HP Field Visit Report

Name of Work:- Upgradation of Jamta to Birla Road Km 0/000 to 21/330 km

Package No. HP-10-290


Starting Village : Jamta
End Village : Birla
Design code : IRC 37-2018 & IRC 72-2015
Traffic Category T6
MSA 0.57
CBR 5.91 %
Cost of DPR
Construction Cost = 2023.44 Lakh
Maintainace Cost = 921.02 Lakh
Total Cost = 2944.46 lakh

1. ROFD= 39934.60 cum


2. Protection work
R/wall in PCC = 170 mtr
B/wall in PCC = 205 mtr
Wire crate in R/wall = 220 mtr
Wire crate in B/wall = 285 mtr
E/wall PCC = 505 mtr
R/wall in RR Masonry= 235 mtr
B/wall in RR Masonry= 120 mtr

3. Observations on CD structures chainage wise

Existing HPC: = 64 no.


New
HPC : 1no.
Box culvert: 9 no.

4. Existing Crust Details

Base Layer +Sub Base Layer = 240 mm


Top Surface BC = 20 mm
Proposed Thickness of Pavement Components
Existing and widening portion
In situ stabilization (FDR) 200 mm
BC 40 mm

5. Rigid Pavement (Paver Block)

Length= 1405m
GSB = 150 mm
WMM = 150 mm
Paver Block = 80mm

6. Observations on Pucca Drain

U-Shape Drain 758.40 m

V-Shape Drain 2320.20 m

Unlined Drain 17991 m

7. Road Safety
i) Crash Barriers: - 390 m
ii) Other Provisions if any:-

8. Road furniture
i) PMGSY Boards 4 Nos
ii) Other Sign Boards 100 Nos
iii) Road Studs and Markings 702 Nos/Rmt

Tentative revision in cost


Initial Proposal Revised Proposal Cost Reduction

Construction Proposed Average Revised Revised Average Total Average %


cost (lakh) length cost Construction Proposed cost Cost cost reduction
(km) (lakh/km) cost (lakh) length (lakh/km) saving saving in cost
(km) (lakh) /km/lakh /km
2023.44 21.330 94.86