PERHITUNGAN VOLUME BESI HALF SLAB LANTAI 1 GEDUNG PARKIR UTARA

DIMENSI (m2) DIAMETER BESI (Kg/m)


BEKISTING
NO. TYPE PEKERJAAN BETON h b L DETAIL TULANGAN BESI VOLUME QTY VOLUME BETON
BODEMAN
(m) (m) (m) Dia Jml kg/m' Total

LANTAI 1
HALF SLAB TYPE HS1 (2.015x3.96) 0.135 2.015 3.96 1,595.88 200 215.44
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 200 4,419.07
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 200 857.68
Wiremesh M8-150 12.16 200 2,432.64
Toping Wiremesh M8-150 12.16 200 2,432.64

D10 4,419.07 Kg
` D13 857.68 Kg
WIREMESH M8 4,865.28 M2
HALF SLAB TYPE HS 2 (2.015x3.96) 0.135 2.015 3.96 797.94 100 107.72
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 100 2,209.54
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 100 428.84
Wiremesh M8-150 12.16 100 1,216.32
Toping Wiremesh M8-150 12.16 100 1,216.32

D10 2,209.54 Kg
D13 428.84 Kg
WIREMESH M8 2,432.64 M2
HALF SLAB TYPE HS 3 (2.015x3.96) 0.135 2.015 3.96 797.94 100 107.72
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 100 2,209.54
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 100 428.84
Wiremesh M8-150 12.16 100 1,216.32
Toping Wiremesh M8-150 12.16 100 1,216.32

D10 2,209.54 Kg
D13 428.84 Kg
WIREMESH M8 2,432.64 M2
HALF SLAB TYPE HS1A (2.015x4.135) 0.135 2.015 4.14 33.33 4 4.50
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 4 91.83
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 4 17.15
Wiremesh M8-150 12.64 4 50.55
Toping Wiremesh M8-150 12.64 4 50.55

D10 91.83 Kg
D13 17.15 Kg
WIREMESH M8 101.11 M2
HALF SLAB TYPE HS2A (2.015x4.135) 0.135 2.015 4.14 16.66 2 2.25
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 2 45.92
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 2 8.58
Wiremesh M8-150 12.64 2 25.28
Toping Wiremesh M8-150 12.64 2 25.28

D10 45.92 Kg
D13 8.58 Kg
WIREMESH M8 50.55 M2
HALF SLAB TYPE HS3A (2.015x4.135) 0.135 2.015 4.14 16.66 2 2.25
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 2 45.92
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 2 8.58
Wiremesh M8-150 12.64 2 25.28
Toping Wiremesh M8-150 12.64 2 25.28

D10 45.92 Kg
D13 8.58 Kg
WIREMESH M8 50.55 M2
HALF SLAB TYPE HS1B (2.015x3.385) 0.135 2.015 3.39 81.85 12 11.05
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 12 231.11
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 12 51.46
Wiremesh M8-150 10.60 12 127.22
Toping Wiremesh M8-150 10.60 12 127.22

D10 231.11 Kg
D13 51.46 Kg
WIREMESH M8 254.45 M2
HALF SLAB TYPE HS2B (2.015x3.385) 0.135 2.015 3.39 40.92 6 5.52
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 6 115.56
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 6 25.73
Wiremesh M8-150 10.60 6 63.61
Toping Wiremesh M8-150 10.60 6 63.61

D10 115.56 Kg
D13 25.73 Kg
WIREMESH M8 127.22 M2
HALF SLAB TYPE HS3B (2.015x3.385) 0.135 2.015 3.39 40.92 6 5.52
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 6 115.56
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 6 25.73
Wiremesh M8-150 10.60 6 63.61
Toping Wiremesh M8-150 10.60 6 63.61

D10 115.56 Kg
D13 25.73 Kg
WIREMESH M8 127.22 M2

BESI EXTRA TOPING SLAB


Tul Extra D10-300 (HS1,HS2,HS3) 0.854 D 10 84 0.62 44.21 100 4,421.23
Tul Extra D10-300 (HS1A,HS2A,HS3A) 0.854 D 10 86 0.62 45.26 2 90.53
Tul Extra D10-300 (HS1B,HS2B,HS3B) 0.854 D 10 82 0.62 43.16 6 258.96
D10 4,770.72 Kg

TOTAL WIREMESH 10,441.67 M2 3,422.11 432 461.99


WIREMESH M8 5,220.84 M2

TOPING WIREMESH M8 5,220.84 M2

DIA BERAT SAT Di Buat Oleh :


D10 14,254.76
D13 1,852.59
Muhammad Alimin
TOTAL BESI 16,107.34 Kg
PERHITUNGAN VOLUME BESI HALF SLAB LANTAI 2 GEDUNG PARKIR UTARA

DIMENSI (m2) DIAMETER BESI (Kg/m)


NO. TYPE PEKERJAAN BETON h b L DETAIL TULANGAN BESI VOLUME BEKISTING QTY VOLUME BETON
(m) (m) (m) Dia Jml kg/m' Total

LANTAI 1
HALF SLAB TYPE HS1 (2.015x3.96) 0.135 2.015 3.96 1,356.50 170 183.13
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 170 3,756.21
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 170 729.03
Wiremesh M8-150 12.16 170 2,067.74
Toping Wiremesh M8-150 12.16 170 2,067.74

D10 3,756.21 Kg
` D13 729.03 Kg
WIREMESH M8 4,135.49 M2
HALF SLAB TYPE HS 2 (2.015x3.96) 0.135 2.015 3.96 678.25 85 91.56
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 85 1,878.11
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 85 364.51
Wiremesh M8-150 12.16 85 1,033.87
Toping Wiremesh M8-150 12.16 85 1,033.87

D10 1,878.11 Kg
D13 364.51 Kg
WIREMESH M8 2,067.74 M2
HALF SLAB TYPE HS 3 (2.015x3.96) 0.135 2.015 3.96 678.25 85 91.56
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 85 1,878.11
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 85 364.51
Wiremesh M8-150 12.16 85 1,033.87
Toping Wiremesh M8-150 12.16 85 1,033.87

D10 1,878.11 Kg
D13 364.51 Kg
WIREMESH M8 2,067.74 M2
HALF SLAB TYPE HS1A (2.015x4.135) 0.135 2.015 4.14 33.33 4 4.50
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 4 91.83
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 4 17.15
Wiremesh M8-150 12.64 4 50.55
Toping Wiremesh M8-150 12.64 4 50.55

D10 91.83 Kg
D13 17.15 Kg
WIREMESH M8 101.11 M2
HALF SLAB TYPE HS2A (2.015x4.135) 0.135 2.015 4.14 16.66 2 2.25
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 2 45.92
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 2 8.58
Wiremesh M8-150 12.64 2 25.28
Toping Wiremesh M8-150 12.64 2 25.28

D10 45.92 Kg
D13 8.58 Kg
WIREMESH M8 50.55 M2
HALF SLAB TYPE HS3A (2.015x4.135) 0.135 2.015 4.14 16.66 2 2.25
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 2 45.92
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 2 8.58
Wiremesh M8-150 12.64 2 25.28
Toping Wiremesh M8-150 12.64 2 25.28

D10 45.92 Kg
D13 8.58 Kg
WIREMESH M8 50.55 M2
HALF SLAB TYPE HS1B (2.015x3.385) 0.135 2.015 3.39 81.85 12 11.05
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 12 231.11
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 12 51.46
Wiremesh M8-150 10.60 12 127.22
Toping Wiremesh M8-150 10.60 12 127.22

D10 231.11 Kg
D13 51.46 Kg
WIREMESH M8 254.45 M2
HALF SLAB TYPE HS2B (2.015x3.385) 0.135 2.015 3.39 40.92 6 5.52
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 6 115.56
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 6 25.73
Wiremesh M8-150 10.60 6 63.61
Toping Wiremesh M8-150 10.60 6 63.61

D10 115.56 Kg
D13 25.73 Kg
WIREMESH M8 127.22 M2
HALF SLAB TYPE HS3B (2.015x3.385) 0.135 2.015 3.39 40.92 6 5.52
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 6 115.56
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 6 25.73
Wiremesh M8-150 10.60 6 63.61
Toping Wiremesh M8-150 10.60 6 63.61

D10 115.56 Kg
D13 25.73 Kg
WIREMESH M8 127.22 M2

BESI EXTRA TOPING SLAB


Tul Extra D10-300 (HS1,HS2,HS3) 0.854 D 10 84 0.62 44.21 85 3,758.05
Tul Extra D10-300 (HS1A,HS2A,HS3A) 0.854 D 10 86 0.62 45.26 2 90.53
Tul Extra D10-300 (HS1B,HS2B,HS3B) 0.854 D 10 82 0.62 43.16 6 258.96
D10 4,107.53 Kg

TOTAL WIREMESH 8,982.09 M2 2,943.35 372 397.35


WIREMESH M8 4,491.04 M2

TOPING WIREMESH M8 4,491.04 M2

DIA BERAT SAT Di Buat Oleh :


D10 12,265.85
D13 1,595.28
Muhammad Alimin
TOTAL BESI 13,861.13 Kg
PERHITUNGAN VOLUME BESI HALF SLAB LANTAI 3 GEDUNG PARKIR UTARA

DIMENSI (m2) DIAMETER BESI (Kg/m)


NO. TYPE PEKERJAAN BETON h b L DETAIL TULANGAN BESI VOLUME BEKISTING QTY VOLUME BETON
(m) (m) (m) Dia Jml kg/m' Total

LANTAI 1
HALF SLAB TYPE HS1 (2.015x3.96) 0.135 2.015 3.96 1,149.03 144 155.12
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 144 3,181.73
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 144 617.53
Wiremesh M8-150 12.16 144 1,751.50
Toping Wiremesh M8-150 12.16 144 1,751.50

D10 3,181.73 Kg
` D13 617.53 Kg
WIREMESH M8 3,503.00 M2
HALF SLAB TYPE HS 2 (2.015x3.96) 0.135 2.015 3.96 574.52 72 77.56
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 72 1,590.87
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 72 308.76
Wiremesh M8-150 12.16 72 875.75
Toping Wiremesh M8-150 12.16 72 875.75

D10 1,590.87 Kg
D13 308.76 Kg
WIREMESH M8 1,751.50 M2
HALF SLAB TYPE HS 3 (2.015x3.96) 0.135 2.015 3.96 574.52 72 77.56
Tul Susut D10-300 4.48 D 10 8 0.62 22.10 72 1,590.87
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 72 308.76
Wiremesh M8-150 12.16 72 875.75
Toping Wiremesh M8-150 12.16 72 875.75

D10 1,590.87 Kg
D13 308.76 Kg
WIREMESH M8 1,751.50 M2
HALF SLAB TYPE HS1A (2.015x4.135) 0.135 2.015 4.14 33.33 4 4.50
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 4 91.83
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 4 17.15
Wiremesh M8-150 12.64 4 50.55
Toping Wiremesh M8-150 12.64 4 50.55

D10 91.83 Kg
D13 17.15 Kg
WIREMESH M8 101.11 M2
HALF SLAB TYPE HS2A (2.015x4.135) 0.135 2.015 4.14 16.66 2 2.25
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 2 45.92
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 2 8.58
Wiremesh M8-150 12.64 2 25.28
Toping Wiremesh M8-150 12.64 2 25.28

D10 45.92 Kg
D13 8.58 Kg
WIREMESH M8 50.55 M2
HALF SLAB TYPE HS3A (2.015x4.135) 0.135 2.015 4.14 16.66 2 2.25
Tul Susut D10-300 4.66 D 10 8 0.62 22.96 2 45.92
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 2 8.58
Wiremesh M8-150 12.64 2 25.28
Toping Wiremesh M8-150 12.64 2 25.28

D10 45.92 Kg
D13 8.58 Kg
WIREMESH M8 50.55 M2
HALF SLAB TYPE HS1B (2.015x3.385) 0.135 2.015 3.39 68.21 10 9.21
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 10 192.59
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 10 42.88
Wiremesh M8-150 10.60 10 106.02
Toping Wiremesh M8-150 10.60 10 106.02

D10 192.59 Kg
D13 42.88 Kg
WIREMESH M8 212.04 M2
HALF SLAB TYPE HS2B (2.015x3.385) 0.135 2.015 3.39 34.10 5 4.60
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 5 96.30
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 5 21.44
Wiremesh M8-150 10.60 5 53.01
Toping Wiremesh M8-150 10.60 5 53.01

D10 96.30 Kg
D13 21.44 Kg
WIREMESH M8 106.02 M2
HALF SLAB TYPE HS3B (2.015x3.385) 0.135 2.015 3.39 34.10 5 4.60
Tul Susut D10-300 3.91 D 10 8 0.62 19.26 5 96.30
Tulangan Lifting Hook 0.51 D13 13 8 1.04 4.29 5 21.44
Wiremesh M8-150 10.60 5 53.01
Toping Wiremesh M8-150 10.60 5 53.01

D10 96.30 Kg
D13 21.44 Kg
WIREMESH M8 106.02 M2

BESI EXTRA TOPING SLAB


Tul Extra D10-300 (HS1,HS2,HS3) 0.854 D 10 84 0.62 44.21 72 3,183.29
Tul Extra D10-300 (HS1A,HS2A,HS3A) 0.854 D 10 86 0.62 45.26 2 90.53
Tul Extra D10-300 (HS1B,HS2B,HS3B) 0.854 D 10 82 0.62 43.16 5 215.80
D10 3,489.61 Kg

TOTAL WIREMESH 7,632.30 M2 2,501.14 316 337.65


WIREMESH M8 3,816.15 M2

TOPING WIREMESH M8 3,816.15 M2

DIA BERAT SAT Di Buat Oleh :


D10 10,421.93
D13 1,355.13
Muhammad Alimin
TOTAL BESI 11,777.07 Kg
VOLUME WIREMESH GEDUNG PARKIR

No Material Vol Satuan Vol Satuan Keterangan

1 Wiremesh M8 10,754.92 m2 948.4 Lembar Untuk Lt 1


2 Wiremesh M8 9,251.55 m2 815.8 Lembar Untuk Lt 2
3 Wiremesh M8 7,861.27 m2 693.2 Lembar Untuk Lt 3

Total Parkir 27,867.74 m2 2,457

Note : Berat sudah termasuk Waste 3%