Method Statement

Orascom Construction
Greater Cairo Metro Line 3 Phase 3

Method of statement

Location: Imbab Workshop-EMSP-Crane Beams

Project: Greater Cairo Metro Line 3 Phase 3

Date: Tue, Nov 17, 2022

Revision 00

Prepared by:

Eng. Luka Saber

Project Manager

Engineering and Services Tech EAST

Engineering and Services Technology S.A.E. Page 1 of 6


ELHEG00081216

30 St. 276 New Maadi, Cairo, Egypt. BANK Commercial International Bank (CIB) VAT 859-189-200
TEL. +20 225 1933 81 (82) BRANCH 67 Road 9 Maadi, Cairo, Egypt CR 4666
FAX +20 225 1933 81 SWIFT CIBEEGCX 012 CHAIRMAN Eng. Ragai Abdel Malek
E-Mail info@east-eg.com ACC 1000136932578 EGP CEO Eng. Kamal Abdel Malek
W-SITE www.east-eg.com 1000136932578 EGP
1000136932578 EGP
The purpose of this document is to outline the working sequence of Erection of Crane Beams in EMSP building.

Engineering and Services Technology S.A.E. Page 2 of 6


ELHEG00081216

30 St. 276 New Maadi, Cairo, Egypt. BANK Commercial International Bank (CIB) VAT 859-189-200
TEL. +20 225 1933 81 (82) BRANCH 67 Road 9 Maadi, Cairo, Egypt CR 4666
FAX +20 225 1933 81 SWIFT CIBEEGCX 012 CHAIRMAN Eng. Ragai Abdel Malek
E-Mail info@east-eg.com ACC 1000136932578 EGP CEO Eng. Kamal Abdel Malek
W-SITE www.east-eg.com 1000136932578 EGP
1000136932578 EGP
 Kindly refer to associated Risk assessment

PPES
Safety shoes - Safety Helmet - Safety Built- Anti cut gloves 5 – Welding Gloves – Welding Apron - Welding Mask -
welding Glasses– safety goggles – Full Face Mask – Ear Muffs - Dust Mask- Safety harness double hock

Engineering and Services Technology S.A.E. Page 3 of 6


ELHEG00081216

30 St. 276 New Maadi, Cairo, Egypt. BANK Commercial International Bank (CIB) VAT 859-189-200
TEL. +20 225 1933 81 (82) BRANCH 67 Road 9 Maadi, Cairo, Egypt CR 4666
FAX +20 225 1933 81 SWIFT CIBEEGCX 012 CHAIRMAN Eng. Ragai Abdel Malek
E-Mail info@east-eg.com ACC 1000136932578 EGP CEO Eng. Kamal Abdel Malek
W-SITE www.east-eg.com 1000136932578 EGP
1000136932578 EGP
 Roller Skid
 Leveling instrument
 Loading hand pallet
 power cables
 Crane
 Manual Tools

 Scissors lift
 Spanners-wrenches
 Cables and wires
 Painting brushes
 Steel Brushes
 Manual erection tools
 Chain Blocks
 staircase platform
 steel wire (8mm)

Engineering and Services Technology S.A.E. Page 4 of 6


ELHEG00081216

30 St. 276 New Maadi, Cairo, Egypt. BANK Commercial International Bank (CIB) VAT 859-189-200
TEL. +20 225 1933 81 (82) BRANCH 67 Road 9 Maadi, Cairo, Egypt CR 4666
FAX +20 225 1933 81 SWIFT CIBEEGCX 012 CHAIRMAN Eng. Ragai Abdel Malek
E-Mail info@east-eg.com ACC 1000136932578 EGP CEO Eng. Kamal Abdel Malek
W-SITE www.east-eg.com 1000136932578 EGP
1000136932578 EGP
1. Steel beams
2. Bolts
3. Nuts
4. Washers

 Safety officer: Kareem Elgamal


 Site Engineer: Ahmad Abdul-Baset
 QC Engineer: Amr Galal
 Supervisor: Adel Abdul Kader
 Two Erectors & Three Helpers

 Permit work will be approved before actual work done


 Crane beams to be stored beside EMSP building using forklift in the approved area by Engineering and Safety
department.
 Storing using forklift certified and approved by safety department.
 labors wearing all required PPES will help forklift to arrange material (plates, bolts, nuts, washers, etc…)

 Permit work will be approved before actual work done


 Each beam is a Built up section with 500 kg weight
 labors wearing all required PPES will help forklift to arrange steel sections.

1. Isolate working area with cones and caution tapes from both sides and a barrier
2. Crane 100 ton to lift the beams from the storing area beside the EMSP to its final position (as shown in the pics)
3. Listing the beams is according to the approved lifting plan.
4. Fixing the beams using bolts & nuts
5. Tightening the bolts using spanners.
6. Labors to use safety belts during execution

Engineering and Services Technology S.A.E. Page 5 of 6


ELHEG00081216

30 St. 276 New Maadi, Cairo, Egypt. BANK Commercial International Bank (CIB) VAT 859-189-200
TEL. +20 225 1933 81 (82) BRANCH 67 Road 9 Maadi, Cairo, Egypt CR 4666
FAX +20 225 1933 81 SWIFT CIBEEGCX 012 CHAIRMAN Eng. Ragai Abdel Malek
E-Mail info@east-eg.com ACC 1000136932578 EGP CEO Eng. Kamal Abdel Malek
W-SITE www.east-eg.com 1000136932578 EGP
1000136932578 EGP
Engineering and Services Technology S.A.E. Page 6 of 6
ELHEG00081216

30 St. 276 New Maadi, Cairo, Egypt. BANK Commercial International Bank (CIB) VAT 859-189-200
TEL. +20 225 1933 81 (82) BRANCH 67 Road 9 Maadi, Cairo, Egypt CR 4666
FAX +20 225 1933 81 SWIFT CIBEEGCX 012 CHAIRMAN Eng. Ragai Abdel Malek
E-Mail info@east-eg.com ACC 1000136932578 EGP CEO Eng. Kamal Abdel Malek
W-SITE www.east-eg.com 1000136932578 EGP
1000136932578 EGP
‫‪rev.00‬‬ ‫تقييم المخاطر العمال مشروع ال ‪Greater Cairo Metro Line 3 Phase 3‬‬

‫‪17-Nov-2022‬‬ ‫التاريخ ‪:‬‬ ‫اعمال المشروع‬ ‫‪EMSP‬‬ ‫تكنولوجيا الهندسة و الصيانة إيست‬ ‫المقاول ‪:‬‬

‫تقييم الخطر النهائى‬ ‫تقييم الخطر المبدئى‬


‫منخفض‪/‬‬ ‫منخفض‪/‬‬
‫متوسط ‪/‬‬
‫االحتمالية‬ ‫شدة الخطر‬
‫تحديد وسائل التحكم‬ ‫متوسط ‪/‬‬
‫االحتمالية‬
‫شدة‬ ‫تحديد المخاطر‬ ‫المهام المصاحبة للعمل‬ ‫العمل‬
‫عالى ‪ /‬غير‬ ‫عالى ‪ /‬غير‬ ‫الخطر‬
‫مقبول‬ ‫مقبول‬
‫• يتم التنسيق مع االدارة الهندسية بالموقع قبل بدء العمل‬
‫• االلتزام بتعليمات مسؤلي السالمة والصحة المهنية اثناء التركيب‬
‫• فحص جميع المعدات المستخدمة والـتأكد من مراجعتها من قبل مشرف االدارة الهندسية ومشرف السالمة الخاص بالمقاول‬
‫قبل البدء في العمل‬
‫• فحص جميع الوصالت الكهربائيه والتأكد من مطابقتها للمعايير المطلوبه بمعرفه االداره الهندسيه قبل اللحام‬
‫دخول العمال الى‬
‫منخفض‬ ‫‪1‬‬ ‫‪1‬‬ ‫• شرح محاضرة للعاملين تبين مخاطر العمل وضرورة االلتزام بتعليمات السالمة والصحة المهنية‬ ‫متوسط‬ ‫‪3‬‬ ‫‪3‬‬ ‫عدم معرفة العمال طبيعة المكان‬ ‫التجهيز لبدء االعمال‬
‫موقع العمل‬
‫• عمل تصاريح العمل العادية والساخنة واعتماد التصاريح والتوقيع عليها من المسئولين والموافقة علية‬
‫• عزل المنطقة اثناء العمل وعمل شريط تحذيري وأقماع حول منطقة العمل‬
‫• وجود طفايه حريق بجوار منطقه العمل في حالة االعمال الساخن‬
‫• ارتداء العاملين لمهمات الوقاية الشخصية ( خوذه ‪ -‬نظارة ‪ -‬سدادة اذن ‪ -‬فيست ‪ -‬حذاء سالمة ‪ -‬جونتي ضد القطع ‪-5‬‬
‫نظاره قطعيه ‪-‬جونتي)‬
‫• التنسيق مع االداره الهندسيه لمنع مرور العمال فى الممرات اثناء العمل‬
‫• فحص المعدات المستخدمة اثناء التشوين ( كالرك ‪ -‬ونش )‬
‫• فحص الكالرك والونش قبل البدء فى العمل‬
‫• فحص ادوات الرفع والتصبين الخاصة بالونش ومراجعة جدول احمال الونش‬
‫• مراجعة شهادات معايرة الونش وكفاءة السائق والبحري‬
‫أعمال رفع كمرة‬
‫منخفض‬ ‫‪2‬‬ ‫‪2‬‬ ‫• ارتداء العاملين لمهمات الوقاية الشخصية ( خوذه ‪ -‬نظارة ‪ -‬فيست ‪ -‬حذاء سالمة )‬ ‫متوسط‬ ‫‪2‬‬ ‫‪4‬‬ ‫سقوط الخامات‬ ‫استخدام الرافعات الشوكيه او الونش‬
‫الونش‬
‫• عزل المنطقه باستخدام اقماع وشرائط تحذيريه‪.‬‬
‫• تشوين الخامات على بلتات ‪.‬‬
‫• استخدام حمل يناسب قدرة الرافعات ‪.‬‬
‫• عمل تصاريح العمل الالزمة واعتماد التصاريح والتوقيع عليها من المسئولين او القائم على المهمه والموافقة علية‬
‫• اخالء منطقة التشوين بعمل شريط تحذيري وأقماع حول منطقة التشوين بالتنسيق مع االدارة الهندسية‬