WEEKLY ACCOMPLISHMENT REPORT

Name: RAYGIL BOY Dept: Technical Date Submitted: December 12, 2022
Date Time (In/Out) Particulars Location Remarks
8:30 am

12:00nn Oversee and assist in the cleaning of pens in the


Done
Marketing, Grow Out, and Nursery buildings.
1:00 pm Oversee the power spraying procedure in other Tigtig Farm
Dec 5’22 Done
buildings.
Communicate with Mam Jecil regarding the Paraform
5:30 pm Prills as a fumigation agent.

Coordinate disposal of the dead pig left behind near the


Gestating 5 and Flat deck building.
Assist in cleaning using a power sprayer in Nursery 3.
Done
Coordination with Doc Jelvie regarding stocks like
8:30 am
“apog” and wipeout disinfectant to be drawn by Jovita
12:00 in Done
Farm.
Dec 6’22 1:00 pm Tigtig Farm
Coordinate with Mam Jecil and Mam Sharon regarding
5:30 pm
the HPS trial for Guimaras and ask for the results for
Done
submission to Ace Global.
Coordinate with Ace Global (Doc Jobbet) for the Trial
result form to be emailed to me for filling up for
Guimaras HPS trial result.
Ask Nemuel to burn the empty and contaminated sacks
of garbage at a clear site and ask personnel to look into
it so that the fire will not creep s into other sites.
8:30 am -
Ask the Nursery Supervisor to mix powder soap on the
12:00 in Done
water tank for cleaning to soften the organic materials
Dec 7’22 Tigtig Farm
during power spraying.
1:00 pm- Done
Assist in the power spraying of pens in Nursery 2.
5:30 pm
Ask Mam Sharon of Guimaras to provide the sows and
starter pigs’ ear numbers for the HPS trial result form for
submission to Ace Global.
Did an inspection on the area where the backhoe is
clearing and making the canals wider at the back of the
farm near the lots outside of the Farm perimeter.
Assist in the cleaning of Nursery House # 2 using a
8:30 am Done
power sprayer.
12:00 nn
Coordinate with the Nursery Supervisor to remove the
Dec 8’22 Tigtig Farm Done
cleaned feeders from the pens and placed-file at the side
1:00 pm
alley.
5:30 pm Done
Teach nursery personnel on how to make the whitewash
using the proportion of 1-kilo “apog” to 4 liters of water
and mix thoroughly before placing them on floors and
feeder areas of the pens.
Ask Christine to make an order powder soap to be used
for cleaning during power spraying to soften organic
materials.
Fill up the HPS trial form, picture them, and submit it to
8:30 am Done
Ace Global.
12:00 am
Coordinate with the welder to make 5 units of pork-like
Done
scoop to remove solid materials like stone, wires,
Dec 9’22 1:0 pm Tigtig Farm
plastics, etc. from the canal area.
5:30 pm Done
Instruct personnel to place sand and other materials
drawn from the canal in a corrugated or plain sheet or
Done
even in empty sacks and not place it directly in the soil
so as not to further contaminate the grounds.
Assist during cleaning of pens using a power sprayer in
the Nursery Building.
Oversee cleaning in the buildings.
8:30 am Assist in the cleaning using the power sprayer in the
Done
Nursery.
12:00 am Coordinate with Maymay (FH Supervisor) to remove the
Dec 10’22 Tigtig Farm Done
solid materials in the canal of the FH houses and place
1:00 pm them in sacks.
Done
5:30 pm Ask the welder to make another 3-5 units of pork-like
scoop to remove solid materials in the canals.
Oversee the removal/extraction of sand and other
debris in the canal in the Gestation bldg. and farrowing
bldg. # 3a.
8:30 am
Assist in the removal of plastic slats in FH#3a.
Dec 11’22 12:00 am
Coordinate and assist in the transfer and movement of a
Tigtig Farm Done
diesel drum from the warehouse into the diesel area.
1:00 pm
Communication with Sir Pat regarding the crates and
5:30 pm
pens for dismantling.
Coordinate with the night guard on duty to switch on
the lights in the pig buildings.