OP2000BS PSU
Installation and operating manual
i

Integrated power system


Instruction Manual
ENELT.OP2000BS

Kazan, Russian Federation


2022

1
ENELT.OP2000BS PSU
Installation and operating manual
i
Content

1 Overview ................................................................................................................... 3

2 Product specifications .............................................................................................. 3

3 Cited standards and specifications ............................................................................ 3

4 Principle introduction ................................................................................................. 4

5 Environmental conditions .......................................................................................... 5

6 Electrical characteristics ............................................................................................ 6

7 Other request ............................................................................................................ 7

8 Safety characteristics ................................................................................................ 8

9 Precautions ............................................................................................................... 8

10 Mechanical properties ........................................................................................ 8

11 Reliability requirements ...................................................................................... 9

12 Packaging, storage and transport requirements ................................................. 9

13 Basic requirements for installation.................................................................... 10

14 Structure diagram ............................................................................................. 23

15 Hazardous substance content table ................................................................. 24

2
ENELT.OP2000BS PSU
Installation and operating manual
i
1 Overview
ENELT.OP2000BS integrated power supply is a new generation of highly reliable, high-performance wireless
micro-station communication power supply system. The system consists of switching power supply, lithium
battery, FSU module, input and output power distribution, etc. The system has the characteristics of self-
heat dissipation, high efficiency, small size, light weight, easy installation, no parameter setting, no maintenance,
high protection level, Bluetooth support, remote monitoring, and online expansion.

2 Product specifications
Voltage
Output Power Input voltage range Output voltage Output current IP System
accuracy
model
2000W 90-300Vac 54Vdc 37A ≤±0.6% IP65 ENELT.
OP2000BS
System
Configuration
AC Input 40A/3 core waterproof connector

load:40A*3(2 core waterproof connector)

DC Output Parallel:60A*1(2 core waterproof connector)


Battery:60A*1(2 core waterproof connector)

Battery module 10/20/50AH(Based on customer request)

AC
Nominal discharge current 20KA, maximum discharge current 40KA
lightning protection
DC
lightning protection Nominal discharge current 10KA, maximum discharge current 20KA

3 Cited standards and specifications


a. YD/T 1058-2007 《High-frequency switching power supply system for communication》
b. YD/T 731-2008《High frequency switching rectifier for communication》
c. YD/T 585-2010《Power distribution equipment for communication》
d. YD/T 1051-2010 《General technical requirements for power systems of communication bureaus
(stations)》
e. YD/T 5040-2005 《Communication power supply equipment installation engineering design
specification》
f. YD/T 983-2013《Communication power supply equipment electromagnetic compatibility limits
and measurement methods》
g. YD/T 944-2007 《Lightning protection technical requirements and test methods for
communication power supply equipment》
h. YD 5083-2005 《Telecommunication equipment anti-seismic performance testing specification》
i. YD 5096-2005 《Code for testing seismic performance of power supply equipment for
communication》

3
ENELT.OP2000BS PSU
Installation and operating manual
i
4 Principle introduction
The principle of the integrated power system is shown below:

BMS Battery

Power supply unit

AC input AC/DC
AC Signal AC
lightning lightning lightning
protection protection protection

Monitoring Shunt
unit
detection

NB/4G
Bluetooth
Monitoring unit

This system mainly includes 48V/2000W power module and 48V/10Ah & 48V/20Ah & 48V/50Ah lithium battery
module (hereinafter referred to as "lithium battery module"), in which the power module converts alternating
current or high voltage direct current into stable 48V direct current, the lithium battery module is The
communication equipment provides a backup power function.

The system adopts single-phase three-wire system AC input. After passing through the rectifier, filtering, voltage
stabilization and other links, the AC power becomes stable DC power to the positive and negative rows of the
system; the system has a set of battery interfaces, and the battery pack passes through the battery fuse and shunt
(Battery current detection) is connected in parallel with the output of the rectifier module. When the AC power
fails, the

DC power distribution unit supplies the customer's DC load.

The AC power distribution status, rectifier status, battery status, DC shunt status, and customer power
consumption are all detected or controlled by the controller. The system is equipped with a Bluetooth unit and a
remote monitoring unit. At the near end, you can view the system-related information through the mobile phone
APP; at the far end, you can remotely monitor the system information through the PC. The system connection
relationship is as follows:

4
ENELT.OP2000BS PSU
Installation and operating manual
i
5 Environmental conditions
Environmental parameters Environmental Transport Storage Remarks
conditions conditions
Project conditions
Parameter Unit

℃ -45 -45 -45


Low temperature
—45℃~55℃
℃ 55 75 75 can work normally
High temperature

Low % 0 / 0
humidity

Humidity /
Climatic High % 95 / 95
conditions humidity

No / No
Condensatio Yes/No
n

Low m 0 0 0
altitude The derating of high
temperature under the use of
Altitude environmental conditions at
High m 2000 2000 2000 3000~4000m, decreases 1℃
altitude for every 200m increase

Sinusoidal vibration: 5~9Hz:


Random vibration:
amplitude 3.5mm;9~200Hz:
Shock 2~10Hz: 30m2/s3; /
acceleration 10m/s2;
10~200Hz: 3m2/s3;
3 Axial, sweep frequency
200~500Hz: 1m2/s3; 3
vibration 5 times in each
axis, 30min in each
direction
Mechanical direction
stress
conditions

Acceleration 250m/s2; Acceleration 400m/s2;


Shock (collision) /
pulse width 6ms; 500 pulse width 6ms; 500
collisions on 3 axes in 6 collisions in 3 axes and 6
directions directions

Drop / 1m drop height;1 /

bottom

Cooling
method Natural air cooling

5
ENELT.OP2000BS PSU
Installation and operating manual
i
6 Electrical characteristics
1 Input characteristics

Serial Project Technical requirements Unit Remarks


1.1 Input rated voltage 220 Vac

176-300V full load output, linear


1.2 Input voltage range 90~300 Vac
down power output below 175Vac

1.3 Input voltage frequency 45-65 (typical value 50/60) Hz


1.4 Maximum input current <13 A

1.5 Power factor ≥0.99 220Vac rated load

2.Output characteristics

Serial Project Technical requirements Unit Remark


s
2.1 Output voltage range 42-58 (typical value 53.5) Vdc

2.2 Maximum output power 2000 W


2.3 Voltage accuracy ≤±0.6%

Rated input voltage and load,


2.4 Output ripple and noise ≤200 mVp-
p bandwidth limit 20MHz

2.5 Current imbalance ≤±5% 50 -- 100% load range

2.6 Effectiveness ≥96%

When the rated input voltage is turned


2.7 Boot time 3~8 S on and the output voltage is established
to the set value, the pre-current limiting
function needs to be used for the output
When any module is hot swapped (at
Overshoot this time, the load current should not be
2.8 amplitude ≤±5% greater than the total output current of
of switch the working module), the system output
voltage fluctuates

Overshoot amplitude ≤±5%


Dynamic 25%—50%—25% or 50%—75%—50%
2.9
Response ≤200 load change
Recovery Time µS
2.10 Temperature Coefficient ≤±0.02 %/℃
2.11 Telephone weighing noise ≤2 mV

≤200 mV 3.4~150KHz
2.12 Broadband noise voltage
≤30 mV 0.15~30MHz

6
ENELT.OP2000BS PSU
Installation and operating manual
i
2.Output characteristics

Serial Project Technical requirements Unit Remarks


≤5 mV 3.4~150KHz

Discrete ≤3 mV 150~200KHz
2.13 noise
voltage ≤2 mV 200~500KHz
≤1 mV 0.5~30MHz
2.14 Output voltage drop ≤500mV mV

3.Protection characteristics

Serial Project Technical requirements Unit Remarks


3.1 Input overvoltage ≥300 Vac Self-recovery, the return difference is
protection not less than 10Vac
3.2 Input undervoltage ≤80 Vac Can be self-recovery, the return
protection difference is not less than 5Vac
3.3 Output overvoltage 59 Vdc
protection
Output undervoltage The battery can be powered off
3.4 protection Battery off protection Vdc through monitoring, and the
protection point can be set
3.5 Output current √
limit protection
3.6 Output short √ Can be short-circuited for a
circuit protection long time and can recover
Shell temperature: 85℃
3.7 Over temperature ℃
protection shutdown protection, 80℃
self-recovery
Reverse battery According to user needs, it can
3.8 polarity protection
√ have reverse polarity
protection function

7 Other request
Serial Project Standard Remarks

1 Acoustic noise Not more than 45dB(A) -

2 Can be parallel Support up to 4 power modules and 16 battery modules in parallel -

3 Module failure Rectifier module can be reliably separated from the system after -
isolation failure
4 Odour Does not produce odors and harmful odors -
requirements
5 Component The rated temperature of the selected -
requirements electrolytic capacitor is not less than 105℃

7
ENELT.OP2000BS PSU
Installation and operating manual
i

8 Safety characteristics
1) Insulation resistance
When the ambient temperature is 15~35℃ and the test voltage is 500V DC, the insulation resistance of the AC
partand the DC part to the ground, and the AC part to the DC part meet the following requirements: relative
humidity ≤65%, insulation resistance is not less than 5MΩ ; 65% <relative humidity ≤ 90%, insulation resistance is not
less than 2MΩ.
2) Dielectric strength
 The AC input should be able to withstand a 50Hz sinusoidal AC voltage with an effective value of
2500V or its equivalent peak value of 2121V DC voltage for 1min without breakdown or arcing.
 The AC input to DC output should be able to withstand 50Hz, 2500V sine AC voltage or its
equivalent peak value of 4242V DC voltage for 1min without breakdown or arcing.
 The DC output to the ground should be able to withstand a sinusoidal AC voltage of 50 Hz and
an effective value of 500 V or its peak value of 707 V DC voltage for 1 min without breakdown
or arcing.
 Grounding performance
The grounding resistance between the chassis and the grounded parts is less than 0.1Ω.

3) System contact current


This machine has a large contact current and must be grounded before turning on the power.

9 Precautions
This machine has dangerous energy output, do not touch it when working.

10 Mechanical properties
Unit Power module 10/20AH battery module 50AH battery module Remarks
(±1mm)
(±1mm) (±1mm)
Height 445mm 445mm 445mm

Width 345mm 345m 345m


m m
Deep 97mm 112m 234m
m m
Weight See the case See the case See the case

8
ENELT.OP2000BS PSU
Installation and operating manual
i
11 Reliability requirements
1 MTBF

Index Unit Magnitude Condition Remarks

25℃, rated input, full load


Machine Ten thousand >10 output Bellcore stress method
hours
is expected

2 Service Life:10 years

12 Packaging, storage and transport


requirements

1 Packing
The packaging box contains the product name, model, manufacturer logo, manufacturer's
quality department inspection certificate, manufacturing date, etc.; the packaging box has a list of
accessories.

2 Transport
Suitable for transportation by car, boat and plane。

3 Storage
The product should be stored in the packaging box when not in use. The warehouse ambient
temperature is -45 … +40°C and the relative humidity is not more than 80%. No harmful gases,
flammable, explosive products and corrosive chemicals are allowed in the warehouse. And without
strong mechanical vibration, impact and strong magnetic field, the packing box should be at least
20cm high from the ground and at least 50cm away from the wall, heat source, window or air inlet.
The storage period under these conditions is generally 2 years, more than 2 The inspection should be
repeated after the year.

9
ENELT.OP2000BS PSU
Installation and operating manual
i
13 Basic requirements for installation
Statement

Before installing the integrated power system, please read this installation manual carefully, and abide by
the safety regulations of related industries. The company is not responsible for product damage caused by
improper operation or exceeding the provisions of this installation manual.
Due to product version upgrades or other reasons, the content of this document will be updated from time to
time. Unless otherwise agreed, this document is only used as a guide, and all statements, information and
suggestions in this document do not constitute any express or implied warranty.

Safety code

High Some parts of the system power supply are under high voltage. Direct contact or indirect contactwith these
pressure parts through wet objects can cause fatal danger.

The construction operation of high-voltage lines may cause fire or electric shock accidents. The installation and
Danger routing of AC cables must comply with local laws and regulations. Only personnel qualified for high-voltage,
alternating current operation can perform various high-voltage operations.

It is strictly forbidden to wear watches, bracelets, bracelets, rings and other conductiveobjects on
the wrist during operation.
When operating in a humid environment, moisture should be strictly prevented fromentering the
Note
device.
During the installation process, the switches and buttons that are not allowed to be operated must
be hung with signs prohibiting closing.

Note AC line terminal contacts and other unnecessary exposed places should be fully insulated.

Note It must be grounded before powering on.

Before carrying out battery work, you must carefully read the safety precautions for battery handlingand
Danger the exact connection method of the battery.

Danger When carrying equipment by hand, wear protective gloves to prevent cuts from sharp objects

Danger It is strictly forbidden to carry out high voltage and alternating current operations in thunderstorms

Note To prevent electrical coupling, the AC cable should be routed separately from the DC cable.

10
ENELT.OP2000BS PSU
Installation and operating manual
i

13.1 Basic requirements for installation


13.1.1 Environmental requirements

Environmental Suggested scope


Ambient -45℃~+55℃
temperature
Humidity ≤95%RH,No condensation
Dustiness ≤1mg/m3

Sunlight No direct irradiation (recommended optional sunshade)


Corrosive
substances No pollutants, such as salt, acid, smoke, etc.
The system can withstand a sine wave vibration with a frequency of (10~55) Hz and an
Shock
amplitude of 0.35mm

Insects, pests, pests,


termites, etc. No

Mildew No
Atmospheric Atmospheric pressure: 70~106kPa, altitude: 0~3000m
pressure
Fire prevention No combustibles on the top and bottom of the cabinet

Input supply voltage Single phase 176~275Vac, 50Hz

The output voltage of the power supply system is nominally -48Vdc, the actual output
The output voltage range is -43.2~-57.6Vdc, the default output voltage is -54V, and the outputpower is
2000W.

13.1.2 Power requirements


AC power supply should use 220Vac city power. The mains power adopts single-phase three-wire system, please pay
attention to grounding. Multi-strand copper core wire should be used for power line, and the cross-sectional area of power line
should be suitable for the load. Outdoor power line laying is recommended to be buried directly or buried, and the power line
laying should be separated from the signal line as much as possible. This product is a large leakage current device. When connecting
to the mains, please do not connect

the leakage current protection switch at the front end, otherwise it will easily cause the leakage protection switch to trip.

13.1.3 Safety protection requirements


Grounding requirements

The grounding method of the communication cabinet is usually designed according to the principle of shared grounding, that is,
the working ground, lightning protection grounding and protective grounding share a set of grounding bodies, and the grounding
resistance should comply with the national telecommunications power equipment regulations. The basic method of common
grounding is to short- circuit the grounding busbar of the power system with the user grounding bar. The DC working ground,
lightning protection ground and

protective ground of the power system should be connected to the grounding busbar of the power system as close as possible.

13.1.4 Preparation for installation


Scene Investigation

Before the equipment is installed, a safety inspection shall be carried out on the cabinet.

1). The environment required for equipment installation. Such as temperature, humidity, dust and other items.
2). The equipment must be cut off from the AC or DC input power before the equipment can be installed and
operated. 3). Conditions required for installation and construction. Such as power supply, lighting, etc.
Tool and material preparation

The tools to be prepared include: multimeter, test pencil, screwdriver ("cross" and "one word"), cutting pliers, needle
nose pliers,wire strippers, cold press pliers, etc.

11
ENELT.OP2000BS PSU
Installation and operating manual
i
13.2 System interface description
13.2.1 Power module interface:

8 4G

10

11

Communication
1 PWR AC input terminal 7 COM
terminal
Load output 1 4G antenna
2 LOAD1 8 4G
interface
Load output 2 GPS antenna
3 LOAD2 9 GPS
interface

4 LOAD3 Load output 3 10 FSU power switch

Parallel
5 Parallel 11 SIM card slot
interface
Battery output Indicator lights
6 BAT 12
terminal (green, yellow, red, green)

Note: The parallel interface supports emergency 48V power access.

12
ENELT.OP2000BS PSU
Installation and operating manual
i
13.2.2 10/20AH Battery module:

COM Switch Parallel BAT


5
4

Battery output
1 BAT 4 Battery start switch
terminal
Battery parallel 4-digit dial switch
2 Parallel 5
interface
Communication Indicator light
3 COM terminal 6 (yellow, green, red)

13.2.3 50AH Battery module:

Switch
4 5

Battery output Battery start switch


1 BAT terminal 4
Battery parallel
2 Parallel 5 4-digit dial switch
interface
Communication Indicator light
3 COM terminal 6 (yellow, green, red)

13
ENELT.OP2000BS PSU
Installation and operating manual
i
13.2.4 Terminal wiring instructions

AC input terminal:

Blue: N line; Red: L line; Yellow: PE, as shown below. Input cable requirements: one strand of 3 cores, the
outer diameter of the cable is not greater than 14.5mm, the cross-sectional area of the connectable conductor is
0.75-6mm2,the recommended is 4mm2.

N
P
E
L
DC/parallel terminal:

Blue: negative wire (DC+); red: positive wire (DC-); as shown in the figure below, the input cable
requirements:one 2-core, the outer diameter of the cable is not greater than 14.5mm, and the cross-sectional
area of the wire thatcan be connected is 0.75-6mm², it is recommended 6mm².

-
+

14
ENELT.OP2000BS PSU
Installation and operating manual
i
Battery terminals:
Blue: negative line (DC+); red: positive line (DC-); as shown below, the input cable is not less than 10mm².

Signal (COM) terminal:

As shown in the figure below, a total of 16 bits, 1, 2 are battery communication lines; 3, 11, 4, 12 are power
supply communication lines; 5, 6, 7, 8 are upgrade connection lines, 9, 10, 13, 14, 15, 16 Wiring for DO alarm volume
requires theinput cable to be two 8-core wires with a cable outer diameter no greater than 6 mm.
Power COM wiring definition Battery COM wiring definition
1 485-A2(BAT) 1、2 /
2 485-B2(BAT) 5、6 /
3、11 CAN-H 9、10 /
4、12 CAN-L 13、14 /
5 RX- 3
6 RX+ Upgrade 7
interface 485A
7 TX+ 11
8 TX- 15
9 COM 4
1
10 DO1 8 485B
13 COM 12
2
14 DO2 16
15 COM
3
16 DO3

15
ENELT.OP2000BS PSU
Installation and operating manual
i

13.3 Electrical performance


AC input
a )The power system input configuration is a 40A single-phase loop and is equipped with corresponding
protection devices.

b )The total AC input is equipped with electric energy measurement function.


c )With historical electrical energy data storage function, power failure data automatic recovery
function. d )The input voltage is AC220V (176V ~ 300V).

Shunt output
The shunt output configuration of the power system is 3 channels of 48V DC output, the output
power isnot less than 40A/channel, and is equipped with corresponding protection devices.

Battery access
Power system input configuration 1 way 10Ah/20Ah/50Ah battery pack access.

Communication Interface
Power system input configuration 1 way monitoring interface (dry contact, RS485, CAN) communication
interface, to communicate with the battery pack or other equipment.

Monitoring Unit (FSU)


The power supply system has a built-in miniature monitoring unit (FSU), which monitors the
operationdata of the power supply equipment in real time, and has positioning and wireless
transmission functions Communication service

a) FSU has built-in NB-IOT or 4G communication module, which has the function of wireless
communicationthrough 4G or NB-IO network.
b) FSU communicates with the centralized monitoring center (SC) through the communication module,

supports plug-in communication module, and can replace the NB-IOT or 4G network module according
to theon-site network environment。
Positioning service
FSU has a built-in GPS positioning module that can monitor local positioning services (latitude,
longitude,etc.).

Data transmission
a) Sampling data such as voltage and current through the power interface, completing data collection
with the power equipment and various environmental quantity collectors and other monitoring objects
through the data interface, after the bottom analysis and intelligent processing, upload to the centralized
monitoring through the wireless network center.
b) With measurement function, it can calculate the actual power consumption generated by the
micro-station equipment and upload it to the centralized monitoring center.
Online registration
a) With 4G / NB-IOT wireless Internet access capability, fill in the configuration through the mobile
APP toachieve the binding, initial configuration and unbinding, and configuration modification of the FSU
and the monitored micro-station.
b) When using the NB-IOT network, FSU first registers with the adaptation platform through the
operatorconnection management platform. After the adaptation platform sends registration
confirmation information tothe link management platform, the adaptation platform management
interface should be able to view the monitoring of the registered FSU With status information.
c) When using the 4G network, FSU can directly register with the adaptation platform. After the
adaptation platform sends registration confirmation information to the FSU, the adaptation platform
management interfaceshould be able to view the monitoring and status information of the registered FSU.

16
ENELT.OP2000BS PSU
Installation and operating manual
i
13.4 Device installation
This product supports various methods such as wall-mounted installation, wall-mounted flag installation,
pole installation, pole pole installation, etc. It is suitable for application scenarios such as wall-
mounted,pole, angle steel tower, etc. Installation, maintenance, and after-sale services shall be
carried out by relevant technical engineers for equipment installation and technical guidance.

1. It is strictly forbidden to open the upper and lower covers after leaving the factory;
2. When installing on the wall, install the equipment on the concrete wall and ensure it is firm;
3. The shell of the integrated power system must be effectively grounded, and the cable
connectorsshould be tightened and plugged to ensure reliable connection;
4. The on-site installation and commissioning of the integrated power system allows the power
supply cover to be opened, the SIM card and related antennas to be installed, and the relevant
fuse protection device to be designed on the interface board. The installation must be powered
off and the related screws must be locked in time after installation.
5. The integrated power system can install 4G/NB-IOT and GPS antenna.
The installation components of ENELT’s integrated power supply are compatible with the installation of all battery
and power supply modules in different application scenarios. The installation parts are composed of parts 1-4, and
different installation components are selected according to different scenarios

Mountingparts1

Mountingparts2

Mountingparts3

(Deprecated when
hanging on the wall)

17
ENELT.OP2000BS PSU
Installation and operating manual
i
The installation effect is as follows:

10/20AH Battery 10/20AH Battery


Mounted on a pole Mounted on a pole

18
ENELT.OP2000BS PSU
Installation and operating manual
i

Mounted on a pole
Mounted on a pole

19
ENELT.OP2000BS PSU
Installation and operating manual
i

13.5 Common fault maintenance instructions


1 AC power outage
Possible reason

 Mains failure.
 The AC input of the previous stage is disconnected.
 The AC input connector cable is loose.

Treatment method

1. Measure whether the AC input voltage is abnormal, and if so, handle the grid fault.
2. Check whether the AC input MCB is open. If yes, close the MCB after handling the back-end fault circuit.
3. Check whether the AC input cable is loose, and if so, fix the input cable.
2 AC overvoltage
Possible reason

 Unstable grid.
 The AC overvoltage alarm point setting is unreasonable.

Treatment method

1. Measure whether the AC input voltage is abnormal, and if so, handle the grid fault.
2. Check whether the setting value of the AC overvoltage alarm point is reasonable, and if it is not reasonable,
adjust itaccording to the actual situation.
3 AC undervoltage
Possible reason

 The power grid is unstable.


 The AC undervoltage alarm point setting is unreasonable.
Treatment method

1. Measure whether the AC input voltage is abnormal, and if so, handle the grid fault.
2. Check whether the setting value of the AC undervoltage alarm point is reasonable. If it is not reasonable,
adjust itaccording to the actual situation.
4 DC overvoltage
Possible reason
 The rectifier module is faulty.
 The setting of the DC overvoltage alarm point is unreasonable.
Treatment method

1. Check whether the fault light of the rectifier module flashes. If yes, replace the rectifier module.
2. Check whether the setting value of the DC overvoltage alarm point is reasonable. If it is not reasonable,
adjust itaccording to the actual situation.

20
ENELT.OP2000BS PSU
Installation and operating manual
i
5 DC undervoltage
Possible reason

 The battery voltage is lower than the DC undervoltage alarm point.


 The setting of the DC undervoltage alarm point is unreasonable.
Treatment method
1. Check whether the setting value of the DC undervoltage alarm point is reasonable. If it is not reasonable,
adjust itaccording to the actual situation.
2. Restore AC power and charge the battery to increase the battery voltage.
6 Communication failed

Possible reason
 The communication line of the rectifier module is loose
 There is a short circuit in the 485 interface communicating with the lithium battery.
Treatment method

1. Check whether the communication cable of the rectifier module is loose, and if so, fix the cable.
2. Check if there is a short circuit on the 485 interface communicating with the lithium battery, and if there is
a shortcircuit, eliminate it.

7 Rectifier module failure


Possible reason
 The parallel power line is loose.
 The rectifier module hardware is damaged.
 Rectifier module external overvoltage.

Treatment method

1. Check whether the parallel power cables between the rectifier modules are loose, and if so, fix the cables.
2. Check whether the output voltage of the system is too high. If yes, disconnect the parallel cables, check the
outputvoltage of the modules one by one, find the modules with abnormally high output voltage and replace
the modules.
8 AC lightning protection failure
Possible reason
 The AC lightning protector is faulty.

Treatment method

1. Replace the AC lightning protection module.


9 Low temperature protection
Possible reason
 The battery is discharged for a long time in a low-temperature environment.
 The battery was powered on for the first time and the temperature did not rise above 0 degrees.
 The battery heater is faulty.
Treatment method

1. Check if APP has battery heater failure alarm; if there is, replace the battery; if not, wait for a while to see if
the batterytemperature can rise to 0 degrees; if it can, no treatment is required; if not, replace the battery.

21
ENELT.OP2000BS PSU
Installation and operating manual
i
10 Discharge high temperature protection
Possible reason

 The high ambient temperature of the battery causes the battery temperature to be too high during
long-termdischarge.
 The battery was powered on for the first time and the temperature did not rise above 0 degrees.
 The battery heater is faulty.
Treatment method

1. Check whether the battery is located in the heat exhaust area of other heat-generating
equipment. If it is,isolate the heat source or replace the battery installation location.
2. Does the discharge time in a high-temperature environment meet the specifications? If not,
replace thebattery.
11 Charging high temperature
protectionPossible reason
 The ambient temperature of the battery is high.

Treatment method

1. Check whether the battery is located in the heat exhaust area of other heat generating equipment. If it
is, thenisolate the heat source or replace the battery installation location.
12 Overcharge protection
Possible reason
 The power module is faulty.
 The charging voltage setting of the power module is unreasonable.
Treatment method

1. Check whether the setting value of the average floating charging voltage is reasonable, if not,
adjust itaccording to the actual situation.
2. Check whether the output voltage of the power module is too high. If it is higher than the setting
value of theaverage floating charging voltage and cannot be adjusted, replace the power module.
13 Discharge overcurrent protection
Possible reason

 The load is greater than the maximum power of the lithium battery module.
 The load is shorted.

Treatment method

1. Check whether the load is greater than the maximum power of the lithium battery. If it is, increase the
lithiumbattery capacity configuration or reduce the power system load.
2. Check if there is a short circuit fault in the load circuit, if yes, remove the fault.

22
ENELT.OP2000BS PSU
Installation and operating manual
i
14 Structure diagram

23
ENELT.OP2000BS PSU
Installation and operating manual
i
15 Hazardous substance content table
Harmful materials
Integrated power Polybrominat
supply Hexavalent
Lead and its Mercury and its Cadmium and its Polybrominated ed
chromium
compounds compounds compounds biphenyls diphenyl
compound
ethers
Monitoring unit and
╳ ○ ○ ○ ○ ○
electrical components
Rectifier module and
electrical ╳ ○ ○ ○ ○ ○
components
Fasteners such as
○ ○ ○ ○ ○ ○
screws and nuts

Other metal parts ○ ○ ○ ○ ○ ○

Sponge ○ ○ ○ ○ ○ ○

Other plastic parts ○ ○ ○ ○ ○ ○

Rubber parts ○ ○ ○ ○ ○ ○

Power cord and cable ╳ ○ ○ ○ ○ ○

Other packaging and


○ ○ ○ ○ ○ ○
printing

○ :It means that the content of this hazardous substance in all homogeneous materials of this part is below the limit
requirements stipulated in GB/T26572-2011 and SJ/T11364-2014.

╳:It means that the content of the hazardous substance in at least one homogeneous material of this part exceedsthe
limit requirements stipulated in GB/T26572-2011 and SJ/T1364-2014. The part marked "╳" in the table above cannot be
replaced due to technical reasons, and will be gradually improved as the technology advances.

For the sake of human health and the protection of the beautiful earth home, please be sure to do the following:
1. After the product is scrapped, please separate it from domestic garbage, we have the responsibility to send it to a
qualified recycling point;
2. The recycling center will be handled according to the corresponding specifications;
3. For information about the recycling of this product, please consult the local government, waste disposal center or
distributor.