Dear Sir:
In response to your request, we are pleased to submit herewith our best offer
to conduct air stack emission test and analysis of your Emission Source Equipment
for Two (2) units 300HP “Cyclotherm” Boiler with single smoke stack and no
water scrubber and One (1) unit 350HP “Cleaver Brooks” Boiler with single
smoke stack and no water scrubber at three (3) runs/stack located at the above
address.
1.2 Preparation of Test Plan for submission by the client to DENR- Reg.
XI upon signing of both client’s PCO representative and Accredited
Team Leader or Quality Assurance/Quality Control of accredited
testing firm fifteen (15) days advance before the on-site testing;
2.4 Install provision for safety sampling protection such as platflorm with
railings, ladder with cage, I-bolt for monorail carrying 20 - 25 kls of
equipments and clip in accordance with the DENR Standard;
2.5 The Client shall operate the Generator Set of atleast thirty (30%)
operating load capacity for standby generator set and ninety (90%) for
continuous operations as per DENR requirement during the
performance of air emission testing.
2.6 Submit test plan prepared by the 3rd party testing firm to DENR- EMB,
Region XI, fifteen (15) days advance prior to the schedule of on-site
testing.
For and in consideration of the above scope of work, our service fee shall be
as follows:
Price is subject for confirmation after the price validity period due to
unavailability of controlled chemicals.
If you have any queries on this proposal, please feel free to contact us.
Thank you for this opportunity to quote and we are looking forward to serve your
environmental requirements.