Professional Documents
Culture Documents
Transformer STP 05
Transformer STP 05
Content
1.0 OBJECTIVE
1
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 2 of 24
Main Contractor Zasco Date
1.0 Objective
1.1 This document defines the specific procedure and report structure for the Site Acceptance
Tests for the Main Transformer.
1.2 The aim of this Site Acceptance Tests is to ascertain the healthiness of the equipment and
demonstrate adherence to the technical specifications.
1.3 This document covers the tests of the stand-alone equipment only. The integral system tests
with remote interfaces are to be done along with the checks of the respective protection and
control schematic drawings.
5 FAT Report.
2
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 3 of 24
Main Contractor Zasco Date
Serial No.
Number of phases 3
Rated Frequency 50
Number of windings 3
No. of taps 21
3
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 4 of 24
Main Contractor Zasco Date
Type of
SN Description Result Remark
Check
1 Name plate information on a visible location Visual (OK/Not OK)
2 Earthing system connections check Visual (OK Not OK)
Bushings check for the soundness of porcelain and
3 sealing Visual (OK/Not OK)
4 Silica gel quantity and color checks Visual (OK/Not OK)
5 Piping installation of Buchholz relay checks Visual (OK/Not OK)
Check CT lugs/wire as per schematic Continuity
6 (OK/Not OK)
diagram and tightness Check
Conformity of power/control cable and
7 identification labels Visual (OK/Not OK)
Check the power/control cable connection
8 Visual (OK/Not OK)
Cable tightness and paint marking
9 Visual (OK/Not OK)
Check all component labels are fitted
10 Visual (OK/Not OK)
Check of Transformer Painting
11 Visual (OK/Not OK)
Cleaning inside the control panel and around the
12 Visual (OK/Not OK)
transformer
Check installation of mechanical protection devices
Visual (OK Not OK)
Main Tank Buchholz Relay
Visual (OK Not OK)
Main Tank Pressure Relief
Visual (OK Not OK)
OLTC Buchholz Relay
Visual (OK Not OK)
OLTC Pressure Relief
Visual (OK Not OK)
13 Main Tank Conservator
Visual (OK Not OK)
OLTC Conservator
Visual (OK Not OK)
WTI and OTI
Visual (OK Not OK)
OLTC surge
Visual (OK Not OK)
Sudden pressure relay
Visual (OK Not OK)
4
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 5 of 24
Main Contractor Zasco Date
5
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 6 of 24
Main Contractor Zasco Date
Test Setup:
A. Test Procedure:
- Isolate primary/secondary/neutral earth.
- Connect the circuit as shown in the above diagram.
- The deviation of the measurement over time during the period of charging the winding.
- The testing kit will automatically perform a discharging of the winding after
saving the measurement.
- By injecting a citrine value of current and measuring the voltage drop across the windings
- Calculate the winding resistance that under test.
- Repeat the test for all taps of the transformer.
6
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 7 of 24
Main Contractor Zasco Date
B. Test Results:
LV
r-n y-n b-n
TV
r-y y-b b-r
Note:
Resistance at R75 = Rt (235+75)/(235+t)
Where, R75: Resistance at 75°C (Ω)
Rt: Resistance at winding temperature t
7
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 8 of 24
Main Contractor Zasco Date
8
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 9 of 24
Main Contractor Zasco Date
9
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 10 of 24
Main Contractor Zasco Date
From the measured voltages check the following conditions for YNyn0.
VR-N = VR-n + VN-n
10
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 11 of 24
Main Contractor Zasco Date
B. Test Procedure:
- Isolate primary/secondary/neutral earth.
- Open all the Three Phases on the LV side of the transformer
- Apply 3 Phase voltage in the HV, measure for the main tap.
- Measure the Current in all three Phases
11
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 12 of 24
Main Contractor Zasco Date
Applied Voltage AI PI
Configuration (Volts) R15 R30 R60 R60/R15 R600/R60
HV – (LV +TV+ Ground) 5000
LV – (HV +TV+ Ground) 1000
TV – (HV +LV+ Ground) 1000
Core - (Ground+Clamping N/A N/A
Frame) 2500
Clamping Frame - (Core + 2500
Ground)
12
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 13 of 24
Main Contractor Zasco Date
13
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 14 of 24
Main Contractor Zasco Date
Test Procedure
- Check the Core to be measured
- Say Typical X – Y(X is value to be checked, Y is against which value to be checked).
- Connect X to - ve Terminal of Megger
- Connect Y to + ve Terminal of Megger
- Select the Voltage Rating of Megger
- Operate the Megger and record Values
14
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 15 of 24
Main Contractor Zasco Date
C. Polarity Test:
(P1 towards (+) ve & P2 towards (-) ve
Test Procedure
- Do the connection as shown fig.
- Isolate primary, secondary & Neutral earth.
- Switch on the kit
- Select the current transformer page
- Connect the Primary and Secondary leads properly.
- Pressing the start button, the test card displays.
- If Polarity is wrong it displays Polarity reversed otherwise it displays OK
- Do the same for all other cores
D. CT Winding Resistance:
Test Procedure
- Isolate primary, secondary & Neutral earth.
- Switch on the kit
- Select the current transformer page
- Pressing the start button, the test card displays
- The deviation of the measurement over time during the period of charging the winding
- The Kit will automatically perform a discharging of winding after saving the measurement
- Measures the DC Voltage
- Measures the Resistance
15
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 16 of 24
Main Contractor Zasco Date
Test Procedure
- Do the connection as shown fig.
- Isolate primary/ secondary / Neutral earth.
- Switch on the kit
- Select the current transformer page
- After entering the current and voltage limits and pressing the start button
- Carry out the test.
- The knee point will be automatically calculated by the kit.
- After test an automatic sequence of demagnetization is performed.
- The test is done using a regulated voltage source.
- Do the same for all other cores.
F. CT Ratio Test:
Test Procedure
17
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 18 of 24
Main Contractor Zasco Date
B. General Check:
SN Description Confirmation Remarks
1 Local operation possible when selector s/w in local position (OK / NOT OK)
2 Remote operation not possible when selector s/w in local position (OK / NOT OK)
3 Handle interlock (OK / NOT OK)
4 End limit switches (OK / NOT OK)
5 Step by step operation (OK / NOT OK)
6 Tap position indication in in Tap Local Panel (OK / NOT OK)
7 Local operation is not possible when selector s/w in Remote position (OK / NOT OK)
8 Remote operation is possible when selector s/w in Remote position (OK / NOT OK)
9 Starting current of motor (OK / NOT OK)
10 Running current of motor (OK / NOT OK)
11 Contacts for all alarm/indication circuits (OK / NOT OK)
12 IR value of motor (OK / NOT OK)
13 Lighting and heater controls (operation of door switch, thermostat etc.) (OK / NOT OK)
14 OLTC counter operation (OK / NOT OK)
C. Operation Test:
SN Test Items and Procedure Test Result
Operate by a manual operation and confirm the rotation direction.
1 Rotation direction : “Raise” --- tap 1→Tap 17, “Lower” --- tap 17→Tap 1
Confirm that the tap position of the OLTC and motor drive mechanism indicate same tap No. at
2 several tap positions.
3 Check no abnormal noise from bearings, gears and others during manual tap changing operation
Check the number of turn from the diverter switch action point to the definite operating position
for “Raise” and “Lower” direction.
4
“Raise” direction: turns “Lower” direction: turns
(Difference of turns for both direction should be within 2 turns.)
Operate by a motor drive operation and confirm the rotation direction at several taps from
6 middle tap position to “Raise” and “Lower” direction.
Check no abnormal noise from bearings, gears and others during motor drive tap changing
7
operation
Check the operation of the safety switch.
8 Depress the control switch with the crank handle mounted condition, and confirm that the motor
circuit is open-circuited.
After satisfied above check, operate by a motor drive operation for one complete operating
9 cycle.
18
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 19 of 24
Main Contractor Zasco Date
19
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 20 of 24
Main Contractor Zasco Date
20
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 21 of 24
Main Contractor Zasco Date
- Note:
- Verification the calibration at different levels of temperatures such as 0%, 25%, 50%, 75%
and 100% of temperature transmitter range.
- Test records shall include temperature reading from oil bath, reading from local indicator,
reading from remote, % error
22
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 23 of 24
Main Contractor Zasco Date
23
Power Transformer Site Acceptance Test Procedures
Project Hiswa – Mansoura – Khor Maksar S/S Report No
Owner Petro Masila Page No. Page 24 of 24
Main Contractor Zasco Date
24