PEKERJAAN PENAMBAHAN LOADING DOCK + 0,95 PROYEK PT.

ROYAL SUTAN AGUNG CILINCING


JAKARTA UTARA
KEBUTUHAN MATERIAL
Harga
No. Uraian Pekerjaan Volume Sat Jumlah Rp.
Sat
1 BESI BETON 16 ULIR SNI 21.00 BTG 210,000 4,410,000
2 BESI BETON 13 ULIR SNI 115.00 BTG 133,000 15,295,000
3 BESI BETON 10 POLOS SNI 40.00 BTG 80,000 3,200,000
4 BESI BETON 16 POLOS SNI 5.00 BTG 207,000 1,035,000
5 BESI WHIREMES M8 42.00 LBR 660,000 27,720,000
6 BESI SIKU 50 X 50 7.00 BTG 295,000 2,065,000
7 BESI ANGKUR 13 MM 67.00 PCS 75,000 5,025,000
8 BESI PIPA 2" 3.00 BTG 1,075,000 3,225,000
9 TRIPLEX 9 MM 42.00 LBR 120,000 5,040,000
10 KASO 5 / 7 3.00 m³ 2,500,000 7,500,000
11 PAKU KAYU 15.00 KG 20,000 300,000
12 MACADAM 216.00 m³ 190,000 41,040,000
13 PASIR URUG 11.00 m³ 150,000 1,650,000
14 PLASTIK COR 7.00 KG 20,000 140,000
15 CEMENT 3 RODA 50 KG 10.00 SAK 73,000 730,000
16 KAWAT BENDRAT 1.00 ROL 400,000 400,000
17 SIKA CAPDUR 25 KG > LOADING DOCK 20 SAK + PERBAIKAN LANTAI 57 77.00 SAK