PERT CPM

A B C D E
Project BillBoard Occupational Excavation
Activity : Start Activity : Permitting Activity : Activity : Activity :
/Sign Board Health & safety common soil
Duration: 0 day Duration: 14 days Duration: 2 days Duration: 75 days Duration: 5 days

F G
Sand
Activity : Activity : Pipe and Fittings
Fill/Bedding
Duration: 5 days Duration: 91 days
PATH
A+B+C+G+H = 107 DAYS, CRITICAL PATH
A+B+C+D+E+F+H = 101 DAYS

H
Activity : Finish

Duration: 0 day

OWNER: DESIGNER: ENGINEER/ARCHITECT: VALIDATED BY: VALIDATED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY: SHEET CONTENT: SHEET NUMBER:

REPUBLIC OF THE PHILIPPINES REX E. MORALES 1 1


MUNICIPALITY OF MACROHON
CONSTRUCTION ENGINEER PEACHY G. HAPITAN CONSTRUCTION OF MUNICIPAL WATER SYSTEM II
UTILIZING DESIGN AND BUILD SCHEME
PERT CPM REVISION NUMBER:
PROVINCE OF SOUTHERN AUTHORIZED MANAGING OFFICER
MUNICIPAL ENGINEER MPDC MUNICIPAL MAYOR
P4- BRGY. LINAO, PRC REG NO.: PLACE:
LEYTE 0
ORMOC CITY PTR NO.: DATE: