You are on page 1of 10

SPE-182441-MS

Well Abandonment Project and Recommendation for Applying Activity


Based Cost/Earn Value Management

Afriandi Eka Prasetya and Shanni Ardhana Herputra, SKK Migas

Copyright 2016, Society of Petroleum Engineers

This paper was prepared for presentation at the SPE Asia Pacific Oil & Gas Conference and Exhibition held in Perth, Australia, 25-27 October 2016.

This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.

Abstract
Review the Activity Based Costing (ABC) and Earned Value Management (EVM) fundamentals of being
applied to the case study. Examine the constraints and its feasibilities in recommending the implementation
of ABC combined with EVM to well abandonment projects.
Well abandonment project is one of phase in the oil well's life span that must be done after it is no
longer producing and to protect environment. Instead of giving revenue, well abandonment projects are
spending money. To fulfill its deliverables with cost-effectively and in timely manner, the project coverage
requires good planning, scheduling, and control. This paper is an actual case study which documents the
abandonment of 7 oil wells located in Indonesia. ABC assigns resource costs to a cost object based on
activities performed for the cost object. EVM coordinates the work scope, schedule, and cost goals of a
program or contract, and objectively measures progress toward these goals.
By applying the fundamentals of ABC and EVM, the abandonment project of 7 oil wells was completed
in a total of 131 days, a slippage of 12% over the approved plan of 117 days and at a total cost of 1.078
million USD, versus the target cost of 1.074 million dollars.
This paper explores the step-by-step process that is used to create the Baseline Schedule, track
the progress against the schedule and report to the appropriate stakeholders. The paper concludes by
recommending ABC combined with EVM be applied to other well abandonment projects.
Keywords: well abandonment, project management, activity based cost, earn value management, project
control

Introduction
Well abandonment project is one of phase in the oil well's life span that must be done after it is no longer
producing and to protect environment. Instead of giving revenue, well abandonment projects are spending
money. Usually, the project covers site clearance work, pull the string out of hole, plugging the hole, and
managing the mob/demob of equipment between sites. The environmental restoration will be done in a
separate project. To fulfill its deliverables with cost-effectively and in timely manner, the project coverage
requires good planning, scheduling, and control.
2 SPE-182441-MS

Activity based costing (ABC) and earned value management (EVM) were very well-known as
methodologies that measure cost and performance of projects. ABC assigns resource costs to a cost object
based on activities performed for the cost object. EVM coordinates the work scope, schedule, and cost goals
of a program or contract, and objectively measures progress toward these goals.
The abandonment project of 7 oil wells, onshore located in Indonesia, was completed in year 2012 with
a total of 131 days, a slippage of 12% over the approved plan of 117 days and at a total cost of 1.078
million USD, versus the target cost of 1.074 million dollars. This case was recorded as a successful project
management in well abandonment. There are many well abandonment projects in Indonesia and many more
potentials not properly planned, scheduled and controlled as well.
This paper explores the step-by-step process that is used to create the Baseline Schedule, track
the progress against the schedule and report to the appropriate stakeholders. Review the ABC and
EVM fundamentals of being applied to the case study. Examine the constraints and its feasibilities in
recommending the implementation of ABC combined with EVM to other well abandonment projects.

Well Abandonment
The terms of well abandonment is about plugging the wells in connection with: temporary suspension,
temporary or permanent abandonment of wells, permanent abandonment of a section of a well. The
definition of each terms described in Table 1 is summarized after NORSOK D-010.

Table 1—Description of Well Abandonment (after NORSOK D-010)

No Terms of Well Description


Abandonment

1 Temporary Suspension temporary suspension of well activities and operations without removing the well control equipment

2 Temporary Abandonment where the well is abandoned and/or the well control equipment is removed, with the intention that the
operation will be resumed within a specified time frame (from days up to several years)

3 Permanent Abandonment permanent abandonment of a section of a well (side tracking, slot recovery) to construct a new wellbore
with a new geological well target

where the well or part of the well, will be plugged and abandoned permanently, and with the intention of
never being used or re-entered again.

The critical issues must be taken care of in abandoning the well are about the well barrier and the well
integrity. Well barrier preventing fluids or gases from flowing unintentionally from the formation, into
another formation or to surface with envelope of one or several dependent barrier elements. According to
NORSOK D-010, well integrity applies technical, operational and organizational solutions to reduce risk
of uncontrolled release of formation fluids throughout the life cycle of a well.
Well intervention operation by deploying tools and equipment (e.g. coiled tubing, wireline, snubbing,
crane or even rig) is delivered to abandoning the well. The well abandonment project explored in this paper
is applying permanent abandonment with proper well barrier and without any further integrity issues and
in compliance with the regulations those exist.
Prior to the well abandonment job, site clearance job including access road preparation usually completed
by the civil works, as different team to the well intervention team. Abandonment activities started after
the well intervention team moved and rigged up their equipments at the well site. The activities are: well
integrity checking, pulling the production tubing out of the hole, and pumping the cements to plug the
appropriate zone.
The conditions of 7 oil wells put in this abandonment project are some of them have lost their wellheads
(Fig. 1), poor well integrity, as well as potentially harmful to the environment. The company proposes the
SPE-182441-MS 3

well abandonment program, consists of well schematic comparison between the existing and the proposed
(Fig. 2), and the abandonment procedures which are standard compliants.

Figure 1—Wellhead(less) condition which is potentially harmful to environment as the reason for well abandonment

Figure 2—Well schematic comparison between the existing and the proposed for well abandonment

Project Cost and Budget Control


Instead of giving revenue, well abandonment projects are spending money. As one of the petroleum
operation defined in the Production Sharing Contract (PSC), all the expenses occurred in this project are cost
recoverable. The government requires credible and reliable cost estimates to support decision of funding,
budget requests and evaluation. High quality cost estimates that are comprehensive and accurate can be
developed by following the cost estimating process as recommended in GAO-09-3SP.
The costs estimated for the well abandonment project can be generated from the accounting records,
engineering sources, and contract documents. According to Generic Cost Estimate Classification Matrix
4 SPE-182441-MS

recommended by Amos, 2012, this estimating method will produce Class 2 cost estimate with the expected
acuracy range is +10/−5%.
The company proposes the budget using specified expenditure schedule. This expenditure schedule
summarizes the expenditure budget of particular projects. It consists of classification and breakdown in
terms of cost categories or elements. The purposes in utilizing such standard form are to provide the unit
costs for trends and comparisons study and estimate profitability. This traditional kind is also helpful for
evaluating the quotations of related services.

Activity Based Costing


When the big variance between the actual cost and the plan budgeted occurred, the expenditure schedule
helps us to know such problem. But it does not help how to solve the problem. Activity based costing (ABC)
offers the need to identify sources of problem related to cost. ABC does not replace the traditional cost
accounting system (general ledger) as it is different than a method of costing. In short, ABC reveals the cost
of complexity, points out where it is and where it comes from (Cokins, 2003).
As a technique for managing the project, ABC measures the cost and performance of activities, resources
and the objects which report more accurate and meaningful information. The information can be used in
decision making, or further financial management.

Earned Value Management


To measure project performance and progress objectively, a methodology of management definition and
control which integrates the scope, schedule, and budget or resources is needed. This methodology is called
earned value management (EVM). To facilitate the project management, the use of EVM System follow the
process defined in the master flowchart as recommended by Humphreys, 2011.
According to Lewis, 20111, three measures are provided by the earned value system to determine project
status. These are measures of what is supposed to be done, the budgeted cost of work scheduled (BCWS) or
planned value (PV); what has actually been done, the budgeted cost of work performed (BCWP) or earned
value (EV); and the amount of effort or cost that has been expended to do the work, the actual cost of work
performed (ACWP) or actual cost (AC).
When utilized properly, EVM can provide early warning for project related problems. Wibiksana, 2012
recommend that EVM can be applied in short duration project. As a short time scheduled project, EVM is
challenged as appropriate application in measuring performance and progress of well abandonment project.

Problem Statement
Since the works are beneath the surface ground, well work activities always face uncertainties. The well
work project requires proper and comprehensive planning and controlling, and all resources require should
be well prepared. Continuous monitoring, measuring and controlling the activity during execution will
ensure it deliver as per plans and prompt response to any deviations and will make the project successful.
Drilling activities use the Chart of Time versus Depth versus Cost (TDC Chart) in measuring drilling
performance and progress. The performance is measured by its consistency to the plan curve and the progress
is shown by the depth drilled. The useful of this chart is the problem will immediately identified when the
line is shown flat or deviated from the plan curve.
Well servicing activities cannot use TDC Chart to measure its performance and progress. Since the wells
are already drilled, constructed and produced, the depth curve is not appropriate to serve as the progress
information. The cost curve will be the chart which provides the performance information as well as a
progress tracking tool.
SPE-182441-MS 5

As a project, well abandonment as well as work activities with the very short duration needs the
accurate method of project monitoring, measurement, control and reporting. These needs allow the project
management to promptly respond to any problems that will affect the project completion.

The Well Abandonment Project: ABC and EVM Application


The well abandonment project management explores the step by step of the following process to be done:

Step 1. Project Definition


The company creates project objectives as follow: the wells which are not producing or no further
intervention and in risk condition or in low integrity level need to plugged and abandoned, the job must
be done immediately and no longer than 6 months, using the equipments which are ready without any new
long procurement process, with a budget under $150 000.
The work scope definition using the work breakdown structure (WBS) helps to segregate the work into
manageable components and avoiding later nightmares of scope changes and litigations. WBS will also
helpful to calculate project cost estimation, planning and scheduling, and create schedule monitoring using
Gantt chart and or performance measurement chart.
Displaying subdivision of the project into smaller and more manageable segments of work, WBS is a
product-oriented, includes all work, support historical cost collection for future cost estimating purposes
(Humphreys, 2011). Fig. 3 shows a simplified WBS for the Well Abandonment project.

Figure 3—Work Breakdown Structure for Well Abandonment Project

Step 2. Team Assignment and Responsibility


The company assigned 3 teams involved in this project. Team #1 is civil work team who responsible for
the site clearance job and access road preparation. Team #2 is well intervention team who responsible for
the plug and abandonment job. Team #3 is the rig team who will involved in heavy work programmed in
the well #7.
Team #1 prepares 7 well sites and its access roads in sequential works. The well site #1 must be ready
prior the mobilization of Team #2 into the well site. Each site is planned to be worked in 7 days. While the
Team #1 working on the Site #1, Team #2 can move to do the civil works in location #2 and so on.
The job of Team #2 is the primary to the project objectives: plug and abandon the wells. They must
responsible in their equipments readiness. Assuring the moving in and rigging up (MIRU) operation,
checking the integrity of the well prior pulling the tubing and plug cementing the formation, then rigging
down (RD) the equipments, and cleaning up the location before moving out to the next site. For these
6 SPE-182441-MS

reasons the project leader is assigned from the Team #2 to collaborate with the other teams and manage
the works as scheduled.

Step 3. Scheduling and updating


The schedule is created to accomplish project objectives on time. It is also used to measure performance
against the plan. The schedule conveys communication throughout the duration of a project: prioritization,
status information, problem area identification, and corrective action support. To meet the government need
of the high quality and reliable schedule, the US GAO's ten best practices can be adopted. All activities are
captured and sequenced to help everyone understand the milestone and its drive. The duration established
to all activities. Scheduling must have the flexibility according to available resources to be assigned.
Contingency plan to risk mitigation and changes in the program can help the schedule to forecast the effects
of actions taken by the program management.
The logical relationship of site preparation job and the P&A job in Well #1 is "start to start" where the
Well #1 job can begin after the location for the Well #1 is completely prepared. The relationships between
wells are "finish to start" due to the limitation of the well intervention equipments performed for these job.
For the job on the Well #7, while the relationships of the second team between Well #6 and Well #7 still
"finish to start", the joining of the third team makes the relationship is "finish to finish" which the third team
cannot finish until the second team's previous job is finished.
Gantt chart is used for scheduling for its simplicity, easy to understand, and requires a minimum of time
to develop and update (Humphreys, 2011). The well abandonment project only last at maximum 20 days
per wells, the use of Gantt chart as shown in Fig. 4 will ease the team to update instead of bother, while
they working on the job.

Figure 4—Gantt chart schedule and budget of well abandonment project

Step 4. Estimating the duration and cost


By using historical data of job and the current contracts, the tasks that already broken down is estimated for
the job duration and cost. This Class 2 cost estimate completes 30% to 70% of project definition. Within
this level, it is expected the input information available to the estimating process is reliable. This level has
also gone beyond the budget purpose. The effort to prepare this estimate level is less as the data is readily
available so that the accuracy is expected to +10/-5% only (DOE G 413.3-21). In addition to expenditure
schedule table, the cost breakdown which is reconstructed to create an ABC table following the tasks defined
in WBS shown in Fig. 5.
SPE-182441-MS 7

Figure 5—Reconstruction of the project cost breakdown to ABC


which can be used to identify sources of problem related to cost.

The site preparation for each location is budgeted for 7 working days. The moving time is calculated
according to the distances between location, the equipment loads and the trailer availability. The pulling
time will depends on the wellbore schematic and the integrity check result, but 4 days budget is allocated
for the work. Plug and cementing for each interval in compliance to the government standard and regulation
is calculated based on the information provided in the wellbore schematic. Rig down and clean up usually
takes 2 days only.
The company was proposing with the same number of duration and budget for each P&A of 7 wells job
except for the Well #7 which require additional rig job. Following the method discussed above, the proposal
was then evaluated and resulting the approved budget of 1.017 million USD is 17% cut.

Step 5. Earn Value and Baseline Development


The same tasks in the WBS are used to develop earned value system. A baseline curve called Planned Value
(PV) or Budgeted Cost of Work Scheduled (BCWS) is built based on the scope of work, schedule and
budget. Measuring accomplishment type used in this study is discrete effort using units complete technique
that match to the work characteristic.

Step 6. Performance Measurement and Estimate at Completion


Actual cost is collected from the direct and indirect costs data source in related to the labor, material, other
direct costs and subcontracts. The performance measurement is used to evaluate the progress and develop
accurate forecasts.
In the seventh period of week program it is measured that the site preparation task is 85% complete to
provide the location ready to be accessed by the well intervention equipments. This number is to mention
that six of seven locations are already completed. The P&A job status for the Well #1 is already completed,
while the job for the Well #2 is being progress. The Well #2 job having problem when pulling out of hole
the production tubing and need additional time to be recovered.
As shown in Fig. 6, the ACWP and BCWP curves are below the baseline (BCWS) curve. These curves
give us information that the schedule variance (SV) and the cost variance (CV) are unfavorable (projected
cost overrun). The costs expected to be spent from "now" to the end of the project is considered as estimate
at completion (EAC). For this project, EAC is calculated at the number 24% overrun from the budget.
8 SPE-182441-MS

Figure 6—The Earned Value and Baseline Chart for the Week 7 gives the information
that the progress of the work is behind schedule and the cost will be overrun.

The cost performance (CPI) and the schedule performance indices (SPI) are the ratio that measure
efficiency. According to Fig. 6, the calculated CPI is 0.81 and SPI is 0.74. These numbers also suggest that
the progress of the work is behind schedule and the cost will be overrun. Predicting the cost will be 50%
over budget, the company is proposing to revise the budget for this particular job.

Step 7. Variance Analysis and Corrective Action


The problem in the Well #2 job is then identified and manageable. With the information collected it was
expected that the same problem will be less to be occurred in the future sequences. The impact of the
problem to the EAC need corrective action plan to be developed for future monitoring. Budget revision for
this particular job proposed by the company must be followed by the baseline revision on the performance
measurement. General rules to this revision are the current period or the past cannot be changed, the budget
is always moved with its scope, and the cost variances are still exist although the work package or the
control account is closed.
The baseline revision shown in Fig. 7 gives us information that the budget will not exceed 24% as
predicted in the EAC. Using the same method of cost estimation discussed above, the government approved
an amount of 1.074 million dollars as the budget revision to complete this project. The project was then
continued without any significant problems and the performance measurement was then continued until all
tasks defined in this project were complete.

Figure 7—The Earned Value and Baseline Revision Chart as a result


of variance analysis and corrective action for future monitoring.

The Well Abandonment Project: At Completion


At completion, the performance chart is shown in Fig. 8. It gives us information that the time to complete
the project was slid about 2 weeks behind the schedule but the budget is slipped only 0.42% of the revised
SPE-182441-MS 9

budget. The final number CPI 1.0 and SPI 1.0 showing us that a credible cost estimation will result a very
accurate level of actual expenses.

Figure 8—The Earned Value at the Project Completion which gives the information that the time to complete the
project was slid about 2 weeks behind the schedule but the budget is slipped only 0.42% of the revised budget.

Fig. 9 shows the Gantt chart at the completion. It gives us another information that the site preparation
task done by the Team #1 also slipped about 11 days from the plan schedule and 28% budget overrun. Some
optimization have been made so that the well abandonment job conducted faster that its plan.

Figure 9—Project Gantt chart, Budget and Actual Cost at the completion

As a result in applying the fundamentals of ABC and EVM, the abandonment project of 7 oil wells was
completed in a total of 131 days, a slippage of 12% over the approved plan of 117 days and at a total cost
of 1.078 million USD, versus the target cost of 1.074 million dollars.
The case study of the well abandonment project shows that proper planning, scheduling and controlling
are necessity to guiding project to its successful conclusion. The constraints of this process are the resistants
to provide such level of detail in defining project objectives and scope of works. A thorough assessment in
scheduling and cost estimating also plays the role for a credible and reliable budgeting.

Conclusions
Applying ABC and EVM fundamentals is a new approach to the well abandonment project management. As
one of the petroleum operation, according to PSC, the well abandonment projects are part of the government
project. The government requires a high quality budget estimation and objective project management
process for they project.
The step by step of the project management process presented in this paper has implementing the ABC and
EVM methodology. The final number CPI 1.0 and SPI 1.0 shows that a credible cost estimation will result a
very accurate level of actual expenses. ABC and EVM approach answer the needs of the accurate method of
10 SPE-182441-MS

project monitoring, measurement, control and reporting to allow the project management promptly responds
to any problems that will affect the project completion.
The ABC combined with EVM is recommended to be implemented to other well abandonment project
as well as work activities with the very short duration.

Acknowledgement
The authors wish to thank the management of SKK Migas for permission to publish this paper and recognize
ConocoPhillips Indonesia Inc. Ltd for their supports. The authors also wish to acknowledge all the parties
who kindly provide valuable works and contributions to support the preparation and presentation of this
paper.

Nomenclature
ABC = Activity Based Costing
ACWP = Actual Cost of Work Performed
BCWP = Budgeted Cost of Work Performed
BCWS = Budgeted Cost of Work Scheduled
CPI = Cost Performance Index
CV = Cost Variance
EAC = Estimate at Completion
EVM = Earn Value Management
MIRU = Moving In and Rigging Up
P&A = Plug and Abandonment
PSC = Production Sharing Contract
PV = Planned Value
RD = Rigging Down
SPI = Schedule Performance Index
SV = Schedule Variance
WBS = Work Breakdown Structure

References
Amos, S. J., & AACE International (2012). Skills & knowledge of cost engineering: A continuing project of the AACE
International Education Board (5th ed.). Morgantown, WV: AACE International.
Cokins, G. (2001). Activity-based cost management: An executive's guide. New York, NY: Wiley.
Humphreys, G. C. (2011). Project management using earned value (2nd ed.). Orange, CA: Humphreys & Associates, Inc.
Lewis, J. P. (2011). Project planning scheduling & control: The ultimate hands-on guide to bringing projects in on time
and on budget (5th ed.). New York, NY: McGraw-Hill.
Smith, D. K. (1993). Handbook on well plugging and abandonment. Tulsa, OK: PennWell Books.
Standards Norway (2004). NORSOK standard: Well integrity in drilling and well operations (D-010 Rev. 3)
United States. Department of Energy. Office of Management (2011). Cost estimating guide (DOE G 413.3-21)
United States. Government Accountability Office (2009). GAO cost estimating and assessment guide: Best practices for
developing and managing capital program costs (GAO-09-3SP)
Wibiksana, R. (2012). EVM Adapted for Underground Mining Operations. PM World Journal, 1(2). Retrieved from
www.pmworldjournal.net

You might also like