You are on page 1of 4

MIDTERM PROJECT MANAGEMENT RISK

RISK MANAGEMENT Risk that must be insured

 In project management, risk management is  Statutory requirement


the practice of identifying, evaluating, and  Contractual requirement
preventing or mitigating risks to a project that
Risk that can be insured if required
have the potential to impact the desired
outcomes.  Management choice
 Project managers are typically responsible for
overseeing the risk management process Risk that are difficult or impossible to insure
throughout the duration of a given project.  The contractor or the customer must accept
the risk.
 Cost: The risk of events that impact the
budget, especially those that cause the CRITICAL PATH METHOD (CPM)
project to be completed over budget. Errors in
The critical path method (CPM) is a technique that’s
cost estimation commonly generate risk in
used by project managers to create a project schedule
addition to external factors.
and estimate the total duration of a project.
 Schedule: The risk of unplanned scheduling
conflicts, such as events that cause the project In project management, the critical path is the longest
to be delayed. Scope creep is a common sequence of tasks that must be completed to
reason for scheduling issues and project complete a project. The tasks on the critical path are
delays. called critical activities because if they’re delayed, the
 Performance: The risk of events that cause whole project completion will be delayed.
the project to produce results that are
Finding the critical path is very important for project
inconsistent with the project specifications.
managers because it allows them to:
METHODS DEALING WITH RISKS
 Accurately estimate the total project duration.
Avoid the risk – The only way to avoid a risk is to  Identify task dependencies, resource
abandon the possible causes, which could even mean constraints and project risks.
deciding not to undertake a project at all.  Prioritize tasks and create realistic project
schedules.
Take precautions to prevent or mitigate risk impact –
requiring the active participation of all managers and ALGORITHM
staff. It needs high-level risk prevention strategy
A process or set of rules to be followed in calculations
combined with executive determination to ensure
or other problem-solving operations, especially by a
that all preventive measures are always followed
computer.
throughout all parts of the organization.
CPM IMPONTANCE
Accept the risk– Rain might make the day chosen for
office relocation miserable for all concerned but the Projects are made up of tasks that have to adhere to a
risk would have to be accepted. schedule in order to meet a timeline.

Share the risk– If a project, or a substantial part of it, ● It sounds simple, but without mapping the work,
appears to carry very high risk, the contractor might your project scope can quickly get out of hand and
seek one or more partners to undertake the work as a you’ll find your project off track.
joint venture.
● Using the critical path method is important when
Limit the risk – There are occasions when project risks managing a project because it identifies all the tasks
should only be accepted with safeguards in place to needed to complete the project, then determines the
limit their potential effect. tasks that must be done on time, those that can be
delayed if needed and how much float or slack you
Transfer the risk – Some risks, or substantial parts of
have.
them, can be transferred to another party on payment
of a fee or premium. This leads to the important
subject of insurance.
When done properly, critical path analysis can help ● We can also identify task dependencies between
you: the critical path activities, and also between activities
(A, F and G) or (A, H and E), which are parallel tasks.
 Identify task dependencies, resource
constraints and project risks. PROJECT EVALUATION REVIEW TECHNIQUE (PERT)
 Accurately estimate the duration of each task.
is used to identify the time it takes to finish a
 Prioritize tasks based on their float or slack
particular task or activity.
time, which helps with project scheduling and
resource allocation.  It is a system that helps in the proper
 Identify critical tasks that have no slack and scheduling and coordination of all tasks
make sure those are completed on time. throughout a project.
 Monitor your project progress and measure  It also helps in keeping track of the progress,
schedule variance. or lack thereof, of the overall project.
 Use schedule compression techniques like
crash duration or fast tracking.

CPM KEY ELEMENTS

Earliest start time (ES): This is simply the earliest time


that a task can be started in your project. You cannot
determine this without first knowing if there are any
task dependencies.

Latest start time (LS): This is the very last minute in


which you can start a task before it threatens to delay
 Knowing the time, it should take to execute a
your project schedule.
project is crucial, as it helps project managers
Earliest finish time (EF): The earliest an activity can be decide on other factors such as the budget
completed, based on its duration and its earliest start and task delegation
time.  No matter how big or small a project is,
estimates can be too optimistic or pessimistic,
Latest finish time (LF): The latest an activity can be but using a PERT chart will help determine
completed, based on its duration and its latest start realistic estimates.
time.
There are four definitions of time used to estimate
Float: Also known as slack, float is a term that project time requirements:
describes how long you can delay a task before it
impacts its task sequence and the project schedule. Optimistic time – The least amount of time it can take
The tasks on the critical path have zero float, because to complete a task
they can’t be delayed.
Pessimistic time – The maximum amount of time it
should take to complete a task

Most likely time – Assuming there are no problems,


the best or most reasonable estimate of how long it
should take to complete a task.

Expected time – Assuming there are problems, the


best estimate of how much time will be required to
complete a task.
Project activities are represented by letters and the
critical path is highlighted in green. CREATING A PERT CHART

● Tasks F, G and H are non-critical activities with float  A flowchart is used to depict the Project
or slack. Evaluation Review Technique.
 Nodes represent the events, indicating the
start or end of activities or tasks.
 The directorial lines indicate the tasks that estimating a budget consists of analyzing an already
need to be completed, and the arrows show completed project with a similar scope to the current
the sequence of the activities. one and using its budgeting calculations.

● primarily using a fully-furnished past project as a


blueprint for the current one.
Here are several terms used in a PERT chart:
● Even though certain qualitative and quantitative
Float/Slack – Refers to the amount of time a task can
parameters may alter, inspiration can be drawn from
be delayed without resulting in an overall delay in
some of your best work from the past.
completion of other tasks or the project
● In the cases wherein data and information are
Critical Path – Indicates the longest possible
lacking and your client needs a budget estimate
continuous path from the start to the end of a task or
beforehand, analyzing data into quantifiable variables
event
analogous to previous projects can help you develop
Critical Path Activity – Refers to an activity without scopes for your current project.
any slack
PARAMETRIC ESTIMATING
Lead Time – Refers to the amount of time needed to
consists of using historical data and other related
finish a task without affecting subsequent tasks
variables for estimating the project's scope, duration
Lag Time – The earliest time by which a successor and total costs.
event/task can follow a prior event/task
● Even though the odds of having two projects that
Fast Tracking – Refers to handling tasks or activities in are similar in size, as well as high levels of complexity,
parallel are high, parametric estimating seems to be more
viable.
Crashing Critical Path – Shortening the amount of time
to do a critical task ● Parametric estimating is a more specific type of
analogous estimating, adjusted for its advanced
GANTT CHART precise accuracy which can be accounted for by the
A Gantt chart is a popular project management tool availability of data and is primarily based on unit rates
that aids in planning and scheduling projects of all per activity.
sizes. It provides a visual representation of the TOP-DOWN ESTIMATING
project’s timeline and assists project managers,
stakeholders, and team members in understanding: consists of looking at the project budget in its entirety
and then calculating individual costs for each of the
 A project’s roadmap required processes.
 Task progress
 Key milestones ● A very logical deduction of budget estimation, the
 Work dependencies top-down method, requires the project manager to
 Resources required make a rough framework of all the possible individual
 Risks involved stages and make a rough estimate of the costs
 A Gantt chart, like most charts, has two axes. involved.
The horizontal axis represents the timeline for ● The next step is to research to educate oneself
all project tasks. about market rates per activity.
 On the other hand, the vertical axis lists the
activities or tasks that must be completed to ● Once calculated, the total costs per stage will then
finish the project. be compared to the rough estimation of costs, and
necessary changes will be made to make the process
BUDGET MANAGEMENT more cost-effective.
 is the art of planning and controlling how money is BOTTOM-UP ESTIMATING
spent and saved
divides the project into multiple processes and
6 PROJECT MANAGEMENT BUDGETTING METHODS calculates the individual costs for each. And, project
ANALOGOUS ESTIMATING
manager attempts to directly generate a total project
budget.

● Contrary to the previous method, bottom-up


estimating is based on the integration of all costs
concerning all the basic units of the processes to find
the overall costs by drawing in variables like the
required time for project completion, the number of
laborers, etc.

● The authenticity of cost information is directly


proportional to the final estimation of the budget
before you hand over the information to your client.

THREE-POINT ESTIMATING

uses three different calculations to estimate a budget:


the most expensive scenario, the most cost-effective
scenario and the scenario that's most likely to occur.

● This method is used especially when there is very


limited data.

● Since the margin of error is astronomical, three-


point estimating allows one to ruminate on risk
factors.

● It is quite mathematical and uses probability


calculation to measure the probability of a most likely
outcome, the pessimistic estimate, and the optimistic
estimate.

● The pessimistic estimate is the amount of work


needed to complete the project if risks and negative
conditions factor in whereas an optimistic estimate is
the amount of work needed to ensure project
completion without any risk hindering its progress.

EARNED VALUE ANALYSIS

a way of estimating the accuracy of a project's budget


during the execution of the project.

● Earned Value Analysis comes into effect once the


project work commences.

● It is done to analyze the real value and ideal value of


costs at all stages of the project.

● This produces a broad range of working knowledge


for the future and a better understanding of risk
assessment and management.

You might also like