Project Field residences

Location Brgy Manuyo Uno, Las Pinas City


Subject Additional works Garden soil and Raphies for Bldg 6 and planting strip
Date June 8, 2023

Item Description Quantity Units Unit Cost


1 Clearing and removal of debris and unustable materials 1 lot 20,000.00
2 Hauling of debris 1 lot 70,000.00
3 Garden soil delivery and distribution 42.64 cubic 1,806.00
4 Raphies delivery and planting 355 pcs 453.6

Prepared by

Engr. Jeremie Carpio

Noted by

Erillon Paulo Vallado

Approved by:

Engr. Obet Dizon

CC. Engr. Elmer S. Castro


Cost
20,000.00
70,000.00
77,007.84
161,028.00
328,035.84