1. Why do certain upgrades require a larger PDU?
(Choose all correct answers)
(0/1) Points
The rack is connected to a storage expansion rack
All servers ship with an adequately sized PDU already
There are more than 11 servers in the 2 socket machine (*)
There are more than 4 servers in an 8 socket Exadata machine (*)
Incorrect! Please review the courses and try again.
3. Select all the tasks done in the Pre-site check for an upgrade?
(Choose all correct answers)
(0/1) Points
Have all the population rules been followed? (*)
Verify the number of servers fit and the PDUs support the max load (*)
Is the upper cable harness kit required and present? (*)
Are all of the necessary kits for an elastic configuration ordered and
delivered? (*)
Incorrect! Please review the courses and try again.
4. Select the server that is the heaviest.
(1/1) Points
Extreme Flash Storage Servers
They are equal in weight
High Capacity Storage Servers (*)
Database Servers
Correct !
Extreme Flash and NVMe
(Answer all questions in this section)
5. Select the considerations for performing a hot removal of an NVMe drive.
(Choose all correct answers)
(0/1) Points
Check to make sure the LED light is green indicating "Ready to Remove"
alter physicaldisk NVME_# drop for replacement (*)
Check to make sure the LED light is blue indicating "Ready to Remove" (*)
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
17. In a base rack (1/8) configuration how many 128 GB DCPMM DIMMs are
installed?
(1/1) Points
12 (*)
9
0
6
Correct !
18. What are the differences in the storage servers on an Exadata X8M HC
and an Exadata X8M ZDLRA? (Select 2 answers)
(Choose all correct answers)
(0/1) Points
Only six DCPMM DIMMs installed on the ZDLRA storage server
No DCPMM DIMMS installed on the ZDLRA storage server (*)
Only two F640 flashcards installed on the ZDLRA storage servers (*)
There are no differences between the two storage servers
Incorrect! Please review the relevant Exadata X8M TOI courses and try again.
19. What features are included in the Exadata X8M that are not included in
the Exadata X8? (Select 3 answers)
(Choose all correct answers)
(0/1) Points
RDMA Network Fabric: QSFP28 100G RDDMA Ethernet Card, RDMA Enabled
Ethernet Switch (*)
PMEM Acceleration: Persistent Memory Data & Commit Accelerator, 128GB
DC Persistent memory Modules (*)
Extended Term (XT) Storage Server
KVM Virtualization (*)
Incorrect! Please review the relevant Exadata X8M TOI courses and try again.
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
23. What are the advantages of RDMA Persistent Memory over Flashcache?
(Select 2 answers)
(Choose all correct answers)
(0/1) Points
Reads at memory speeds (*)
Cheaper than flash cards (*)
Higher Capacity
Incorrect! Please review the relevant Exadata X8M TOI courses and try again.
24. How is PMEM on the storage server accessed from the database server?
(0/1) Points
DB server uses RDMA to directly access remote PMEM on storage server (*)
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
OVM Deployment
(Answer all questions in this section)
26. How is the grid infrastructe installed on the VM Cluster?
(0/1) Points
Separately on each cluster (*)
Grid infrastructure is not installed on the VM Cluster
On shared storage on the storage cell
Incorrect! Please review the course "Exadata Software Architecture and OVM Overview"
content and try again.
28. What is the command to select ovm as the primary operating system
only?
(0/1) Points
prim_ovm.sh
convert_ovm.sh
OVM is chosen as a factory setting
OVM is chosen in OEDA
switch_to_ovm.sh (*)
Incorrect! Please review the course "Exadata Software Architecture and OVM Overview"
content and try again.
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Elastic Configuration
(Answer all questions in this section)
31. What is the key reason for the existance of Exadata population rules?
(0/1) Points
There are no population rules for Exadata, the configuration is elastic
To ensure racks are configured similarly across customers
To avoid top heavy racks (*)
To ensure that lighter systems are in the lower positon
Incorrect! Please review the course "Elastic Configuration Rules and Best Practices" content and
try again.
32. Your customer requests an install with a mix of Extreme Flash and High
Capacity Storage servers. What is your response?
(0/1) Points
This is a supported configurtaion. Extreme Flash and High Capacity can exist
in the same rack (*)
This is not a supported configuration, Extreme Flash storage cannot mix with
High Capacity
This is a supported configuration for X5-2 only
Incorrect! Please review the course "Elastic Configuration Rules and Best Practices" content and
try again.
33. How can the baseline config be determined for an Exadata Elastic Scale-
Out configuration
(0/1) Points
Install.sh checks configuration validity
baseline_config.sh
OECA (*)
Any baseline config is acceptable
OEDA
Incorrect! Please review the course "Elastic Configuration Rules and Best Practices" content and
try again.
34. Can the slots alloted for the switches be used for database or storage
servers?
(0/1) Points
Yes, for database servers only
Yes for X4-8 servers only
Yes, for storage servers only
Yes, for Exadata Expansion Racks only
No, those slots are reserved for network comoponents (*)
Incorrect! Please review the course "Elastic Configuration Rules and Best Practices" content and
try again.
35. What is a cable trough?
(0/1) Points
The storage location for all connected cables in exadata
Not a feature used in Exadata, Supercluster only
A storage for cables in empty slots (*)
Incorrect! Please review the course "Elastic Configuration Rules and Best Practices" content and
try again.
Previous Page 7 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
37. Why does Exadata X9M require 7 uplinks from leaf to spine vs 4 uplinks
on previous generations?
(0/1) Points
To increase the throughput to 400 gb/s
There is a significant increase in over-subscription due to Gen4 PCIe speeds
on Exadata X9m requiring additional uplinks from leaf to spine. (*)
To eliminate dropped packets
To enable secure fabric between switches
Incorrect! Please review the course content and try again.
38. There are now 3 RoCE X9M Golden Config multi-rack templates.
(1/1) Points
False
True (*)
Correct !
39. How many uplinks per rack are now needed for multi-racking the
Exadata X9M?
(0/1) Points
56
14
28 (*)
7
Incorrect! Please review the course content and try again.
40. We now use patchmgr to apply the Golden Config on the RoCE Network
Fabric switches.
(1/1) Points
True (*)
False
Correct !
Previous Page 8 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
42. When multi-racking a new Exadata X9M rack to an existing Exadata X8M
rack, additional uplinks will need to be added to the X8M rack.
(1/1) Points
False
True (*)
Correct !
43. What is the primary change to the X9M Golden Config for the RoCE leaf
switches?
(1/1) Points
All network ports on the leaf switches are configured as Edge ports
Port 1-3 and 34-36 are now configured as router ports and connected to the
spines. (*)
One Golden Config for all deployment types.
The Golden Config is on the leaf switch from the factory
Correct !
44. When adding a ZFS Appliance to the RDMA Network Fabric of a multi-
racked Exadata X9M, 2 hosts will have to be removed from the rack.
(1/1) Points
True (*)
False
Correct !
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
48. Which document lists the details of the supported software versions of
ZDLRA?
(0/1) Points
All of the above
ZDLRA Release and Patching Policy (Doc ID 2410137.1)
Zero Data Loss Recovery Appliance Supported Versions (Doc ID
1927416.1) (*)
Release Schedule of Current Database Releases (Doc ID 742060.1)
Incorrect! Please review the course content and try again.
49. Which add-in PCIe card is newly supported on the ZDLRA X9M?
(0/1) Points
Qlogic 16gb Fiber Channel PCIe card
8-Port 12Gbps SAS-3 HBA (External)
Dual 10/25 Gigabit SFP28 Ethernet
Quad-port 10 Gigabit RJ-45 Copper (Fort Pond) Network PCIe Card (*)
Incorrect! Please review the course content and try again.
50. What size disk drive is used in the ZDLRA X9M Storage server?
(1/1) Points
14TB
18TB (*)
10TB
8TB
Correct !
Previous Page 10 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
53. What are the two primary objectives for the Installation Configuration
Planning step of the EIS methodology?
(Choose all correct answers)
(1/1) Points
Oracle/Partner confirms power and cooling requirements for system
installation
*Tests that will be performed during the Systems Testing will be defined. (*)
*Oracle/Partner and Customer will determine and mutually agree upon the
hardware and software installation requirements which will be documented
in the Installation and Configuration Plan (*)
Customer provides walk-through of installation site
Correct!
54. What two activities are accomplished during Installation Task Planning
step in the EIS Methodology?
(Choose all correct answers)
(1/1) Points
System unpacking and acclimatization
Networking and system component cabling
*Communicate schedule for installation to the customer (*)
*Organization of the team who will actively work the Installation (*)
Review the timeframe options for delivery of the service
Correct!
55. What are two cautions that should be acknowledged when acclimatizing
a system?
(Choose all correct answers)
(1/1) Points
Once powered on the temperature is no longer an issue, as internal cooling
systems commence
*The maximum positive or negative temperature gradient that is permitted
for multi-layer<br>boards is approximately 2° C (4° F) per hour. (*)
*Avoid unpacking items inside the computer centre (dust/dirt contaminating
filters etc.) (*)
Powering ON the system will speed the acclimatization process as the heat
from the system will accelerate its warming
Correct!
Previous Page 11 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
57. What three typical activities are done during the Project Initiation phase
of the EIS Methodology?
(Choose all correct answers)
(1/1) Points
System delivery occurs, and the project commences
*Details about the customer are determined and documented (*)
*The EIS Site-Audit is scheduled (*)
*Details about the project are identified and documented, for example, is
this a single system installation or a complex, multi-product installation (*)
58. Which two EIS documents are most useful during the Installation and
Configuration of Oracle Hardware and Software step?
(Choose all correct answers)
(1/1) Points
*EIS Checklist (*)
Site-Audit Report
DVD
Operational Handover Agreement
*Installation Configuration Plan (*)
Correct!
59. Why should you use the EIS methodology to guide your installation
process?
(1/1) Points
The EIS methodology provides a 20% discount on Support Services if you
install your customers’ hardware or software using it
*Using the proven EIS methodology will provide step-by-step installation
guidelines, help guarantee a quality installation, make your life easier, and
ensure customer satisfaction (*)
Installation processes are very lengthy, the EIS methodology is quick and
dirty
Larry Ellison has mandated using EIS
Correct!
60. What are three items in the EIS Site-Audit Report are documented for all
Oracle hardware?
(Choose all correct answers)
(1/1) Points
*Facility Power requirements (*)
IP Address requirements
Operating System requirements
*Access Route requirements (*)
*Operating Environment and Cooling requirements (*)
Correct!
Previous Page 12 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
62. What four tasks are typically happening at the EIS Planning and
Preparation stage in the installation process?
(Choose all correct answers)
(1/1) Points
*Begin work on Project Schedule (*)
*Identify Installation team – Oracle Installation Coordinator, Project
Manager, Customer Point of Contact, others as needed (*)
*Compile EIS planning documents (*)
Unpack and power ON systems
*Notification of Customer Installation project (*)
Cable and install systems into custom rack
Correct!
63. Which four objectives are primary goals for an EIS Site Audit?
(Choose all correct answers)
(1/1) Points
*Determine installation needs for the System, including such assessments
as: the suitability of access routes to the installation location, such as doors,
elevators, floor strengths and ramps (*)
*Determine the environmental conditions at Customer's site including
temperature, humidity, cleanliness and such other assessments as are
determined to be necessary in Oracle's sole discretion (*)
*Determine the floor weight load capacity at the location where the System
will be installed (*)
*Determine the availability of required electrical power to run and maintain
the System (*)
Determine how frequently system backups will be completed
Determine how many logical domains need to be configured on the system
Correct!
64. What is the primary goal of the Installation and Configuration of Oracle
Hardware and Software step in the EIS methodology?
(1/1) Points
Troubleshooting software configuration issues
Managing transition from Installation phase to Field Service issue recording
65. For safety awareness with respect to grounding, if a system has been
modified after the manufacturer's assembly process, what three
recommendations does the EIS Grounding Standard make?
(Choose all correct answers)
(1/1) Points
*If modifications involved any power supplies, distribution units or wiring,
did qualified personnel verify that the modification was was correct and did
they test the system to ensure that it doesn't pose any safety hazard? (*)
Determine whether the local electrician can support the installation process
*If qualified personnel did not test the safety of the modified system then
proper testing should be requested before Oracle and/or partner personnel
will work on the equipment (*)
*Check whether the modification involved any power supplies, distribution
units or wiring? (*)
If the temperature is below 60 degrees F., warm the room first before power
ON
Correct!
Previous Page 13 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Correct!
67. What are two activities that take place during the System Test step of
the EIS methodology?
(Choose all correct answers)
(1/1) Points
*On Solaris-based systems, Oracle's Explorer Data Collector will be run and
the results evaluated with ORAS/CLI from the EIS-DVD (*)
Application installation, configuration, and testing
Electrical grounding and environmental assessment
*Tests specified in the Test Procedures Plan Plan will be carried
performed (*)
Correct!
69. What if the customer has their own labeling methodology that differs
from the recommended one from EIS?
(1/1) Points
Submit a Service Request for Oracle approval on use of the customer
labeling and routing methods
Ignore the customer’s standard and use the EIS standard
*Follow the customer's standard for cable labeling provided it meets with
EIS requirements for identification and port location. (*)
Redo cabling throughout the datacenter to meet the EIS standard
Correct!
70. Why do the EIS Standards recommend that external cables between
Oracle hardware, such as servers, storage devices, network devices and
ports be clearly labeled?
(1/1) Points
Service requests for field diagnostics will not be accepted unless cables are
labeled
*For ease of maintenance it should be unambiguously clear from the label on
each cable, where the cable has to be attached (*)
Labeling is not an EIS best practice
Cable routing should be done with rubber bands for ease of reconfiguration
Correct!
Previous Page 14 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Correct!
73. Why is the rate of temperature change when acclimatizing systems such
an important factor as described in the EIS methodology?
(1/1) Points
Systems should be warmed up and powered ON as quickly as possible to
optimize the installation project timeline
*Variations in temperature should not exceed the approved gradient of
approximately 2° C (4° F) per hour, because ignoring this may could lead to
long-term damage (hair-cracks) on the boards (*)
It is actually not relevant or important
Variations in temperature do not have as big an impact as do Service
contract considerations for how long an installation will take
Correct!
75. What are three factors that influence how long a system (server,
storage, engineered system) will require to be acclimatized after delivery to
a customer, before power can be applied without causing damage?
(Choose all correct answers)
(1/1) Points
*temperature (*)
*humidity (*)
timezone
data center space
*cleanliness (*)
Correct!
Previous Page 15 of 24 Next
Test: Oracle Exadata Hardware Installation & Software
Configuration Online Assessment (2021)
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
77. Name two functions for the EIS-DVD during the Installation and
Configuration of Oracle Hardware and Software step in the EIS
methodology?
(Choose all correct answers)
(1/1) Points
Provides an excellent tool as a leave behind utility for customers
Used as a back-up for complete documentation sets that are on
http://docs.oracle.com
*Contains required patches and firmware for most installations (*)
*Provides installation assessment and diagnostic tools (*)
Correct!
78. According to the EIS methodology, when issues are uncovered during
the Site-Audit, who should be notified?
(Choose all correct answers)
(1/1) Points
Oracle Premier Support
*Installation coordinator if applicable (*)
Oracle sales management
*Customer point of contact (*)
Correct!
82. Why should you typically complete the Installation Configuration Plan
and create your Test Procedures Plan at the same time?
(1/1) Points
You should create the Test Procedures Plan after you have completed the
system installation and configuration.
Test Procedures plan is a standard document used in all generic system
installations.
*As you work through the system configuration process with your customer,
you should state how you will test key items in the system’s configuration
for having been successfully completed. (*)
Correct!
83. Which four documents are included as part of the Operational Handover?
(Choose all correct answers)
(1/1) Points
*Installation and Configuration Plan (*)
EIS Checklist for the System installed
*System Documentation (*)
*Site Audit Report (*)
*Test Procedures Plan (*)
MOS Internal Documentation
Correct!
OVM Overview
(Answer all questions in this section)
84. What is the Xen Hypervisor responsible for in virtualization?
(Choose all correct answers)
(0/1) Points
Guest Domain Management
Virtual Hardware presentation to guest domains
Memory Management (*)
Interrupt Handling (*)
CPU Scheduling (*)
Incorrect! Please review the course "Exadata Software Architecture and OVM Overview"
content and try again.
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
OVM Overview
(Answer all questions in this section)
86. What version of Linux is deployed on dom0?
(0/1) Points
Linux 6 (*)
Linux 5
Linux 4
Linux 5 or Linux 6 can be installed
Linux 7
Incorrect! Please review the course "Exadata Software Architecture and OVM Overview"
content and try again.
87. What is the difference between domU and dom0? Select the answers
that best apply.
(Choose all correct answers)
(0/1) Points
domU is the guest domain (*)
domU runs the database (*)
dom0 is the management domain (*)
domU is the control domain
dom0 houses the grid infrastructure software
Incorrect! Please review the course "Exadata Software Architecture and OVM Overview"
content and try again.
Exadata Hardware Installation
(Answer all questions in this section)
88. What does NVMe stand for?
(1/1) Points
*Non Volatile Memory Express (*)
Non Volatile Maximum Energy
Nu Vios Maximum Express
Nu Vios Memory Express
Correct !
89. What are the elastic configuration options for a customer currently
running Solaris on Exadata?
(1/1) Points
The customer may configure non-Solaris VMs and run elastic config on the
Virtual Machines
Solaris has never been supported on Exadata
*None. Elastic config requires 12.1.2.1 and Solaris is not supported (*)
The customer can upgrade to the latest software release and run Solaris in
an Elastic Configuration
Correct !
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
99. What are the two types of storage servers used in the Exadata X7-2
hardware?
(Choose all correct answers)
(1/1) Points
*Extreme Flash (*)
*High Capacity (*)
High Performance
Extreme Performance
Correct !
100. If the customer does not have easy access to the server and/or cannot
visibly report on the status of the LED indicator, what tools can be used to
view this information remotely?
(Choose all correct answers)
(1/1) Points
*ILOM CLI (*)
DBMCLI
*IPMITOOL (*)
EMCLI
Correct !
Previous Page 20 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
103. What is the most common resource to find data about common
customer hardware issues?
(1/1) Points
*Oracle System Handbook (*)
Service Request Recap PDF
MOS SR Report
Sun Hardware Issue Handbook
Correct !
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
107. Select the true statement about the network for the Exadata X7-2
hardware.
(1/1) Points
The infiniband switches have been replaced with spine switches for faster
internal connectivity
*The 40Gb Infiniband can be configured active-active for a throughput of
80Gb (*)
1Gb Ethernet data center connectivity is no longer avaialble
The infiniband has been updated to active-active 80GB internal connectivity
for a throughput of 160Gb
Correct !
Exadata X9M TOI - Hardware Overview Assessment
(Answer all questions in this section)
108. Which two of the following are true, in respect to how Linux Ethernet
device enumeration occurs between the three Exadata X9M PCIe slots?
Select two answers.
(Choose all correct answers)
(0/1) Points
The dual-port SFP28 25Gb ports are enumerated from top-to-bottom when
installed in an X9M-8, and right-to-left when installed in an X9M-2. (*)
The quad-port RJ45 10Gb ports are enumerated from top-to-bottom, right-
to-left when installed in an X9M-2.
The devices for PCIe slots 1 through 3 will be in a mixed enumeration,
depending on what dual-port SFP28 25Gb and quad-port RJ45 10Gb cards
are selected, and how they are mixed-and-matched between the slots.
The devices are always enumerated with eth1 – eth4, for PCIe slot 1
network ports, eth5 – eth8, for PCIe slot2 ports, and eth9 – eth12 for PCIe
slot3 ports. (*)
Incorrect! Please review the course content and try again.
109. Which of the following are true for the Exadata X9M Storage Servers?
Select all that apply.
(Choose all correct answers)
(0/1) Points
NVMe flash – F320v3 (capacity – 3.2 TB)
Contains 36-core Ice Lake Intel processors
Persistent memory – Intel Optane PMem Series 200 (same capacity – 1.5
TB) (*)
All of the above
Contains new DDR4-3200 memory, in increased capacity of 256GB (*)
Incorrect! Please review the course content and try again.
110. On an Exadata X9M multi-rack, the RoCE leaf interlinks have increased
from four to seven when compared to the X8M.
(1/1) Points
True (*)
False
Correct !
Previous Page 22 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Exadata X9M TOI - Hardware Overview Assessment
(Answer all questions in this section)
111. The Exadata or ZDLRA X9M platforms allow RoCE Fabric Switches to be
replaced from the front of the rack.
(1/1) Points
False
True (*)
Correct !
112. What is the primary reason the X9M racks now use standard-length 3
meter cables, versus the mixed-length cables on previous platforms?
(1/1) Points
Because having extra slack of power cables, in the side-panels and rear of
the cabinet, is attractive.
Higher power draw of X9 servers required more flexibility in PDU group
balancing, resulting in the need to increase from 2M to 3M. (*)
The extra cable length is required to attach to the neighboring rack.
Correct !
113. Like the Exadata X8M, the Exadata X9M platform database servers
contain two onboard SFP28 and RJ45 ports, giving customers the choice
between either pair.
(0/1) Points
False (*)
True
Incorrect! Please review the course content and try again.
114. The Exadata X9M platform increases the RDMA Network Fabric speeds
from 100 Gb/s to 200 Gb/s.
(0/1) Points
False (*)
True
Incorrect! Please review the course content and try again.
115. 1. Which of the following are true of the Exadata X9M Database Server?
Select all that apply.
(0/1) Points
Contains 32-core Ice Lake Intel processors
All of the above (*)
Increased Memory Capacity – 512 GB standard, 1 TB, and 2 TB-DDR4-
3200MT/s
2x 3.84 TB NVMe Disks expandable to 4x 3.84 TB NVMe Disks
Based on PCIe Gen4 architecture
Incorrect! Please review the course content and try again.
Previous Page 23 of 24 Next
Review your answers, feedback, and question scores below. An asterisk (*)
indicates a correct answer.
Exadata Software
(Answer all questions in this section)
116. Select the true statements about Elastic Configuration
(Choose all correct answers)
(0/1) Points
Elastic configuration references IP addresses duing server startup (*)
Elastic configuration refers to the ability to add non-Exadata storage cells to
the existing configuration
Elastic configuration refers to a database machine that is not a standard rack
configuration (*)
Elastic configuration refers to the ability to upgrade online and add servers
without taking an outage
Incorrect! Please review the course "Exadata Software Architecture and OVM Overview"
content and try again.
119. What service is replaced by init in the way services get started now?
(1/1) Points
initstart
mount -d
upstart (*)
fstab
Correct !
120. Select the operating system that replaced the Solaris software stack
(0/1) Points
VMWare
Linux
Ubuntu
CentOS
OVM (*)
Incorrect! Please review the course "Exadata Software Architecture and OVM Overview"
content and try again.
Previous Page 24 of 24