PILING INSPECTION CHECKLIST

Location: Company: Date/Time:

Please tick () where applicable. Day-1 Day2- Day-3 Day-4 Day-5 Day-6 Day-7
1. Safe Work Method Statement briefed & signed
2. Work area barricaded with warning signs displayed.
3. Piing machine are placed on a safe and sound foundation ground
4. All openings left by piling operations are properly barricaded
5. Sides of excavation to be made safe by shoring, stepping or others.
6. Open cut slope are covered with concrete or water proof cover.
7. Workers and operators are provided with appropriate PPE's (ear plug)
8. Piling equipment is inspected by operator before use
9. Crane operator and rigger is appointed and competent
10. Proper collection / Discharge of sludge system provided
Others (please specify):

Inspected by(Subcontractor supervisor in charge):

(name) (sign) (date/time)


Verified by(Hexacon Trade in charge):

(name) (sign) (date/time)