A B C D E
Project BillBoard Occupational Excavation
Activity : Start Activity : Permitting Activity : Activity : Activity :
/Sign Board Health & safety common soil
Duration: 0 day Duration: 14 days Duration: 2 days Duration: 75 days Duration: 5 days
F G
Sand
Activity : Activity : Pipe and Fittings
Fill/Bedding
Duration: 5 days Duration: 91 days
PATH
A+B+C+G+H = 107 DAYS, CRITICAL PATH
A+B+C+D+E+F+H = 101 DAYS
H
Activity : Finish
Duration: 0 day