Professional Documents
Culture Documents
Sub––total
Sub totalfor
forDC Php
Php 7,146.36
DE. Job
Job– –Order
Order 0.00
. Sub – total for E 0.00
Sub – total for D 0.00
F. Direct Cost (A+B+C+D+E) Php 90,823.38
E. Direct Cost (A+B+C+D)
G. Overhead, Contingencies and Miscellaneous 11.1165581% Php 12,561.36
9,083.34
F.H. Overhead, Contingencies
Contractor’s Profit (CP) and Miscellaneous 11.1165581%
10.0000000% 1,884.20
4,995.29
GI. Contractor’s Profit
Total-As submitted (CP) 10.0000000% 1,256.14
104,901.01
.J. Total Php
HK. Value Added Tax (VAT)
Total Unit Cost-As Submitted 12.0000000% 785.09
65,563.13
.
I. Total Php 16,486.79
J. Total Unit Cost 16,486.79
b. Marine
Plywood,1/2"x4x8(4
4.44 pcs. 800.00 3,552.00
uses)
c. Assorted CW nail
2.12 kg. 95.00 201.59
d. Cement
107.00 bag 282.50 30,277.50
e. Sand
5.63 cu.m 1,100.00 6,187.50
f. Gravel
11.25 cu.m 1,100.00 12,375.00
1000 gal