3000

50 x 50 rectangular pipe
at 3000mm width x 1500mm height
as first frame.

25 x 25 rectangular pipe
as bracing
1290

1500
2790

25 x 25 rectangular pipe
at 2790mm width x 1290mm height
as second frame.

130 130
E LEVATION: P ROJECTOR S CREEN
3000

50 x 50 rectangular pipe
at 3000mm width x 1500mm height
as first frame.

1500
Proposed mild steel
handrail @1100mm
25 x 25 rectangular pipe
from the upstand
at 2790mm width x 1290mm height
as second frame.
2700

4 nos 50mm rectangular pipe


as up-stand at 2750mm height
Existing up stand
from the finished floor level +

1200
@ 300mm
some part buried into the slab.

890 865 890

E LEVATION: P ROJECTOR S CREEN/S TAND


Screen 50mm rectangular pipe
as up-stand at 2750mm height
from the finished floor level +
some part buried into the slab.

1500

Proposed mild steel


handrail at 1100mm from the upstand
1950

1100
4 nos 50mm slanted rectangular pipe
@1950mm height to act as
1200

additional support for the vertical pipes,


part to be buried into the slab

300 Existing upstand

S ECTION: P ROJECTOR S CREEN/S TAND