agreement signed, and the
contract documents attached (integrated), constitute the entire and
only agreement.
Any modifications to the agreement would have to be done through "There are a
a proper procedure (for example, a change order) as described in the million things in
document. this universe you
can have, and
Terms and Conditions there are a million
Terms and conditions are stipulations within a contract document things you can't
that qualify the general terms of the contract. have. It's no fun
facing that, but
Specifically, each condition agreed on will have its own legal that's the way
significance within the context of the document. Some of these things are."
specific conditions will be covered in "Chapter 2: Your Construction Captain Kirk,
Contract." Star Trek
Condition Precedent
A condition precedent is something that has to happen first, before
an obligation can take effect.
Condition Subsequent
A condition subsequent is one that tends to free a party from
obligation. An example would be an insurance company denying
liability for damages resulting from an illegally installed wood
stove.
Ignorance of the
law is what keeps
our court sys-
tems busy.
Contract Classifications
Contracts are classified based on the following four criteria:
■ Creation of intent
■ Formation of the contract
■ Status of a contract
■ Enforceability of a contract
Creation of Intent
Intent is the heart of the contract. Courts will attempt to interpret
a contract based on the intent of the parties to the agreement. If the
intent is not discernible, the courts can consider the contract
unenforceable.
■ Expressed contract
■ Implied contract
■ Quasi contract
Expressed Contract
The terms and conditions of an expressed contract are clearly stated
in oral or written words. This should be the case for most construction
projects.
Implied Contract
An agreement between two parties can be implied from specific
circumstances. When requesting the services of a professional,
This concept would also hold true if the contract was made by a
contractor who was not correctly licensed or registered at the time
of the signing of the agreement. Under state law, where contractors
are required to be licensed or registered, a noncomplying contractor
gives up most of the normal remedies enforceable in court. A quasi
contract is one of the few benefits available. (For a related concept
see "Quantum Meruit," under "Damages" later in this chapter.)
I
Warning
A noncomplying contractor does not have the same pro-
tection under the law as a complying contractor. While
the contract may not be declared completely void, the
noncomplying contractor is normally not judged by the
court as a competent party to a construction contract.
They have not fulfilled the conditions of a contractor
under the law.
Unilateral Contract
A unilateral contract comes into being when one party’s acceptance
is contingent upon another’s action or restraint from action.
Status of a Contract
The status of a contract is expressed as either executed or executory.
Executed Contract
An executed contract is one in which the performance of the
agreement has been completed. Sometimes the term "executed" is
used to denote a contract that simply has been signed.
Executory Contract
An executory contract is one in which there is still unfinished
business. The project is not finished and/or the final payment has
"Laws are never as not been made.
effective as habits."
Adlai Stevenson
Enforceability of a Valid Contract
An enforceable contract is:
Void Contract
A void contract is a contract that is not legal (not valid). In essence,
there never was a contract in the first place because one of the four
elements was missing, or it was not in the proper form (written) as
required by statute.
Voidable Contract
A voidable contract indicates that one of the contracting parties has "There is no
a right to terminate responsibility regarding the agreement. country in the
world in which
For example, a minor would have the option to void a contract to everything can be
which he or she is a party. provided for by
the laws, or in
Unenforceable Contract which political
An unenforceable contract is one that does not meet some statutory institutions can
requirement, has non-definitive, non-understandable terms and/or prove a sub-
stitute for
intent, or is non-construable.
common sense
and public mor-
Promissory Estoppel Rule
ality."
Promissory estoppel is a rule of law that says that if a promise is
DeTocqueville
made and another person has been placed in a position of reliance
on that promise, the promisor is estopped (prevented) from denying
the responsibility of that promise.
This rule comes into play especially when dealing with subcontracts.
A general contractor who has used a subcontractor’s bid as a basis for
the contract price has established justifiable reliance on that
subcontractor’s bid.
I
Warning
Degrees of Breach
There are degrees of breach that determine if the breach is material
or nonmaterial.
Claiming a Breach
A typical defense for breach of contract is to claim that the other guy
breached first:
I never was ruined
but twice: once I "He didn’t do what he was supposed to do, so I don’t have to do what
lost a lawsuit, and I’m supposed to do."
the second time
when I won a This may seem reasonable but remember two things:
lawsuit.
■ First, the burden of proof is on the party claiming breach
of contract. If you allege breach of contract and the other
party claims that there was no agreement to begin with,
then not only would you have to prove breach of contract,
but you would also have to prove the contract was valid.
■ Second, even if a breach exists and a valid contract has
been proven, the question still remains whether the breach
is a material breach.
I
Warning
Not all breaches of contract will free the offended party
from the obligation to perform what they promised.
A contractor who mistakenly walks off the job, thinking the owner
has materially breached, could instead find himself in material
breach. The courts could find the contractor liable for damages to
the owner.
P Tip
There are many legal avenues for litigating (to bring
court action against) breach of contract.
Before you decide to go to court, consider the fact that even if you
win, you may lose your shirt as far as money is concerned. You may
not recover all of your costs and the court process could take a very
long time to complete.
2
Note
There are options to litigation. Negotiation and compro-
mise are a lot less expensive. Mediation and arbitration
are other options. See Chapter 4 of this course.
Damages
Damages are losses caused to one party of the contract as a result of
breach by the other party.
■ Punitive damages
■ Compensatory damages
■ Liquidated damages
Compensatory Damages
Compensatory damages are compensation to a party deprived of
contracted-for-services and/or payment for services.
General Damages
General damages are the money and/or service needed to make up
the difference between the performance promised and the
performance given.
Special Damages
Special damages are awarded on the basis of additional expenses
and/or loss of revenue incurred as a result of the inadequate
performance of another.
Liquidated Damages
Liquidated damages is a term associated with the timely completion
of a construction project. It comes into play when the contractor does
not finish the project. Liquidated damages are amounts of money
awarded as compensation for costs incurred by the owner as a result "You can have
of a project delay. anything you
want, but you
As a contractor, you will see and hear this term often. A clear can't have every-
understanding of the legal intentions behind the assessment of such thing you want."
damages will be of great value in your negotiation with the owner Wealth 101
and other contractors.
One thing that a contractor should be aware of is that the courts will
examine a liquidated damages clause very closely. They recognize
that unequal negotiating power can exist. Thus, the courts can
mandate that such clauses represent reasonable and fair conditions
for all parties of the agreement.
2
Note
The penalty stated in the contract has to reflect the degree
of damage.
If the time factor is not clearly indicated in the contract, then the
courts will determine whether such a condition actually exists in the
intent.
P Tip
Because it is not always possible to refuse such time
penalty clauses, (even if you can, the courts may later rule
that "time is of the essence" was implied), then negotiat-
"Instincts are no
match for infor-
mation."
ing a time reward clause may be the next best option.
Harvey Mackay
2
Note
In public construction projects, "no damage for delay"
clauses would normally be interpreted as being contrary
to public policy and would be considered void and unen-
forceable.
I
Warning
If you are the primary contractor, a "no damage for delay"
clause may sound tempting. But there are two possibilities
in this clause. Consider the possible consequences if this
clause prevented you from recovering damages to you
resulting from delays caused by subcontractors.
2
Note
Because of such possible variations in the precise meaning
of substantial completion, this term needs to be defined
within the context of your contract to promote mutual
understanding of its meaning.
■ Negligent work
■ Improper work
■ Breach of contract
This claim would have to qualify under the claim terms. Usually the
claim amount has to be under a certain minimum dollar amount
and subject to the decision of the agency arbitrator or hearings
officer. In most cases these claim processes are designed to resolve
smaller, less complicated disputes. Larger or more complex cases go
to a court of law.
2
Note
This is an important legal distinction. An owner’s claim of
breach may be handled by the licensing or registration
agency. However, claims by contractors against owners
are normally dealt with in court, as are liens and suits.
Time of Limitations
Claims handled by the state licensing or registration agencies
usually require a quick disposition.
Claims of this nature often arise from a lack of clarity within the
contract documents themselves. Unrealistic expectations by the
owners are usually the main culprit leading to claims of breach.
P Tip
Knowing in what way an owner is entitled to recover
damages is necessary in order to know your expected
responsibilities as a contractor.
However, even without such wording, the owner will have implied
rights to reasonable work.
The only people who
enjoy hearing your Cost of Replacement or Repair Rule
troubles are When economically feasible, the owner is entitled to be reimbursed
lawyers, and they for the cost of replacing or fixing anything the contractor did not do
are paid to do it. properly.
If you choose court action, you may be able to use your state's small
claims process for disputes less than the minimum dollar amount
established by law. For action involving an amount greater than
the minimum, litigation would have to take place in a higher court
of proper jurisdiction.
I
Warning
Litigation would normally involve hiring an attorney. In
general, many state courts do not allow for the recovery of
the cost of attorney’s fees. The prevailing (winning) party
can recover costs of legal counsel only if it is stated in the
contract.
However, these criteria are not adequate evidence for proof of one’s
actual costs and profit. Details showing the reasonable certainty of
such lost profits would be required. A thorough and accurate record
keeping system would usually provide such evidence. (More
Suppose the contract was to build new steps to the front porch. The
owner has given the contractor the go ahead and tells the contractor
to do whatever it takes to get the project done.
The contractor discovers that half the porch is rotten. The owner is
now out of town. The contractor rebuilds the rotten porch to facilitate
the building of the steps.
I
Warning
Be aware that it is the contractor’s responsibility to prove,
with reasonable certainty, that the work performed was in
the best interest of the owner, and that the cost of the
additional work is reasonable.
Cardinal Change
The principle of cardinal change is similar to the concept of "as much
as he deserved."
and no subsequent contract was made for the additional work, There are two
under the cardinal change criteria and the principle of quantum types of experts:
meruit, the paint contractor could claim entitlement to reasonable There is the expert
compensation for the work done. who can make
something happen,
Generally speaking, the intent of the law is just compensation for and there is the
work done. The key words are reasonable and certainty. expert who can tell
you what he or she
The value attached to the work in question has to be established thinks will happen.
with reasonable certainty. The evidence of lost profits has to be
reasonable in scope. Profits not realized from other projects "down
the road" typically are not recoverable as lost profits connected with
the project in question.
Avoidable Consequences
The sense of what is reasonable is contained in another concept of
law—avoidable consequences.