No: SE-04-037
Doc.Type: Work Description
Page: 1 of 5
Author (sign): JRS Rev. date: 04.06.2012
Light Lowering and Recovery
Approved (sign): eei Rev. no: 1
Verified (sign): SFL Test Rescue boat - NDA First publ.date: 14.05.2012
AMENDMENTS REGISTER:
Rev
Originator History Date Amendment Details
No.
Doc.No: SE-04-037
Doc.Type: Work Description
Page: 2 of 5
Author (sign): JRS Rev. date: 04.06.2012
Light Lowering and Recovery
Approved (sign): eei Rev. no: 1
Verified (sign): SFL Test Rescue boat - NDA First publ.date: 14.05.2012
1 PROCESS FLOW
3 DEFINITIONS
Light Lowering Test = each launching appliances shall be arranged so that the fully equipped survival
craft can safely launched against unfavorable conditions; a trim of 10° and a list of up
to 20°.
Recovery Test= a lifeboat launching appliances shall be capable of recovering the lifeboat with
its crew.
4 RESPONSIBILITY
- (“A”)Who is Accountable for the activity or decision (Owner) Service Engineer
Only one accountable per activity (Service Station)
- (“R”)Who is Responsible (Doer)
Role / area
Activity
Preparation of the boat
Lowering and recovery Test AR
5 WORK METHOD
SN PROCESS T/E/PPE PICTURES
1 Before starting to perform lowering, Basic PPE
please read through the instruction
plate.
Doc.No: SE-04-037
Doc.Type: Work Description
Page: 3 of 5
Author (sign): JRS Rev. date: 04.06.2012
Light Lowering and Recovery
Approved (sign): eei Rev. no: 1
Verified (sign): SFL Test Rescue boat - NDA First publ.date: 14.05.2012
Note:
6 SAFETY INITIATIVE
Standard Service Engineer PPE or according to SJA, if additional risk are present.
7 REFERENCES
A list of other QHSE documents
QHSE Doc.No Title
SE-07-052 Commissioning- NDA- Rescue Boat.docx
SE-07-058 Hazard Assessment for PPE.docx