Professional Documents
Culture Documents
AND
(In the matter of the High Court of Sabah and Sarawak at Kuching
Originating Summons No. KCH-24NCvC -2/1-2020 (HC 2))
Between
And
BETWEEN
AND
1
[2023] 1 LNS 386 Legal Network Series
(In the matter of the High Court of Sabah and Sarawak at Kuching
Originating Summons No. KCH-24C (ARB) 1/2-2020 (HC 1))
Between
And
INTRODUCTION
[1] There are 2 appeals before us arising from decision made by the
Learned Judicial Commissioner [‘LJC’] of the High Court [‘HC’] in
Kuching, Sarawak. The 1st decision appealed against was to allow the
Respondent’s Application to enforce the Adjudication Decision [‘AD’]
dated 3.01.2020 while the 2 nd Appeal was against the LJC’s decision to
dismiss the Appellant’s Application to set aside the said AD. For
convenience, we would refer to the Appellant as ‘Jumsar’ and the
Respondent as ‘Robin Dockyard’.
[3] Robin Dockyard was at all material times involved in the business
2
[2023] 1 LNS 386 Legal Network Series
of operating dockyards and ship repair. Robin Dockyard was one of the
sub-contractors appointed by Jumsar to supply and install a 15M x 110M
x 1.325M Pipe-Frame Type Floating Pontoon [‘the Floating Pontoon’]
for the Project.
[8] Robin Dockyard delivered and installed the Floating Pontoon at the
site in early October 2018. Robin Dockyard issued various invoices to
Jumsar claiming for the contract works and other variation works carried
out in respect of the Project.
[9] Jumsar made part payments towards the invoices issued by Robin
Dockyard but withheld the remaining claims on the ground that:
3
[2023] 1 LNS 386 Legal Network Series
OUR DECISION
4
[2023] 1 LNS 386 Legal Network Series
[16] The thrust of the Appellant’s case in the HC was that the
Adjudicator in arriving at his AD had breached the established rules of
natural justice, particularly in denying the Appellant the right to be heard
on issues material to the decision-making process.
[17] For convenience, we would set out the Appellant’s broad grounds
against the LJC’s decision as follows:
[18] In dealing with the Appellant’s contention that the Adjudicator had
gone on a frolic of his own by relying on the Malaysian Audit Report
[‘MAR’] in finding that the CPC had been issued for the project, the LJC
noted that there were 2 issues in contention between the parties in the
Adjudication Proceedings:
(i) The primary issue was whether under the contract between
the parties, Robin Dockyard was to supply and install a
protection screen for the Floating Pontoon or was merely to
install a protection screen (with the provision of the
5
[2023] 1 LNS 386 Legal Network Series
[19] In essence the LJC held that it was erroneous for counsel for the
Appellant to argue to the effect that the Adjudicator had based his whole
decision on the CPC, when the CPC was merely one of the factors the
Adjudicator had taken into account in his ruling on the secondary issue.
[20] Secondly, on the issue of natural justice, the LJC rejected the
contention that the fact the Adjudicator did not ask the parties to
comment on the CPC, amounted to a breach of natural justice.
6
[2023] 1 LNS 386 Legal Network Series
[23] Essentially, the LJC concluded on the issued at hand that the above
denial of the opportunity to be heard on the CPC could not be considered
a breach of any rule of natural justice as the CPC by itself was not
conclusive evidence and the Adjudicator took cognizance of the same as
reflected in paragraph 100 of his AD.
[24] In support of the LJC’s view that the CPC is not conclusive
evidence that there were no defects in that there could be defects that
were not patent, ie, latent, the LJC made reference to Xtreme Engineering
Sdn Bhd v. Paragon Promenade Sdn Bhd [2019] 1 LNS 113, which held
that practical completion of a project denotes “a state of affairs in which
the works have been completed free from patent defects other than ones
to be ignored as trifling.”
[25] In conclusion on the issue at hand, the LJC held that the breach, if
any by Adjudicator was not material and, thus, could not be considered a
breach of natural justice in accordance with trite principle.
7
[2023] 1 LNS 386 Legal Network Series
[27] A case squarely in point that the Appellant brought to our attention
is Cantillion Ltd v. Urvasco Ltd [2008] All ER (D) 406, where Akenhead
J summarised the guidelines relating to breaches of natural justice in
adjudication cases in paragraph 57 as follows:
(b) Any breach of the rules must be more than peripheral; they
must be material breaches.
8
[2023] 1 LNS 386 Legal Network Series
[29] While we have taken cognisance of the LJC’s finding that the
additional evidence that the Adjudicator had taken into consideration in
arriving at his decision was, even though it was a document extracted
from the public domain that neither party had referred to in the
proceedings, it was not a material fact that figured importantly in the
Adjudicator’s conclusion, our view differs with that of the LJC. In our
considered view, the LJC was plainly in error when he made a finding
that there was no need for reference of the additional evidence to the
parties based on the LJC’s own speculation that the Appellant could not
have made any useful comment on it.
[30] In the LJC’s view, the act of the Adjudicator complained of was
not contrary to law by reference to Section 25 of CIPAA which provides
that:
(i) inquisitorially take the initiative to ascertain the facts and the
law required for the decision.
i) the date of issuance of the CPC was clearly not within the
9
[2023] 1 LNS 386 Legal Network Series
“If the defects on the pontoon existed before 18.10.2018, the CPC
cannot be issued out. Therefore, I determined that during the point
of handing over the pontoon is deemed to be in compliance to the
drawing, specification, and condition to be fit for handing over.”
[34] As pointed out to us, it was plainly apparent that the finding that
the floating pontoon was not damaged and was in compliance to
specification and drawing at the time of delivery or handing over was
made purely based on the issuance of CPC on 18.10.2018 as stated in the
said report.
10
[2023] 1 LNS 386 Legal Network Series
[37] The Respondent, on the other hand, urged us to consider that it was
undisputed that the evidence pertaining to the Protection Screen was
before the Adjudicator where the parties had also presented their case
pertaining to this subject to the Adjudicator.
[39] The Respondent’s contrary contention on this point was that the
above complaint had taken the AD out of context in that para 91 was only
a part of the AD’s ‘Findings and Reasons’. In his determination at para
92, the Adjudicator had decided that the absence of the protection screen
on the completed Pontoon did not constitute any omission of work from
the contract having considered the revised quotation dated 4/6/2018. As
such, it was submitted that the AD had merely decided to accept the
Respondent’s version of the case.
11
[2023] 1 LNS 386 Legal Network Series
LJC had erred in law and fact in failing to apply correctly established
principles governing the concept of natural justice. In our c onsidered
view, the LJC had consequently wrongly concluded that the Adjudicator
had not breached the rule of natural justice in regard to the right to be
heard when he took into consideration extraneous documents and/or
evidence not referred to by either or both of the litigating parties on core
issues in dispute. We are not in agreement with the Respondent‘s
contention that the impugned document or evidence was not a material
factor in the decision-making process by the Adjudicator in the present
Adjudication.
[42] The Adjudicator, in our view, should have rightly adopted the
simple step of disclosing the additional evidence procured by him from
an external source to the parties concerned to dispel any notion or
suggestion of injustice. [See WRP Asia Pacific Sdn Bhd v. NS
Bluescope Lysaght Malaysia Sdn Bhd [2015] 1 LNS 1236.
12
[2023] 1 LNS 386 Legal Network Series
[45] Importantly, the adjudicator relied on the CPC date in the said
report which he sourced for from the public domain to conclude that the
damage to the floating pontoon did not exist at the time of handing over
and the floating pontoon is in compliance to the drawing, specification
and conditions as agreed upon to be fit for handing over.
[46] Hence, the contention that the CPC was not a material factor but
only one of the several factors that led to the conclusion reached on the
core issues by the Adjudicator fails. On the contrary, it clearly was of
considerable importance and had a decisive effect as pointed out by the
Appellant.
CONCLUSION
[47] While we do not take any issue with the Respondent’s proposition
that even if the Adjudicator had erred in his finding, it is well established
that a wrong finding by the Adjudicator under CIPAA only amounts to a
breach of natural justice in very limited circumstances, the Respondent’s
submission that the said limited circumstances were not existent in the
instant case was wholly misconceived.
13
[2023] 1 LNS 386 Legal Network Series
[50] The issue of CPC or the AG report was never raised by the any
party nor were they were given an opportunity to address the Adjudicator
before he arrived at his decision at the conclusion of the Adjudication
proceedings.
[51] Our view is that the aforesaid breach of due process by the
Adjudicator was fundamental to warrant interference by us. Hence, the
LJC had plainly erred in law and fact in his decision to dismiss the
Appellant’s application to set aside the AD and to allow the
Respondent’s application to enforce the AD.
[52] We, therefore, allow both appeals with costs of RM15,000.00 here
and below subject to allocator in respect of the 1 st appeal and
RM5,000.00 here and below subject to allocator in respect of the 2 nd
appeal. The orders made by the LJC are hereby accordingly set aside.
(GUNALAN MUNIANDY)
Judge Court of Appeal
Putrajaya
Counsel:
For the appelant - Liew Sheau Kie; M/s Loke, King, Goh & Partners
Advocates
For the respondent - Alvin Yong Sze Lung & Wong Chun Ming; M/s Alvin
Yong Advocates
14