1. Turn the battery switch ON 7.Move the levers (7) in the same direction as
you want to go. Check track tilting, adjust
switches (8) if needed (See item 9) point 9.
7

2. Check that switch (2a) is OFF (pos. B) and


that knob (2b) is in pos. B (tramming)
A
2a 8. Push switch (5) to pos. B to lock the
B oscillation cylinders. (Close the yellow cap)
2b A
B C
D A
5
B
3. Turn start key (3) to pos. B. Wait 30 sec.
Then turn to pos. C. When engine starts,
release key to pos. B
9. Pull switch (4) rearwards until the jack is
supporting the rig. Note: Do not lift the rigg!
A
4
8 B
3
4. Push switch (4) forward until the rear jack is
fully retracted (Option)
A 10. Position the boom by levers (6) to transport
4 position (See next page)
B

6 a

d b e

5. Open the yellow cap and push switch (5) to c


pos. A to unlock the oscillation cylinders
11. Turn start key (3) to pos. A. The engine will
A
stop.

5
B

3
6. Position the boom and feedbeam with
12. Turn the battery switch OFF.
levers (6).
IMPORTANT!
6

ATLAS COPCO ROCK DRILLS AB


ÖREBRO SWEDEN
©Atlas Copco Rock Drills AB, 2004 All rights reserved.
Lifting

A B A B
Folding boom version: Single boom version:
For best rig stability, For best rig stability,
position boom, feed and position boom, feed and
rock drill as follows:
- Boom cylinder max. OUT.
! rock drill as follows:
- Rock drill in END (upper)
- Boom extension cylinder max. IN. position.
- Feed dump cylinder max. OUT. - Operate the boom and
(Make sure that feed does not hit feed controls to lay down
the lifting eq.) the feed on the feed
Rock drill in END (Bottom) position. support. (Make sure that
the body does not get
damaged.
Both versions:
Check that the jack is retracted. Make sure that the oscillation cylinders are LOCKED
see item 8.
Fasten the sling under the tracks at A and B shown above. Check that none of the hoses,
controls or other parts are damaged when the slings become tightened.

Transportation
- Run the rockdrill to it´s lowest position
- Alternately use the boom and feed controls to lay down the
feed on to the transportation vehicle.

After stopping the rig on the transportation vehicle: Single boom Alt. 1
- Run down the hydraulic jack
- Lock the oscillation cylinders, see item 8.
- Shut down the diesel engine and switch off the battery switch
- Lash the rig on the transport vehicle

! Single boom Alt. 2

Folding boom Alt. 3


Transport dimensions and weight:
(Fully equipped with drill string and all optional equipment)
ROC F6 F6 F7-10 F7-10 F7-11 F9-10 F9-10 F9-11 F9-LM
Length 12,3 m 9,0 m 12,3 m 8,6 m 13,0 m 12,3 m 8,6 m 13,0 m 11,3 m
Width 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m
Height 3,2 m 4,0 m 3,2 m 3,8 m 3,2 m 3,2 m 3,8 m 3,2 m 3,7 m
Weight 19,0 ton 19,0 ton 18,5 ton 18,5 ton 18,5 ton 18,5 ton 18,5 ton 18,5 ton 19,0 ton
Position Alt Alt, 1 Alt. 2 Alt. 1 Alt. 2 Alt. 3 Alt. 1 Alt. 2 Alt. 3 Alt. 2