WEEKLY ACCOMPLISHMENT REPORT

Name: RAYGIL BOY Dept: Technical Date Submitted: December 18, 2022
Date Time (In/Out) Particulars Location Remarks
Assist in cleaning the Gestating 2 flooring using a power
spray.
8:30 am Coordinate with the Breeding Supervisor to ask his crew
to remove manure underneath the floor slabs in
12:00nn Gestating #5.
Done
Coordinate with Nemuel and the Backhoe driver to
1:00 pm move earth to cover the pit used to bury pigs that Tigtig Farm
Dec 12’22 Done
sagged down already including the area where sacks of
manure and used apog were filled up coming from the
5:30 pm Gestation buildings.
Remove left over sand and apog in the canal in
Gestating bldg #2.
Coordinate and assist in the movement of 2 full diesel
drum from a pick-up car down the cement floor.

Done
8:30 am
12:00 in Oversee cleaning of canals in the Farrowing and Nursery Done
Dec 13’22 1:00 pm section. Tigtig Farm
5:30 pm Power spraying of pens in the Marketing building.
Done

8:30 am -
12:00 in Done
Meeting with HR with Tigtig personnel.
Dec 14’22 Tigtig Farm
Power spraying of pens in the Boar house.
1:00 pm- Done
5:30 pm
8:30 am Done
12:00 nn
Dec 15’22 Start Vacation Tigtig Farm Done
1:00 pm
5:30 pm Done

8:30 am Done
12:00 am
Done
Dec 16’22 1:0 pm Vacation Tigtig Farm
5:30 pm Done

Done

8:30 am
Done
12:00 am
Dec 17’22 Vacation Tigtig Farm Done
1:00 pm
Done
5:30 pm

8:30 am
Dec 18’22 12:00 am
Vacation Tigtig Farm Done
1:00 pm
5:30 pm